01 32 33 - Photographic Documentation.pdf

PDF 223 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This file is a specification section for Photographic Documentation prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 at the Ephrata Borough Authority in Pennsylvania. The specification requires the contractor to provide comprehensive photographic documentation throughout all phases of the construction project, including preconstruction photographs prior to any work commencing, bi-weekly periodic construction photographs timed to coincide with Applications for Payment cutoff dates, and final completion photographs after Substantial Completion. All photographs must be submitted within three days of being taken and must be accompanied by a key plan identifying vantage points with compass directions and elevation information. The preconstruction phase must capture all elements within the construction limits including driveways, sidewalks, curbs, ditches, streets, landscaping, utilities, and building exteriors.

The specification requires digital photographs with a minimum 8-megapixel sensor resolution, submitted in JPG format with minimum 3200 by 2400 pixel dimensions in unaltered original files with date and time stamps. Each image must include metadata containing the project name, photographer contact information, engineer and contractor names, photograph date, vantage point description with compass direction, and a unique sequential identifier keyed to the key plan. The contractor must transfer all copyright usage rights to the Owner for unlimited use and reproduction. All photographs must demonstrate maximum depth of field with sharp focus throughout, and blurry or out-of-focus images will not be accepted. No pricing information, funding sources, or set-asides are addressed in this technical specification document.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 32 33 – PHOTOGRAPHIC DOCUMENTATION

Herbert, Rowland & Grubic, Inc. 01 32 33 - 1 011139.0465

SECTION 01 32 33 – PHOTOGRAPHIC DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Preconstruction photographs.

2. Periodic construction photographs.

3. Web-based construction photographic documentation.

4. Final completion construction photographs.

B. Related Sections:

1. Section 01 33 00 – Submittals: Procedures for submitting photographic documentation.

2. Section 01 77 00 – Closeout Procedures: Procedures for submitting photographic documentation as project record documents at Project closeout.

1.2 SUBMITTALS

A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each photograph. Indicate elevation or story of construction. Include same information as corresponding photographic documentation.

B. Digital Photographs: Submit image files within three days of taking photographs.

1. Digital Camera: Minimum sensor resolution of 8 megapixels.

2. Format: JPG with minimum 3200 by 2400 pixels, in unaltered original files, with same aspect ratio as the sensor, uncropped, date and time stamped, in folder named by date of photograph, accompanied by key plan file.

3. Identification: Provide the following information with each image description in file metadata tag:

a. Name of Project.

b. Name and contact information for photographer.

c. Name of Engineer.

d. Name of Contractor.

e. Date photograph was taken.

f. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.

g. Unique sequential identifier keyed to accompanying key plan.

1.3 USAGE RIGHTS

A. Transfer copyright usage rights to Owner for unlimited use and reproduction of photographic documentation.

01 32 33 – PHOTOGRAPHIC DOCUMENTATION

Herbert, Rowland & Grubic, Inc. 01 32 33 - 2 011139.0465

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION

3.1 GENERAL

A. Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted.

1. Maintain key plan with each set of construction photographs that identifies each photographic location.

3.2 PRECONSTRUCTION PHOTOGRAPHS

A. Photographic documentation is required prior to the start of any construction. Coverage shall include everything within the construction limits as identified on the Contract Drawings.

B. Include coverage driveways, sidewalks, curbs, ditches (to show drainage patterns), street (as full width as possible), landscaping, trees, shrubs, culverts, catch basins, retaining walls, headwalls, fences, visible utilities, and building exteriors within the zones of influence. Buildings should be identified visibly when possible.

C. Properly identify all photographs by number, date, locations and project name.

3.3 PERIODIC CONSTRUCTION PHOTOGRAPHS

A. Take photographs bi-weekly, with timing each month adjusted to coincide with the cutoff date associated with each Application for Payment. Select vantage points to show status of construction and progress since last photographs were taken.

3.4 FINAL COMPLETION CONSTRUCTION PHOTOGRAPHS

A. Take color photographs after date of Substantial Completion for submission as project record documents. Select vantage points to show status of construction and progress since last photographs were taken.

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Preconstruction photographs.
2. Periodic construction photographs.
3. Web-based construction photographic documentation.
4. Final completion construction photographs.
B. Related Sections:
1. Section 01 33 00 – Submittals: Procedures for submitting photographic documentation.
2. Section 01 77 00 – Closeout Procedures: Procedures for submitting photographic documentation as project record documents at Project closeout.
1.2 SUBMITTALS
A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each photograph. Indicate elevation or story of construction. Include same information as corresponding photographic docu...
B. Digital Photographs: Submit image files within three days of taking photographs.
1. Digital Camera: Minimum sensor resolution of 8 megapixels.
2. Format: JPG with minimum 3200 by 2400 pixels, in unaltered original files, with same aspect ratio as the sensor, uncropped, date and time stamped, in folder named by date of photograph, accompanied by key plan file.
3. Identification: Provide the following information with each image description in file metadata tag:
a. Name of Project.
b. Name and contact information for photographer.
c. Name of Engineer.
d. Name of Contractor.
e. Date photograph was taken.
f. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.
g. Unique sequential identifier keyed to accompanying key plan.
1.3 USAGE RIGHTS
A. Transfer copyright usage rights to Owner for unlimited use and reproduction of photographic documentation.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION
3.1 GENERAL
A. Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted.
1. Maintain key plan with each set of construction photographs that identifies each photographic location.
3.2 PRECONSTRUCTION PHOTOGRAPHS
A. Photographic documentation is required prior to the start of any construction. Coverage shall include everything within the construction limits as identified on the Contract Drawings.
B. Include coverage driveways, sidewalks, curbs, ditches (to show drainage patterns), street (as full width as possible), landscaping, trees, shrubs, culverts, catch basins, retaining walls, headwalls, fences, visible utilities, and building exteriors...
C. Properly identify all photographs by number, date, locations and project name.
3.3 PERIODIC CONSTRUCTION PHOTOGRAPHS
A. Take photographs bi-weekly, with timing each month adjusted to coincide with the cutoff date associated with each Application for Payment. Select vantage points to show status of construction and progress since last photographs were taken.
3.4 FINAL COMPLETION CONSTRUCTION PHOTOGRAPHS
A. Take color photographs after date of Substantial Completion for submission as project record documents. Select vantage points to show status of construction and progress since last photographs were taken.