About this file
This is a Work Change Directive Form issued by Herbert, Rowland & Grubic, Inc., the engineer for the Ephrata Borough Authority, pertaining to the Biosolids Project 011139.0465 in Pennsylvania. The form authorizes the contractor to proceed promptly with specified work changes prior to final agreement on contract price and time adjustments. The directive is issued due to either non-agreement on pricing of the proposed change or necessity to proceed for schedule or other project reasons. The form includes provisions for documenting the estimated change in contract price (marked as increase, decrease, or not yet estimated) and contract time (in days, similarly marked as increase, decrease, or not yet estimated). The basis for determining the change in contract price may be established through lump sum, unit prices, cost of work, or other methods.
The form requires authorization and approval signatures from the engineer, owner, and funding agency, with designated spaces for titles and dates from each approving party. As a preliminary directive, the form establishes a mechanism for the contractor to continue work on the project while the parties negotiate final terms and pricing for the work change. No specific pricing amounts, contract time extensions, or detailed work descriptions are completed on the form provided, indicating this is a blank template or example document used to establish the process for managing changes to the Biosolids Project construction contract.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Herbert, Rowland & Grubic, Inc. 00 63 49 - 1 011139.0465
WORK CHANGE DIRECTIVE NO. [X]
Date of Issuance: Effective Date: [DATE EXECUTED BY OWNER]
Owner: Ephrata Borough Authority Contract No.:
Contractor: Contract Name:
Engineer: Herbert, Rowland and Grubic, Inc. HRG Project No.: 011139.0465
Project:
Contractor is directed to proceed promptly with the following change(s):
Description:
Attachments:
Purpose for Work Change Directive:
Directive to proceed promptly with the Work described herein, prior to agreeing to changes on Contract Price and Contract Time, is issued due to:
Non-agreement on pricing of proposed change
Necessity to proceed for schedule or other Project reasons.
Estimated Change in Contract Price and Contract Times (non-binding, preliminary):
Contract Price: $ [increase] [decrease] [not yet estimated].
Contract Time: days [increase] [decrease] [not yet estimated].
Basis of determining change in Contract Price:
Lump Sum Unit Prices Cost of the Work Other
RECOMMENDED: AUTHORIZED BY: APPROVED (if applicable):
By: By: By:
Engineer (Authorized Signature) Owner (Authorized Signature) Funding Agency
Title: Title: Title:
Date: Date: Date: