This is a technical specification document for motor control centers (MCCs) prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 at Ephrata Borough Authority in Pennsylvania. The specification details the requirements for supplying and installing motor control centers as part of the electrical construction contract (EBA26-3). The MCCs must comply with NEMA ICS 2 Class II Type BT standards, feature a 480-volt three-phase four-wire 60 Hertz configuration, and achieve a 65,000-ampere short circuit rating. The units shall be fabricated by approved manufacturers including Schneider Electric (Square D) Model 6, Eaton, or equivalent, with dimensions of approximately 20 inches deep, 72 inches of unit mounting space, and 90 inches overall height. Installation must occur on raised concrete housekeeping pads, include manufacturer supervision, and comply with all field testing and inspection requirements outlined in Section 26 08 00 - Electrical Field Acceptance Tests. Bids for the overall Biosolids Project are due December 8, 2026 at 10:00 AM local time through PennBid, with a pre-bid open house scheduled for November 18, 2026 from 8:00 AM to 10:00 AM.

The specification requires extensive submittals including shop drawings, test reports, as-built wiring diagrams, and manufacturer installation instructions. The contractor must furnish comprehensive spare parts and extra materials, including multiple control power fuses, starter contacts and coils, pilot lights in various colors, control relays, circuit breakers, and corrugated switchboard matting up to 200 linear feet. All terminals must have a minimum 75-degree Celsius temperature rating, and the motor control centers must be equipped with arc-flash hazard reduction technology to achieve Risk/Hazard Category 2 per NFPA 70.110.16 and NFPA 70E. The specification emphasizes quality assurance through NEMA ICS 2.3 compliance, Underwriters Laboratories listing, and rigorous field inspection including infrared thermograph scanning of all power connections and breakers under near-full-load conditions. Pricing information, set-asides, and funding sources are not specified in this technical document.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

26 24 19 – MOTOR CONTROL CENTERS

Herbert, Rowland & Grubic, Inc. 26 24 19 - 1 011139.0465

SECTION 26 24 19 - MOTOR CONTROL CENTERS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Motor control centers.

1.2 RELATED SECTIONS

A. Division 03.

B. Division 26.

C. Division 40.

D. 40 95 13 – Process Control Panels and Hardware.

1.3 REFERENCES

A. NFPA 70 - National Electrical Code.

B. UL 198C - High-Interrupting Capacity Fuses; Current Limiting Type.

C. UL 198E - Class R Fuses.

D. NEMA AB 1 - Molded Case Circuit Breakers.

E. NEMA ICS 2 - Industrial Control Devices, Controllers, and Assemblies.

F. NEMA ICS 2.3 - Instructions for the Handling, Installation, Operation, and Maintenance of Motor Control Centers.

G. NEMA ICS 2 - Industrial Control Devices Controllers and Assemblies

1.4 SUBMITTALS

A. Submit under provisions of Sections 01 30 00 – Submittal Procedures and 26 05 00 - Electrical General.

B. Shop Drawings - Include front and side views of enclosures with overall dimensions shown; conduit entrance locations and requirements; nameplate legends; size and number of bus bars per phase, short circuit bracing, neutral, and ground; electrical characteristics including voltage, frame size and trip ratings, withstand ratings, and time/current curves of all equipment and components; factory elementaries for each compartment; motor control centers structures; and motor control center layout diagrams.

Herbert, Rowland & Grubic, Inc. 26 24 19 - 2 011139.0465

C. Samples shall be submitted as may be requested by the Engineer. Any samples requested will be returned.

D. Test Reports - Indicate field test and inspection procedures and test results.

E. The Contractor shall furnish a reproducible copy and four prints of the approved as-built wiring diagrams showing all wiring in the motor control center. See Section 26 05 00 – Electrical General, for final construction record drawing requirements.

F. Manufacturer's Installation Instructions - Indicate application conditions and limitations of use stipulated by product testing agency specified under Article 1.08. Include instructions for storage, handling, protection, examination, preparation, installation, and starting of product.

1.5 OPERATION AND MAINTENANCE DATA

A. Submit under provisions of 01 78 39 – Project Record Documents and 26 05 00 – Electrical General.

B. Maintenance Data - Include spare parts data listing; source and current prices of replacement parts and supplies; and recommended manufacturer maintenance procedures and intervals.

1.6 QUALITY ASSURANCE

A. Perform work in accordance with NEMA ICS 2.3.

1.7 QUALIFICATIONS

A. Manufacturer - Company specializing in manufacturing the products specified in this section with minimum 10 years' experience.

1.8 REGULATORY REQUIREMENTS

A. Conform to requirements of NFPA 70, Underwriters Laboratories Publication UL-845, and NEMA Publication ICS 2.

B. Furnish products listed and classified by Underwriters Laboratories, Inc. as suitable for purpose specified and indicated.

1.9 DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, provide protection, and handle products to and at the site under provisions of 01 61 00 – Product Requirements, and 26 05 00 – Electrical General.

B. Deliver in 60-inch maximum width shipping splits, individually wrapped for protection, and mounted on shipping skids.

Herbert, Rowland & Grubic, Inc. 26 24 19 - 3 011139.0465

C. Store in a clean, dry, heated and air conditioned space. Maintain factory wrapping or provide an additional heavy canvas or heavy plastic cover to protect units from dirt, water, construction debris, and traffic. Do not store outside.

D. Handle in accordance with NEMA ICS 2.3. Lift only with lugs provided for the purpose.

Handle carefully to avoid damage to motor control center components, enclosure, and finish.

E. MCC sections shall be internally braced to allow the shipping splits to be laid on their sides to move units through doors.

1.10 ENVIRONMENTAL REQUIREMENTS

A. Conform to NEMA ICS 2 service conditions during and after installation of motor control centers.

1.11 FIELD MEASUREMENTS

A. Verify field measurements are as indicated on shop drawings and the unit fits into the space shown on the Contract Drawings.

B. Coordinate the locations and sizing of housekeeping pads. Pads shall be large enough to accommodate future sections.

1.12 ARC FLASH

A. Provide a motor control center that has been equipped by the manufacturer with a technology to reduce to arc-flash incident energy to arc-flash Risk/Hazard Category 2.

1.13 EXTRA MATERIALS

A. Furnish under provisions of 01 61 00 – Record Documents, and 26 05 00 – Electrical- General.

B. Provide the following materials, each tagged or conspicuously marked or labeled with the manufacturer's name, part number and name. All parts shall appear on a typed list showing the above plus quantity and location.

1. One box (minimum 10) of each size control power fuses furnished.

2. One set of starter contacts for every two starters or fraction thereof of each

NEMA size installed.

3. One starter coil for every five NEMA size starters installed. (All starters are full sized NEMA.)

4. One control power transformer (CPT) for each size installed.

5. Indicating Pilot Lights, LED Type - 12 red, 12 amber, 2 green, 2 blue, and 2 white.

6. Two control relays, timing relays and motor timing relays of each type used.

7. Six sets of control relay contacts.

8. Six sets of each N.O. and N.C. starter auxiliary contacts for each size starter provided.

Herbert, Rowland & Grubic, Inc. 26 24 19 - 4 011139.0465

9. Two NEMA Size 1 starters.

10. One 3-amp frame MCP.

11. One 15-amp frame MCP.

12. Lamp replacer tool.

13. One fuse puller for each MCC, new or modified.

14. 36-inch wide, 1/4-inch thick corrugated switchboard matting. A total length of up to 200 lineal feet shall be provided. Matting will be installed in front of all new and existing interior electrical equipment as designated by the Engineer. Shall comply with ANSI/ASTM D178 J6-7 Type 2, Class 2 specifications. Available Lab Safety Supply (1 800 356 0783).

15. Two metal storage cabinets 36 inches wide by 20 inches deep by 78 inches high with doors. Cabinet shall be welded, 12 gauge steel construction, three-point locking mechanism, with four fully adjustable shelves. Grainger Stock No. 5ZH07, Stronghold Model 36 204, or equal.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Schneider Electric (Square D) - Model 6.

B. Eaton.

C. Or Approved Equivalent.

2.2 GENERAL

A. Provide motor control centers as shown on the Contract Drawings.

B. Motor Control Centers - NEMA ICS 2, Class II, Type BT wiring with terminal blocks mounted on lift out brackets in the units. Coordinate wire color coding with Section 26 05 00, Electrical-General. This requirement is applicable to the #14 control wires and to the power wiring

C. Terminals - Accept all control and power wiring as shown. All terminals shall have a minimum temperature rating of 75 degrees C. All conductor sizes shall be fully rated at this temperature.

D. Main Overcurrent Protection - Molded case switches or circuit breakers as shown on the Drawings.

E. Branch Breakers - Molded case thermal-magnetic circuit breakers.

F. Voltage Rating - 480 volts, three phase, four wire, 60 Hertz.

Herbert, Rowland & Grubic, Inc. 26 24 19 - 5 011139.0465

G. Horizontal Bus - Tin-plated copper with a continuous current rating as shown on the Contract Drawings. Include tin-plated copper ground bus entire length of control center and a fully rated neutral.

H. Vertical Bus - Tin-plated copper with a minimum continuous current rating of 300 amperes minimum or larger as required for the loads or as shown on the Contract Drawings, running the full working height (unless otherwise shown) of the section with bolted connections to horizontal bus. Also increase vertical bus rating where shown on the Drawings.

I. Integrated Equipment Short Circuit Rating - 65,000 amperes rms symmetrical at 480 volts.

J. Configuration - Units front mounting only, accessible from the front only.

K. Enclosure - NEMA ICS 6, Type 12.

L. Dimensions – Nominal:

1. Depth - 20 inches.

2. Vertical Sections - 6 space factors (72 inches) of unit mounting space.

3. Overall Height - 90 inches.

M. Finish:

1. Manufacturer's standard gray enamel.

2. Factory finish process with cleaning, rinsing, phosphating, four pre-paint rinses, three post paint rinses, a bake cure, and cool down for each section.

N. Section Wireways:

1. Two horizontal and one vertical wireway, the full width and working height of each section.

2. Provide barrier plates, cable supports reusable wire ties, and captive screws.

3. For openings or cutouts in wireways, provide rubber grommet-type protectors around openings.

O. Material:

1. Exterior Frame - Fabricated from copper bearing reinforced steel plate construction.

2. Bus Supports - High strength glass reinforced alkyd material.

P. Bus Barriers:

1. Permit unit plug-on contacts to pass through and engage the vertical bus bars.

2. Provide bottom bus covers below the vertical bus.

3. Unused Plug-On Openings - Provide plastic closing plates.

Q. Plug-On Connections:

1. Two-point connection to tighten around the vertical bus bar.

Herbert, Rowland & Grubic, Inc. 26 24 19 - 6 011139.0465

2. Material - Silver plated.

3. Cable Connections to the Plug-On Connections - Welded type.

R. Provide "infrared" clear panels in front of all terminations (line and load) for main breakers, pump circuit breakers for pumps 30 HP and larger, and for all VFD and soft starters.

S. Bucket Alignment - Guide rails within the structure for horizontal and vertical alignment.

T. Arch-Flash Safety Signs:

1. Provide arc-flash sign per Provide arc-flash signs required by NFPA 70.110.16 and

NFPA 70E.

2. Provide signs for panelboards, motor control centers, and control panels containing 480-volt equipment.

2.3 AUTOMATIC CONTROLLERS

A. Magnetic Motor Controllers - NEMA ICS 2, AC general-purpose Class A magnetic controller for induction motors rated in horsepower. Minimum NEMA Size 1.

B. Coil Operating Voltage - 120 volts, 60 Hertz.

C. Overload Relay - NEMA ICS; melting alloy (for fractional HP motors).

D. Provide motor controller (Square D LTM RTeSys T or equal) with Ethernet (Modbus TCP) communications for all full voltage non-reversing starters 1 HP and larger.

E. Variable frequency drives and harmonic mitigation equipment installed in the MCCs shall be in accordance with Section 26 29 23 - Variable Frequency Drives.

2.4 PRODUCT OPTIONS AND FEATURES

A. Auxiliary Contacts - NEMA ICS 2, two each normally open/closed contacts in addition to seal-in contact.

B. Door-Mounted Pilot Devices - NEMA ICS 2, heavy duty type. See Section 26 09 16 – Auxiliary Controls and Relays.

C. Refer to Section 26 09 16 - Auxiliary Controls and Relays, for pushbuttons, indicating lights, selector switches, relays, and control power transformers.

2.5 DISCONNECTS

A. Combination Controllers - Combine motor controllers with thermal magnetic circuit breakers or motor circuit protector as scheduled. Provide means for locking disconnect handle, and means for defeating cover interlock.

Herbert, Rowland & Grubic, Inc. 26 24 19 - 7 011139.0465

B. Thermal-Magnetic Circuit Breakers - NEMA AB 1, with integral thermal and instantaneous magnetic trip in each pole.

C. Motor Circuit Protector - NEMA AB 1, circuit breakers with integral instantaneous magnetic trip in each pole.

D. Disconnect Operator - All circuit disconnecting means shall be handle operated through approximately a 180-degree arc to open or close the device. Operation shall be done vertically; horizontal or rotary operators are not acceptable. With labeled and color coded On, Off, and Tripped position indicators. Provide means of locking disconnect in the Off position.

E. Maximum height from floor to top of any disconnecting means shall be no higher than 6 feet 6 inches above the floor with the MCC on the housekeeping pad as shown. Contractor may use permanently attached "drop handles" to meet this requirement.

F. Fuses - In conformance with Section 26 28 16.13 - Overcurrent Protective Devices.

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify conditions in accordance with Section 26 05 00 – Electrical General.

B. Verify that surface is suitable for motor control center installation.

C. The manufacturer of this equipment will be permitted to arrange his equipment to the best advantage and will be required to furnish at least the spare compartments as noted on the Drawings.

3.2 PREPARATION

A. Contractor shall coordinate the size and location of housekeeping pads with the electrical equipment shop drawings.

B. Housekeeping pads are detailed on the Contract Drawings.

3.3 INSTALLATION

A. The MCCs and all necessary appurtenances and/or accessories shall be installed in accordance with the manufacturer's installation instructions, approved shop drawings, Contract Drawings and this section.

B. The Contractor shall review the method of installation for the MCCs with the MCC manufacturer.

Herbert, Rowland & Grubic, Inc. 26 24 19 - 8 011139.0465

C. The Contractor shall field verify existing conditions and shall notify the Owner's representative of any conditions that need to be corrected prior to commencing the work of this section. Commencement of work by the Contractor is acceptance of existing conditions.

D. A manufacturer's representative shall supervise, check or assist in the installation of the motor control centers as required by Section 01 60 00, Materials and Equipment.

E. Tighten accessible bus connections and mechanical fasteners after placing motor control center, but prior to energization. Provide written certification that this was done.

F. Select and install overload elements in motor starters to match installed motor characteristics.

G. Provide engraved plastic nameplates under the provisions of Sections 26 05 00 – Electrical General and 26 05 53 - Electrical System Identification.

H. Motor Data - Provide neatly typed label inside each motor starter door identifying motor served, nameplate horsepower, full load amperes, code letter, service factor, and voltage/phase rating.

I. Wiring Diagrams - Approved final elementary diagram shall be glued inside each compartment door housing a motor controller, relay, or similar equipment. Other compartments shall also have approved final unit wiring diagrams glued on the inside face of door as well as a heater selection table.

J. MCCs shall be mounted on raised concrete bases (housekeeping pads) unless noted otherwise. Bases are provided under provisions of Division 3, Cast-in-Place Concrete.

Connections to external equipment and connections of the incoming services shall be as shown or as required by the equipment manufacturer.

3.4 FIELD QUALITY CONTROL

A. Field tests shall be conducted on the motor control centers to ensure that the equipment is assembled and installed in accordance with the manufacturer's installation instructions, approved shop drawings, Contract Drawings and this Section. The primary goal of field testing is to ensure the proper installation, setup and operation of equipment or systems.

Field testing includes all testing, measuring and adjusting of equipment or systems by the Contractor and/or manufacturer's representative prior to performance testing.

B. Field tests shall be conducted in accordance with the manufacturer's instructions and requirements, together with the provisions of Section 26 08 00 – Electrical Field Acceptance Tests.

C. Deficiencies identified during field tests shall be corrected.

D. All labor, equipment, special tools or apparatus and supplies required for field tests shall be supplied by the Contractor.

Herbert, Rowland & Grubic, Inc. 26 24 19 - 9 011139.0465

E. Field tests shall include, but are not limited to the following, where applicable:

1. Checking the voltage to a piece of equipment or system.

2. Checking the rotation of a motor.

3. Checking the clearance between mounting and mating surfaces.

4. Testing the operation of a manually operated or motorized piece of equipment to ensure smooth operation of mechanisms.

5. Checking the flow rate through a piece of equipment, system or structure.

6. Testing the operation of equipment controls.

7. Any testing of the operation of a piece of equipment or system prior to performance testing.

F. Field inspection and testing will be performed under the provisions of Sections 26 05 00 - Electrical General and 26 08 00 – Electrical Field Acceptance Tests.

G. Inspect each controller to NEMA ICS 2.

H. Correct any problems identified during field testing.

3.5 LABELING AND IDENTIFICATION

A. All interior relays, timers or other control devices shall be labeled according to its designation on the elementary diagram.

B. A control center identification nameplate with factory identification numbers and characteristics shall be fastened within every section. Each control center compartment (bucket) shall have its own identification nameplate fastened to the unit saddle. These nameplates shall have suitable references to factory records for efficient communication with supplier or manufacturer.

3.6 TESTING

A. Prior to connection of any external feeder or load circuits, MCC breakers shall be electrically tested per Section 26 08 00 – Electrical Field Acceptance Tests.

B. Make all connections in accordance with the torqueing specifications provided by the manufacturer.

C. All power connections, breakers, and starters shall be given an infrared thermograph scan after the unit is operational and with each unit operating at as near full load as possible.

See Section 26 08 00 – Electrical Field Acceptance Tests. The Contractor shall prepare and submit written tabulation of the test results of each MCC compartment components.

D. Contractor shall retorque or redo connections identified as potential problems.

E. Contractor shall individually adjust all trip units for the specific requirements of each device.

Herbert, Rowland & Grubic, Inc. 26 24 19 - 10 011139.0465

F. Contractor shall submit a letter of certification that all of the above have been done, are correct, and are fully operational.

END OF SECTION