01 29 00 - Payment Procedures.pdf

PDF 238 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This document is a Payment Procedures specification section prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 administered by Ephrata Borough Authority in Pennsylvania. The specification establishes the framework for contractor compensation, requiring submission of a Schedule of Values within 15 days after the Owner-Contractor Agreement date, with detailed line-item breakdowns organized by the Project Manual's Table of Contents. The contractor must submit Applications for Payment in three copies plus electronic files via email at intervals stipulated in the Agreement, with executed originals delivered to the Engineer within 24 hours. Initial Applications for Payment require submission of subcontractor lists, preliminary construction schedules, product lists, insurance certificates, and submittals schedules. Applications at Substantial Completion require Final Operation and Maintenance Manuals and draft Project Record Documents, while final payment applications require evidence of project closeout completion, final Project Record Documents, and Contractor's Affidavits. All substantiating data must accompany payment applications, including current construction photographs, partial lien releases from major subcontractors, and revised construction progress schedules.

The contractor receives compensation as full payment for furnishing all materials, labor, tools, equipment, and performing all Work in a complete and acceptable manner, including miscellaneous labor and materials not specifically mentioned in the Contract Documents, material disposal, and all testing costs without additional compensation. The Schedule of Values must round all amounts to the nearest whole dollar with a total equal to the Contract Sum, include proportional amounts of contractor overhead and profit in each line item, and be revised to list approved Change Orders with each Application for Payment. The Engineer possesses final authority to assess defective work and identify payment adjustments, with provisions for replacement, remedy, or payment adjustment at the Engineer's and Owner's discretion. Payment will not be made for rejected products, including those wasted, disposed of improperly, determined unacceptable before or after placement, incompletely unloaded, placed beyond required lines and levels, or remaining on hand after project completion.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 29 00 - PAYMENT PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 29 00 - 1 011139.0465

SECTION 01 29 00 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Scope of Payment.

B. Schedule of Values.

C. Application for Payment.

D. Defect Assessment.

1.2 SCOPE OF PAYMENT

A. Contractor will receive and accept compensation provided for in the Contract as full payment for furnishing all materials, labor, tools, and equipment and for performing all Work in a complete and acceptable manner and for all risk, loss, damage, or expense of whatever character arising out of the nature of the Work or the prosecution thereof.

B. Contractor shall furnish all labor, materials, equipment, machinery, apparatus and tools and perform all operations necessary to install, equip, adjust and put into satisfactory operation the Work, and shall connect the various items or sections of the Work as to form a complete and properly operating whole. Any miscellaneous labor, materials, equipment or apparatus not specifically mentioned herein, or shown on the drawings, which may be found necessary to complete or perfect any portion of the Work in a substantial manner and in compliance with the requirements stated or implied by the Contract Documents, shall be furnished by the Contractor without additional compensation. This includes the cost of material disposal, water for testing and all testing costs including laboratory fees.

1.3 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

B. Submit electronic file via email of schedule on Application for Payment Continuation Sheets.

C. Submit Schedule of Values as electronic file via email to Engineer within 15 days after date of Owner-Contractor Agreement.

D. Format:

1. Provide a breakdown of the Contract Price in enough detail to facilitate continued evaluation of Applications for Payment and progress reports.

Herbert, Rowland & Grubic, Inc. 01 29 00 - 2 011139.0465

2. Use Table of Contents of this Project Manual. Identify each line item with number and title of major Specification Section. Provide several line items for principal subcontract amounts, where appropriate.

3. Identify Site mobilization and bonds and insurance.

4. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

E. Include in each line item amount of allowances as specified.

F. Include within each line item, direct proportional amount of Contractor's overhead and profit.

1. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

G. Revise schedule to list approved Change Orders with each Application for Payment.

1.4 APPLICATION FOR PAYMENT

A. Submit three copies and electronic files via email of each Application for Payment on form(s) provided in Section 00 62 76 in accordance with requirements of the General Conditions.

1. Initial Application for Payment, Application for Payment at time of Substantial

Completion, and final Application for Payment involve additional requirements.

B. Content and Format: Use Schedule of Values for listing items in Application for Payment.

1. Execute by a person authorized to sign legal documents on behalf of Contractor.

Engineer will return incomplete applications without action.

2. Include amounts of Change Orders issued before last day of construction period covered by application.

C. Submit updated construction schedule with each Application for Payment.

D. Payment Period: Submit at intervals stipulated in the Agreement.

E. Submit executed originals with transmittal letter to Engineer by method ensuring receipt within 24 hours.

F. Submit three copies of waivers requested by Owner.

G. Substantiating Data: When Engineer requires substantiating information, submit data justifying dollar amounts in question. Include the following with Application for Payment:

1. Current construction photographs specified in Section 01 32 33 - Photographic

Documentation.

2. Partial release of liens from major Subcontractors and vendors.

3. Record Documents as specified in Section 01 77 00 - Closeout Requirements, for review by Owner, which will be returned to Contractor.

4. Affidavits attesting to off-Site stored products.

5. Construction Progress Schedule, revised and current as specified in Section 01 33

00 - Submittal Procedures.

Herbert, Rowland & Grubic, Inc. 01 29 00 - 3 011139.0465

H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Contractor's Construction Schedule (preliminary if not final).

3. Products list.

4. Submittals Schedule (preliminary if not final).

5. Certificates of insurance and insurance policies.

I. Application for Payment at Substantial Completion: After issuance of the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete less the amounts certified by the Engineer as remaining.

1. Administrative actions and submittals that must precede or coincide with submittal of the Substantial Completion Application for Payment include the following:

a. Final Operation and Maintenance Manuals, as applicable.

b. Final test and field reports.

c. Draft Project Record Documents.

J. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following. Final Application will be prepared by the Engineer following completion of the final inspection per Section 01 77 00.

1. Evidence of completion of Project closeout requirements.

2. Final Project Record Documents.

3. Insurance certificates for products and completed operations and proof that taxes, fees, and similar obligations were paid.

4. Contractor's Affidavit: Submit on form provided by Engineer.

5. Consent of Surety to Final Payment: Submit on form provided by Engineer.

1.5 DEFECT ASSESSMENT

A. Replace the Work, or portions of the Work, not conforming to specified requirements.

B. If, in the opinion of Engineer, it is not practical to remove and replace the Work, Engineer will direct appropriate remedy or adjust payment.

C. The defective Work may remain, but unit sum/price will be adjusted to new sum/price at discretion of Engineer and Owner.

D. Defective Work will be partially repaired according to instructions of Engineer, and unit sum/price will be adjusted to new price at discretion of Engineer.

E. Individual Specification Sections may modify these options or may identify specific formula or percentage sum/price reduction.

F. Authority of Engineer to assess defects and identify payment adjustments is final.

G. Nonpayment for Rejected Products: Payment will not be made for rejected products for

Herbert, Rowland & Grubic, Inc. 01 29 00 - 4 011139.0465 any of the following reasons:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from transporting vehicle.

4. Products placed beyond lines and levels of the required Work.

5. Products remaining on hand after completion of the Work.

6. Loading, hauling, and disposing of rejected products.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION

PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Scope of Payment.
B. Schedule of Values.
C. Application for Payment.
D. Defect Assessment.
1.2 SCOPE OF PAYMENT
A. Contractor will receive and accept compensation provided for in the Contract as full payment for furnishing all materials, labor, tools, and equipment and for performing all Work in a complete and acceptable manner and for all risk, loss, damage, o...
B. Contractor shall furnish all labor, materials, equipment, machinery, apparatus and tools and perform all operations necessary to install, equip, adjust and put into satisfactory operation the Work, and shall connect the various items or sections of...
1.3 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.
B. Submit electronic file via email of schedule on Application for Payment Continuation Sheets.
C. Submit Schedule of Values as electronic file via email to Engineer within 15 days after date of Owner-Contractor Agreement.
D. Format:
1. Provide a breakdown of the Contract Price in enough detail to facilitate continued evaluation of Applications for Payment and progress reports.
2. Use Table of Contents of this Project Manual. Identify each line item with number and title of major Specification Section. Provide several line items for principal subcontract amounts, where appropriate.
3. Identify Site mobilization and bonds and insurance.
4. Round amounts to nearest whole dollar; total shall equal the Contract Sum.
E. Include in each line item amount of allowances as specified.
F. Include within each line item, direct proportional amount of Contractor's overhead and profit.
1. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

G. Revise schedule to list approved Change Orders with each Application for Payment.

1.4 APPLICATION FOR PAYMENT
A. Submit three copies and electronic files via email of each Application for Payment on form(s) provided in Section 00 62 76 in accordance with requirements of the General Conditions.
1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.
B. Content and Format: Use Schedule of Values for listing items in Application for Payment.
1. Execute by a person authorized to sign legal documents on behalf of Contractor. Engineer will return incomplete applications without action.
2. Include amounts of Change Orders issued before last day of construction period covered by application.
C. Submit updated construction schedule with each Application for Payment.
D. Payment Period: Submit at intervals stipulated in the Agreement.
E. Submit executed originals with transmittal letter to Engineer by method ensuring receipt within 24 hours.
F. Submit three copies of waivers requested by Owner.
G. Substantiating Data: When Engineer requires substantiating information, submit data justifying dollar amounts in question. Include the following with Application for Payment:
1. Current construction photographs specified in Section 01 32 33 - Photographic Documentation.
2. Partial release of liens from major Subcontractors and vendors.
3. Record Documents as specified in Section 01 77 00 - Closeout Requirements, for review by Owner, which will be returned to Contractor.
4. Affidavits attesting to off-Site stored products.
5. Construction Progress Schedule, revised and current as specified in Section 01 33 00 - Submittal Procedures.
H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Contractor's Construction Schedule (preliminary if not final).
3. Products list.
4. Submittals Schedule (preliminary if not final).
5. Certificates of insurance and insurance policies.
I. Application for Payment at Substantial Completion: After issuance of the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete less the amo...
1. Administrative actions and submittals that must precede or coincide with submittal of the Substantial Completion Application for Payment include the following:
a. Final Operation and Maintenance Manuals, as applicable.
b. Final test and field reports.
c. Draft Project Record Documents.
J. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following. Final Application will be prepared by the Engineer foll...
1. Evidence of completion of Project closeout requirements.
2. Final Project Record Documents.
3. Insurance certificates for products and completed operations and proof that taxes, fees, and similar obligations were paid.
4. Contractor's Affidavit: Submit on form provided by Engineer.
5. Consent of Surety to Final Payment: Submit on form provided by Engineer.
1.5 DEFECT ASSESSMENT
A. Replace the Work, or portions of the Work, not conforming to specified requirements.
B. If, in the opinion of Engineer, it is not practical to remove and replace the Work, Engineer will direct appropriate remedy or adjust payment.
C. The defective Work may remain, but unit sum/price will be adjusted to new sum/price at discretion of Engineer and Owner.
D. Defective Work will be partially repaired according to instructions of Engineer, and unit sum/price will be adjusted to new price at discretion of Engineer.
E. Individual Specification Sections may modify these options or may identify specific formula or percentage sum/price reduction.
F. Authority of Engineer to assess defects and identify payment adjustments is final.
G. Nonpayment for Rejected Products: Payment will not be made for rejected products for any of the following reasons:
1. Products wasted or disposed of in a manner that is not acceptable.
2. Products determined as unacceptable before or after placement.
3. Products not completely unloaded from transporting vehicle.
4. Products placed beyond lines and levels of the required Work.
5. Products remaining on hand after completion of the Work.
6. Loading, hauling, and disposing of rejected products.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION - Not Used.