40 05 65.23 - Swing Check Valves.pdf
PDF 252 KB Posted
- Attached to
- Biosolids Project 011139.0465
- Solicitation number
- US.260443
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a technical specification document for swing check valves associated with the Biosolids Project 011139.0465 being managed by Ephrata Borough Authority in Pennsylvania. The specification covers swing check valves sized 3 inches and larger, which are to be supplied and installed as part of the broader biosolids project that includes coordination of two new biodryers, demolition and replacement of dewatered solids conveyor systems, wall demolition and replacement, indoor utility replacements, site piping replacement and relocation, a dumpster loading canopy, and associated electrical improvements. The project is divided into two separate contracts: Contract No. EBA26-2 for General Construction and Contract No. EBA26-3 for Electrical Construction. Bids are being received through PennBid until December 8, 2026 at 10:00 AM local time. A pre-bid open house is scheduled for November 18, 2026 from 8:00 AM to 10:00 AM, with bidding documents available through the PennBid website at https://pennbid.bonfirehub.com/.
The swing check valve specification requires compliance with AWWA C508 standards and establishes minimum working pressure of 150 psig with full open flow area equal to connecting nominal pipe diameter. Approved manufacturers include Val-Matic Valve & Manufacturing Corp., DeZurick, Kennedy Valve Company, Mueller Co., or approved equal alternatives. Valves must feature ductile iron bodies, bronze discs and chambers, Type 304 stainless steel seats and connecting hardware, and be supplied with adjustable air cushion chambers for 6-inch and larger models. Products must be hydrostatically tested at twice rated pressure with zero permitted leakage at indicated working pressure. Manufacturers must have a minimum of three years' documented experience, and all swing check valves are to be furnished with a five-year manufacturer's warranty. Installation must comply with AWWA C508 and manufacturer instructions, with dielectric fittings required between dissimilar metals.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
40 05 65.23 - SWING CHECK VALVES
Herbert, Rowland & Grubic, Inc. 40 05 65.23 - 1 011139.0465
SECTION 40 05 65.23 - SWING CHECK VALVES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes: Swing check valves 3 inches and larger.
B. Related Requirements:
1. Section 40 05 51 - Common Requirements for Process Valves: Basic materials and methods related to valves commonly used for process systems.
1.2 REFERENCE STANDARDS
A. American Water Works Association:
1. AWWA C508 - Swing-Check Valves for Waterworks Service, 2-In. Through 24-In.
(50-mm Through 600-mm) NPS.
B. ASME International:
1. ASME B16.1 - Gray Iron Pipe Flanges and Flanged Fittings: Classes 25, 125, and
250.
2. ASME B16.11 - Forged Fittings, Socket-Welding and Threaded.
3. ASME B16.42 - Ductile Iron Pipe Flanges and Flanged Fittings: Classes 150 and
300.
C. ASTM International:
1. ASTM A126 - Standard Specification for Gray Iron Castings for Valves, Flanges, and
Pipe Fittings.
2. ASTM A536 - Standard Specification for Ductile Iron Castings.
3. ASTM B62 - Standard Specification for Composition Bronze or Ounce Metal
Castings.
4. ASTM B148 - Standard Specification for Aluminum-Bronze Sand Castings.
D. NSF International:
1. NSF 61 - Drinking Water System Components - Health Effects.
2. NSF 372 - Drinking Water System Components - Lead Content.
E. SSPC - The Society for Protective Coatings:
1. SSPC SP 6 - Commercial Blast Cleaning.
1.3 COORDINATION
A. Section 01 31 13 – Project Coordination: Requirements for coordination.
B. Coordinate Work of this Section with piping and equipment connections as specified in other Sections and as indicated on Drawings.
Herbert, Rowland & Grubic, Inc. 40 05 65.23 - 2 011139.0465
1.4 PREINSTALLATION MEETINGS
A. Section 01 31 19 – Project Meetings: Requirements for preinstallation meeting.
1.5 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data: Submit manufacturer's catalog information, indicating materials of construction and compliance with indicated standards.
C. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.
D. Source Quality-Control Submittals: Indicate results of shop or factory tests and inspections.
E. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections.
1.6 CLOSEOUT SUBMITTALS
A. Section 01 77 00 - Closeout Requirements: Requirements for submittals.
B. Project Record Documents: Record actual locations of piping, valves and other appurtenances, connections, and centerline elevations.
1.7 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum three years' documented experience.
1.8 DELIVERY, STORAGE, AND HANDLING
A. Section 01 61 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products.
B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.
C. Store materials according to manufacturer instructions.
D. Protection:
1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.
2. Protect valves and appurtenances by storing off ground.
3. Provide additional protection according to manufacturer instructions.
1.9 EXISTING CONDITIONS
A. Field Measurements:
Herbert, Rowland & Grubic, Inc. 40 05 65.23 - 3 011139.0465
1. Verify field measurements prior to fabrication.
2. Indicate field measurements on Shop Drawings.
1.10 WARRANTY
A. Section 01 78 36 - Warranty Requirements: Requirements for warranties.
B. Furnish five-year manufacturer's warranty for swing check valves.
PART 2 - PRODUCTS
2.1 SWING CHECK VALVES
A. Manufacturers:
1. Val-Matic Valve & Manufacturing Corp.,
2. DeZurick,
3. Kennedy Valve Company,
4. Mueller Co., or
5. Approved equal.
6. Substitutions: As specified in Section 01 61 00 - Product Requirements.
B. Description:
1. Type: Swing, resilient seated, with outside lever and adjustable weight.
2. Size: 3 inches and larger.
3. Comply with AWWA C508.
4. Minimum Working Pressure: 150 psig.
5. Flow Area: Full open, equal to connecting nominal pipe diameter.
6. Check Valves 6 Inches and Larger: Furnish with adjustable air cushion chambers.
7. Mounting: Horizontal.
8. End Connections: Flanged, ASME B16.42.
C. Materials:
1. Body and Cover: Ductile iron, ASTM A536.
2. Disc: Bronze, ASTM B62.
3. Seat: Field replaceable, Type 304 stainless steel.
4. Chamber and Plunger: Bronze, ASTM B62.
5. Hinge Pin and Key: Stainless steel.
6. Packing and O-Ring: Buna-N.
7. Rubber Components: Buna-N.
8. Connecting Hardware: Type 304 stainless steel.
D. Finishes: As specified in Section 40 05 51 - Common Requirements for Process Valves.
2.2 SOURCE QUALITY CONTROL
A. Section 01 40 00 - Quality Requirements: Requirements for testing, inspection, and analysis.
Herbert, Rowland & Grubic, Inc. 40 05 65.23 - 4 011139.0465
B. Testing:
1. Hydrostatically test check valves at twice rated pressure according to AWWA
C508.
2. Permitted Leakage at Indicated Working Pressure: None.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.
B. Verify that field dimensions are as indicated on Shop Drawings.
C. Inspect existing flanges for nonstandard bolt-hole configurations or design and verify that new valve and flange mate properly.
3.2 PREPARATION
A. Section 01 73 00 - Execution Requirements: Requirements for installation preparation.
B. Thoroughly clean valves before installation.
C. Surface Preparation:
1. Touch up shop-primed surfaces with primer as specified in Section 09 90 00 -
Painting and Coating.
2. Solvent-clean surfaces that are not shop primed.
3. Clean surfaces to remove loose rust, mill scale, and other foreign substances by power wire brushing.
3.3 INSTALLATION
A. According to AWWA C508 and manufacturer instructions.
B. Dielectric Fittings: Provide between dissimilar metals.
3.4 FIELD QUALITY CONTROL
A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.
B. Inspection:
1. Inspect for damage to valve lining or coating and for other defects that may be detrimental as determined by Architect/Engineer.
2. Repair damaged valve or provide new, undamaged valve.
3. After installation, inspect for proper supports and interferences.
C. Pressure test valves with piping.
3.5 CLEANING
A. Section 01 73 00 - Execution Requirements: Requirements for cleaning.
Herbert, Rowland & Grubic, Inc. 40 05 65.23 - 5 011139.0465
B. Keep valve interior clean as installation progresses.
C. After installation, clean valve interior of soil, grit, loose mortar, and other debris.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes: Swing check valves 3 inches and larger. |
| B. Related Requirements: |
| 1. Section 40 05 51 - Common Requirements for Process Valves: Basic materials and methods related to valves commonly used for process systems. |
| 1.2 REFERENCE STANDARDS |
| A. American Water Works Association: |
| 1. AWWA C508 - Swing-Check Valves for Waterworks Service, 2-In. Through 24-In. (50-mm Through 600-mm) NPS. |
| B. ASME International: |
| 1. ASME B16.1 - Gray Iron Pipe Flanges and Flanged Fittings: Classes 25, 125, and 250. |
| 2. ASME B16.11 - Forged Fittings, Socket-Welding and Threaded. |
| 3. ASME B16.42 - Ductile Iron Pipe Flanges and Flanged Fittings: Classes 150 and 300. |
| C. ASTM International: |
| 1. ASTM A126 - Standard Specification for Gray Iron Castings for Valves, Flanges, and Pipe Fittings. |
| 2. ASTM A536 - Standard Specification for Ductile Iron Castings. |
| 3. ASTM B62 - Standard Specification for Composition Bronze or Ounce Metal Castings. |
| 4. ASTM B148 - Standard Specification for Aluminum-Bronze Sand Castings. |
| D. NSF International: |
| 1. NSF 61 - Drinking Water System Components - Health Effects. |
| 2. NSF 372 - Drinking Water System Components - Lead Content. |
| E. SSPC - The Society for Protective Coatings: |
| 1. SSPC SP 6 - Commercial Blast Cleaning. |
| 1.3 COORDINATION |
| A. Section 01 31 13 – Project Coordination: Requirements for coordination. |
| B. Coordinate Work of this Section with piping and equipment connections as specified in other Sections and as indicated on Drawings. |
| 1.4 PREINSTALLATION MEETINGS |
| A. Section 01 31 19 – Project Meetings: Requirements for preinstallation meeting. |
| 1.5 SUBMITTALS |
| A. Section 01 33 00 - Submittal Procedures: Requirements for submittals. |
| B. Product Data: Submit manufacturer's catalog information, indicating materials of construction and compliance with indicated standards. |
| C. Manufacturer's Certificate: Certify that products meet or exceed specified requirements. |
| D. Source Quality-Control Submittals: Indicate results of shop or factory tests and inspections. |
| E. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections. |
| 1.6 CLOSEOUT SUBMITTALS |
| A. Section 01 77 00 - Closeout Requirements: Requirements for submittals. |
| B. Project Record Documents: Record actual locations of piping, valves and other appurtenances, connections, and centerline elevations. |
| 1.7 QUALIFICATIONS |
| A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum three years' documented experience. |
| 1.8 DELIVERY, STORAGE, AND HANDLING |
| A. Section 01 61 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products. |
| B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage. |
| C. Store materials according to manufacturer instructions. |
| D. Protection: |
| 1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas. |
| 2. Protect valves and appurtenances by storing off ground. |
| 3. Provide additional protection according to manufacturer instructions. |
| 1.9 EXISTING CONDITIONS |
| A. Field Measurements: |
| 1. Verify field measurements prior to fabrication. |
| 2. Indicate field measurements on Shop Drawings. |
| 1.10 WARRANTY |
| A. Section 01 78 36 - Warranty Requirements: Requirements for warranties. |
| B. Furnish five-year manufacturer's warranty for swing check valves. |
| PART 2 - PRODUCTS |
| 2.1 SWING CHECK VALVES |
| A. Manufacturers: |
| 1. Val-Matic Valve & Manufacturing Corp., |
| 2. DeZurick, |
| 3. Kennedy Valve Company, |
| 4. Mueller Co., or |
| 5. Approved equal. |
| 6. Substitutions: As specified in Section 01 61 00 - Product Requirements. |
| B. Description: |
| 1. Type: Swing, resilient seated, with outside lever and adjustable weight. |
| 2. Size: 3 inches and larger. |
| 3. Comply with AWWA C508. |
| 4. Minimum Working Pressure: 150 psig. |
| 5. Flow Area: Full open, equal to connecting nominal pipe diameter. |
| 6. Check Valves 6 Inches and Larger: Furnish with adjustable air cushion chambers. |
| 7. Mounting: Horizontal. |
| 8. End Connections: Flanged, ASME B16.42. |
| C. Materials: |
| 1. Body and Cover: Ductile iron, ASTM A536. |
| 2. Disc: Bronze, ASTM B62. |
| 3. Seat: Field replaceable, Type 304 stainless steel. |
| 4. Chamber and Plunger: Bronze, ASTM B62. |
| 5. Hinge Pin and Key: Stainless steel. |
| 6. Packing and O-Ring: Buna-N. |
| 7. Rubber Components: Buna-N. |
| 8. Connecting Hardware: Type 304 stainless steel. |
D. Finishes: As specified in Section 40 05 51 - Common Requirements for Process Valves.
| 2.2 SOURCE QUALITY CONTROL |
| A. Section 01 40 00 - Quality Requirements: Requirements for testing, inspection, and analysis. |
| B. Testing: |
| 1. Hydrostatically test check valves at twice rated pressure according to AWWA C508. |
| 2. Permitted Leakage at Indicated Working Pressure: None. |
| PART 3 - EXECUTION |
| 3.1 EXAMINATION |
| A. Section 01 73 00 - Execution Requirements: Requirements for installation examination. |
| B. Verify that field dimensions are as indicated on Shop Drawings. |
| C. Inspect existing flanges for nonstandard bolt-hole configurations or design and verify that new valve and flange mate properly. |
| 3.2 PREPARATION |
| A. Section 01 73 00 - Execution Requirements: Requirements for installation preparation. |
| B. Thoroughly clean valves before installation. |
| C. Surface Preparation: |
| 1. Touch up shop-primed surfaces with primer as specified in Section 09 90 00 - Painting and Coating. |
| 2. Solvent-clean surfaces that are not shop primed. |
| 3. Clean surfaces to remove loose rust, mill scale, and other foreign substances by power wire brushing. |
| 3.3 INSTALLATION |
| A. According to AWWA C508 and manufacturer instructions. |
| B. Dielectric Fittings: Provide between dissimilar metals. |
| 3.4 FIELD QUALITY CONTROL |
| A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing. |
| B. Inspection: |
| 1. Inspect for damage to valve lining or coating and for other defects that may be detrimental as determined by Architect/Engineer. |
| 2. Repair damaged valve or provide new, undamaged valve. |
| 3. After installation, inspect for proper supports and interferences. |
C. Pressure test valves with piping.
| 3.5 CLEANING |
| A. Section 01 73 00 - Execution Requirements: Requirements for cleaning. |
| B. Keep valve interior clean as installation progresses. |
| C. After installation, clean valve interior of soil, grit, loose mortar, and other debris. |