Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This is a Work Change Directive Form issued by Herbert, Rowland & Grubic, Inc., the engineer for the Ephrata Borough Authority, pertaining to the Biosolids Project 011139.0465 in Pennsylvania. The form authorizes the contractor to proceed promptly with specified work changes prior to final agreement on contract price and time adjustments. The directive is issued due to either non-agreement on pricing of the proposed change or necessity to proceed for schedule or other project reasons. The form includes provisions for documenting the estimated change in contract price (marked as increase, decrease, or not yet estimated) and contract time (in days, similarly marked as increase, decrease, or not yet estimated). The basis for determining the change in contract price may be established through lump sum, unit prices, cost of work, or other methods.

The form requires authorization and approval signatures from the engineer, owner, and funding agency, with designated spaces for titles and dates from each approving party. As a preliminary directive, the form establishes a mechanism for the contractor to continue work on the project while the parties negotiate final terms and pricing for the work change. No specific pricing amounts, contract time extensions, or detailed work descriptions are completed on the form provided, indicating this is a blank template or example document used to establish the process for managing changes to the Biosolids Project construction contract.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Herbert, Rowland & Grubic, Inc. 00 63 49 - 1 011139.0465

WORK CHANGE DIRECTIVE NO. [X]

Date of Issuance: Effective Date: [DATE EXECUTED BY OWNER]

Owner: Ephrata Borough Authority Contract No.:

Contractor: Contract Name:

Engineer: Herbert, Rowland and Grubic, Inc. HRG Project No.: 011139.0465

Project:

Contractor is directed to proceed promptly with the following change(s):

Description:

Attachments:

Purpose for Work Change Directive:

Directive to proceed promptly with the Work described herein, prior to agreeing to changes on Contract Price and Contract Time, is issued due to:

Non-agreement on pricing of proposed change

Necessity to proceed for schedule or other Project reasons.

Estimated Change in Contract Price and Contract Times (non-binding, preliminary):

Contract Price: $ [increase] [decrease] [not yet estimated].

Contract Time: days [increase] [decrease] [not yet estimated].

Basis of determining change in Contract Price:

Lump Sum Unit Prices Cost of the Work Other

RECOMMENDED: AUTHORIZED BY: APPROVED (if applicable):

By: By: By:

Engineer (Authorized Signature) Owner (Authorized Signature) Funding Agency

Title: Title: Title:

Date: Date: Date: