This is a Scope of Work document for selective building demolition work associated with the Biosolids Project 011139.0465 in Ephrata Borough Authority, Pennsylvania. The document outlines demolition and removal of designated building equipment, fixtures, and construction elements, along with protection of items designated to remain and removal of designated items for reuse. The project scope includes demolishing process piping and electrical conduit as shown on contract drawings, custom steel plate and tube sloped conveyor supports on steel frames, and concrete slab on grade. Additionally, the contractor must remove, store, and protect insulated metal wall panels, a dewatering room hazardous gas monitoring panel, wall cee and zee girts, and wall louvers. The contractor is required to submit a demolition schedule indicating overall project schedule and required utility and building service interruptions, along with shop drawings showing demolition and removal sequence, location of items designated for reuse, and temporary work construction. A pre-installation meeting must be convened minimum one week prior to commencing work. The work must be coordinated to coincide with new construction and scheduled to minimize impact on the Owner's operations and adjacent spaces.
Quality assurance requirements mandate conformance to applicable codes for demolition work, dust control, and electrical disconnection and reconnection procedures, with particular emphasis on hazardous or contaminated materials discovery protocols and required permits from authorities having jurisdiction. The contractor must notify affected utility companies before starting work, mark utility locations and terminations, and maintain temporary barriers, security devices, warning signs, and lights for public and Owner protection. Fire and life safety systems cannot be disabled or disrupted without three days prior written notice to the Owner, and the contractor must maintain protected egress and access to adjacent buildings at all times. All demolished materials must be removed from the site except where specifically noted otherwise, with prohibited burning or burying on site. Upon completion, project record documents must accurately record actual locations of capped utilities, concealed utilities discovered during demolition, and any subsurface obstructions discovered.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
02 41 19.13 - SELECTIVE BUILDING DEMOLITION
Herbert, Rowland & Grubic, Inc. 02 41 19.13 - 1 011139.0465
SECTION 02 41 19.13 - SELECTIVE BUILDING DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Demolishing designated building equipment and fixtures.
2. Demolishing designated construction.
3. Cutting and alterations for completion of the Work.
4. Removing designated items for reuse.
5. Protecting items designated to remain.
6. Removing demolished materials.
1.2 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Demolition Schedule: Indicate overall schedule and interruptions required for utility and building services.
C. Shop Drawings:
1. Indicate demolition and removal sequence.
2. Indicate location of items designated for reuse.
3. Indicate location and construction of temporary work.
1.3 CLOSEOUT SUBMITTALS
A. Section 01 77 00 - Closeout Requirements: Requirements for submittals.
B. Project Record Documents: Accurately record actual locations of capped utilities, concealed utilities discovered during demolition, and subsurface obstructions.
C. Operation and Maintenance Data: Submit description of system, inspection data, and parts lists.
1.4 QUALITY ASSURANCE
A. Conform to applicable code for demolition work, dust control, and products requiring electrical disconnection and re-connection.
B. Conform to applicable code for procedures when hazardous or contaminated materials are discovered.
C. Obtain required permits from authorities having jurisdiction.
1.5 PRE-INSTALLATION MEETINGS
A. Section 01 31 19 – Project Meetings: Pre-installation meeting.
Herbert, Rowland & Grubic, Inc. 02 41 19.13 - 2 011139.0465
B. Convene minimum one week prior to commencing work of this section.
1.6 SEQUENCING
A. Section 01 10 00 - Summary: Requirements for sequencing.
1.7 SCHEDULING
A. Section 01 32 16 - Construction Progress Schedule: Requirements for scheduling.
B. Schedule Work to coincide with new construction.
C. Cooperate with Owner in scheduling noisy operations and waste removal that may impact Owners operation and in adjoining spaces.
D. Coordinate utility and building service interruptions with Owner.
1. Do not disable or disrupt building fire or life safety systems without three days prior written notice to Owner.
2. Schedule tie-ins to existing systems to minimize disruption.
3. Coordinate Work to ensure fire sprinklers, fire alarms, smoke detectors, emergency lighting, exit signs and other life safety systems remain in full operation in occupied areas.
1.8 PROJECT CONDITIONS
A. Conduct demolition to minimize interference with adjacent and occupied building areas.
B. Cease operations immediately if structure appears to be in danger and notify Engineer.
Do not resume operations until directed.
PART 2 - PRODUCTS – Not Used
PART 3 - EXECUTION
3.1 PREPARATION
A. Notify affected utility companies before starting work and comply with their requirements.
B. Mark location and termination of utilities.
C. Erect, and maintain temporary barriers and security devices at locations indicated, including warning signs and lights, and similar measures, for protection of the public, Owner, and existing improvements indicated to remain.
D. Erect and maintain weatherproof closures for exterior openings.
E. Prevent movement of structure; provide temporary bracing and shoring required to ensure safety of existing structure.
Herbert, Rowland & Grubic, Inc. 02 41 19.13 - 3 011139.0465
F. Provide appropriate temporary signage including signage for exit or building egress.
G. Do not close or obstruct building egress path.
H. Do not disable or disrupt building fire or life safety systems without 3 days prior written notice to Owner.
3.2 SALVAGE REQUIREMENTS
A. Coordinate with Owner to identify building components and equipment required to be removed and delivered to Owner.
B. Tag components and equipment Owner designates for salvage.
C. Protect designated salvage items from demolition operations until items can be removed.
D. Carefully remove building components and equipment indicated to be salvaged.
E. Disassemble as required to permit removal from building.
F. Package small and loose parts to avoid loss.
G. Mark equipment and packaged parts to permit identification and consolidation of components of each salvaged item.
H. Prepare assembly instructions consistent with disassembled parts. Package assembly instructions in protective envelope and securely attach to each disassembled salvaged item.
I. Deliver salvaged items to Owner. Obtain signed receipt from Owner.
3.3 DEMOLITION
A. Conduct demolition to minimize interference with adjacent and occupied building areas.
B. Maintain protected egress from and access to adjacent existing buildings at all times.
C. Cease operations immediately when structure appears to be in danger and notify Engineer.
D. Disconnect and remove designated utilities within demolition areas.
E. Cap and identify abandoned utilities at termination points when utility is not completely removed. Annotate Record Drawings indicating location and type of service for capped utilities remaining after demolition.
F. Demolish in orderly and careful manner. Protect existing improvements, supporting structural members and unit heater system.
G. Carefully remove building components indicated to be reused.
Herbert, Rowland & Grubic, Inc. 02 41 19.13 - 4 011139.0465
1. Disassemble components as required to permit removal.
2. Package small and loose parts to avoid loss.
3. Mark components and packaged parts to permit reinstallation.
4. Store components, protected from construction operations, until reinstalled.
H. Remove demolished materials from site except where specifically noted otherwise. Do not burn or bury materials on site.
I. Remove materials as Work progresses. Upon completion of Work, leave areas in clean condition.
J. Remove temporary Work.
3.4 SCHEDULES
A. Remove, store and protect the following materials and equipment:
1. Insulated Metal Wall Panels.
2. Dewatering Room Hazardous Gas Monitoring Panel.
3. Wall Cee and Zee Girts.
4. Wall Louver.
B. See Section 01 64 00 for scope of materials to be demolished by others. Owner generally will remove the following material and equipment before start of demolition, coordinate with Work by others:
1. Pyrolysis Unit and Appurtenances (as described).
C. Protect the following materials and equipment remaining:
1. Existing utilities within the building not shown for demolition must be protected, temporarily connected, and/or reinstalled to keep facility in operation.
D. Demolish the following materials and equipment:
1. Process piping, as shown on Contract Drawings.
2. Electrical conduit, as shown on Contract Drawings.
3. Custom Steel Plate Sloped Conveyor Supports on Steel Frame.
4. Custom Steel Tube Sloped Conveyor Supports on Steel Frame.
5. Concrete slab on grade.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes: |
| 1. Demolishing designated building equipment and fixtures. |
| 2. Demolishing designated construction. |
| 3. Cutting and alterations for completion of the Work. |
| 4. Removing designated items for reuse. |
| 5. Protecting items designated to remain. |
| 6. Removing demolished materials. |
| 1.2 SUBMITTALS |
| A. Section 01 33 00 - Submittal Procedures: Requirements for submittals. |
| B. Demolition Schedule: Indicate overall schedule and interruptions required for utility and building services. |
| C. Shop Drawings: |
| 1. Indicate demolition and removal sequence. |
| 2. Indicate location of items designated for reuse. |
| 3. Indicate location and construction of temporary work. |
| 1.3 CLOSEOUT SUBMITTALS |
| A. Section 01 77 00 - Closeout Requirements: Requirements for submittals. |
| B. Project Record Documents: Accurately record actual locations of capped utilities, concealed utilities discovered during demolition, and subsurface obstructions. |
| C. Operation and Maintenance Data: Submit description of system, inspection data, and parts lists. |
| 1.4 QUALITY ASSURANCE |
| A. Conform to applicable code for demolition work, dust control, and products requiring electrical disconnection and re-connection. |
| B. Conform to applicable code for procedures when hazardous or contaminated materials are discovered. |
| C. Obtain required permits from authorities having jurisdiction. |
| 1.5 PRE-INSTALLATION MEETINGS |
| A. Section 01 31 19 – Project Meetings: Pre-installation meeting. |
| B. Convene minimum one week prior to commencing work of this section. |
| 1.6 SEQUENCING |
| A. Section 01 10 00 - Summary: Requirements for sequencing. |
| 1.7 SCHEDULING |
| A. Section 01 32 16 - Construction Progress Schedule: Requirements for scheduling. |
| B. Schedule Work to coincide with new construction. |
| C. Cooperate with Owner in scheduling noisy operations and waste removal that may impact Owners operation and in adjoining spaces. |
| D. Coordinate utility and building service interruptions with Owner. |
| 1. Do not disable or disrupt building fire or life safety systems without three days prior written notice to Owner. |
| 2. Schedule tie-ins to existing systems to minimize disruption. |
| 3. Coordinate Work to ensure fire sprinklers, fire alarms, smoke detectors, emergency lighting, exit signs and other life safety systems remain in full operation in occupied areas. |
| 1.8 PROJECT CONDITIONS |
| A. Conduct demolition to minimize interference with adjacent and occupied building areas. |
| B. Cease operations immediately if structure appears to be in danger and notify Engineer. Do not resume operations until directed. |
| PART 2 - PRODUCTS – Not Used |
| PART 3 - EXECUTION |
| 3.1 PREPARATION |
| A. Notify affected utility companies before starting work and comply with their requirements. |
| B. Mark location and termination of utilities. |
| C. Erect, and maintain temporary barriers and security devices at locations indicated, including warning signs and lights, and similar measures, for protection of the public, Owner, and existing improvements indicated to remain. |
| D. Erect and maintain weatherproof closures for exterior openings. |
| E. Prevent movement of structure; provide temporary bracing and shoring required to ensure safety of existing structure. |
| F. Provide appropriate temporary signage including signage for exit or building egress. |
| G. Do not close or obstruct building egress path. |
| H. Do not disable or disrupt building fire or life safety systems without 3 days prior written notice to Owner. |
| 3.2 SALVAGE REQUIREMENTS |
| A. Coordinate with Owner to identify building components and equipment required to be removed and delivered to Owner. |
| B. Tag components and equipment Owner designates for salvage. |
| C. Protect designated salvage items from demolition operations until items can be removed. |
| D. Carefully remove building components and equipment indicated to be salvaged. |
| E. Disassemble as required to permit removal from building. |
| F. Package small and loose parts to avoid loss. |
| G. Mark equipment and packaged parts to permit identification and consolidation of components of each salvaged item. |
| H. Prepare assembly instructions consistent with disassembled parts. Package assembly instructions in protective envelope and securely attach to each disassembled salvaged item. |
| I. Deliver salvaged items to Owner. Obtain signed receipt from Owner. |
| 3.3 DEMOLITION |
| A. Conduct demolition to minimize interference with adjacent and occupied building areas. |
| B. Maintain protected egress from and access to adjacent existing buildings at all times. |
| C. Cease operations immediately when structure appears to be in danger and notify Engineer. |
| D. Disconnect and remove designated utilities within demolition areas. |
| E. Cap and identify abandoned utilities at termination points when utility is not completely removed. Annotate Record Drawings indicating location and type of service for capped utilities remaining after demolition. |
| F. Demolish in orderly and careful manner. Protect existing improvements, supporting structural members and unit heater system. |
| G. Carefully remove building components indicated to be reused. |
| 1. Disassemble components as required to permit removal. |
| 2. Package small and loose parts to avoid loss. |
| 3. Mark components and packaged parts to permit reinstallation. |
| 4. Store components, protected from construction operations, until reinstalled. |
| H. Remove demolished materials from site except where specifically noted otherwise. Do not burn or bury materials on site. |
| I. Remove materials as Work progresses. Upon completion of Work, leave areas in clean condition. |
| J. Remove temporary Work. |
| 3.4 SCHEDULES |
| A. Remove, store and protect the following materials and equipment: |
| 1. Insulated Metal Wall Panels. |
| 2. Dewatering Room Hazardous Gas Monitoring Panel. |
| 3. Wall Cee and Zee Girts. |
| 4. Wall Louver. |
| B. See Section 01 64 00 for scope of materials to be demolished by others. Owner generally will remove the following material and equipment before start of demolition, coordinate with Work by others: |
| 1. Pyrolysis Unit and Appurtenances (as described). |
| C. Protect the following materials and equipment remaining: |
| 1. Existing utilities within the building not shown for demolition must be protected, temporarily connected, and/or reinstalled to keep facility in operation. |
| D. Demolish the following materials and equipment: |
| 1. Process piping, as shown on Contract Drawings. |
| 2. Electrical conduit, as shown on Contract Drawings. |
| 3. Custom Steel Plate Sloped Conveyor Supports on Steel Frame. |
| 4. Custom Steel Tube Sloped Conveyor Supports on Steel Frame. |
| 5. Concrete slab on grade. |