This is a Project Forms document for the Biosolids Project 011139.0465 prepared by Herbert, Rowland & Grubic, Inc. for Ephrata Borough Authority in Pennsylvania. The project encompasses coordination and interconnection of two new owner-procured biodryers, demolition and replacement of dewatered solids conveyor systems, select wall demolition and replacement, indoor utility replacements, site piping replacement/relocation, a dumpster loading canopy, and associated electrical improvements. Separate bids are requested for two contracts: Contract No. EBA26-2 for General Construction and Contract No. EBA26-3 for Electrical Construction. Bidding documents are available through PennBid at https://pennbid.bonfirehub.com/, with bids due December 8, 2026 at 10:00 AM local time. A pre-bid open house is scheduled for November 18, 2026 from 8:00 AM to 10:00 AM to allow prospective bidders to view the facility.
The document specifies the contractual framework and administrative procedures for the project, utilizing modified EJCDC C-520 agreement and modified EJCDC C-700 general conditions, along with supplementary conditions. Standard preconstruction requirements include performance bonds (EJCDC C-610) and payment bonds (EJCDC C-615). The project will employ standard construction administration forms including Requests for Information, Substitution Request Forms, Field Orders, Work Change Directives, and Change Orders, with an Application for Payment Form for contractor reimbursement. Closeout procedures include Certificate of Substantial Completion, Affidavit of Release of Liens, Consent of Surety to Final Payment, and Notice of Acceptability of Work. All forms will be available in native format through the Project Documentation Website or upon request.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
00 60 00 – PROJECT FORMS
Herbert, Rowland & Grubic, Inc. 00 60 00 - 1 011139.0465
SECTION 00 60 00 – PROJECT FORMS
PART 1 - GENERAL
1.1 FORM OF AGREEMENT AND GENERAL CONDITIONS
A. The following form of Owner/Contractor Agreement and form of the General Conditions shall be used for Project:
1. The Agreement between the Owner and Contractor is included in the Project
Manual, modified EJCDC C-520.
2. The General Conditions are included in the Project Manual, modified EJCDC C-
700.
3. The Supplementary Conditions for Project are incorporated into a modified copy of the General Conditions included in the Project Manual.
1.2 ADMINISTRATIVE FORMS
A. Preconstruction Forms:
1. Performance Bond: Section 00 61 13.13 of Project Manual, EJCDC C-610.
2. Payment Bond: Section 00 61 13.16 of the Project Manual, EJCDC C-615.
B. Information and Modification Forms: The following forms contained in the Project
Manual will be utilized:
1. Requests for Information (RFIs): Section 00 63 13, modified CSI 13.2A.
2. Substitution Request Form (During Construction): Section 00 63 25.
3. Field Order: Section 00 63 36, modified EJCDC C-942.
4. Work Change Directive: Section 00 63 49, modified EJCDC C-940.
5. Change Order Form: Section 00 63 63, modified EJCDC C-941.
6. Forms identified above will be available in their native format will be made available on the Project Documentation Website or upon request.
C. Application for Payment: The following forms contained in the Project Manual will be utilized:
1. Application for Payment Form: Section 00 62 76, EJCDC C-620.
2. Forms identified above will be available in their native format will be made available on the Project Documentation Website or upon request.
D. Closeout Forms: The following forms contained in the Project Manual will be utilized:
1. Certificate of Substantial Completion: Section 00 65 16, modified EJCDC C-625.
2. Affidavit of Release of Liens: Section 00 65 19.16.
3. Consent of Surety to Final Payment: Section 00 65 19.19.
4. Notice of Acceptability of Work: Section 00 65 19.23, modified EJCDC C-626.
END OF SECTION
| PART 1 - GENERAL |
| 1. The Agreement between the Owner and Contractor is included in the Project Manual, modified EJCDC C-520. |
| 2. The General Conditions are included in the Project Manual, modified EJCDC C-700. |
| 3. The Supplementary Conditions for Project are incorporated into a modified copy of the General Conditions included in the Project Manual. |
| 1. Performance Bond: Section 00 61 13.13 of Project Manual, EJCDC C-610. |
| 2. Payment Bond: Section 00 61 13.16 of the Project Manual, EJCDC C-615. |
| 1. Requests for Information (RFIs): Section 00 63 13, modified CSI 13.2A. |
| 2. Substitution Request Form (During Construction): Section 00 63 25. |
| 3. Field Order: Section 00 63 36, modified EJCDC C-942. |
| 4. Work Change Directive: Section 00 63 49, modified EJCDC C-940. |
| 5. Change Order Form: Section 00 63 63, modified EJCDC C-941. |
| 6. Forms identified above will be available in their native format will be made available on the Project Documentation Website or upon request. |
| 1. Application for Payment Form: Section 00 62 76, EJCDC C-620. |
| 2. Forms identified above will be available in their native format will be made available on the Project Documentation Website or upon request. |
| 1. Certificate of Substantial Completion: Section 00 65 16, modified EJCDC C-625. |
| 2. Affidavit of Release of Liens: Section 00 65 19.16. |
| 3. Consent of Surety to Final Payment: Section 00 65 19.19. |
| 4. Notice of Acceptability of Work: Section 00 65 19.23, modified EJCDC C-626. |
| END OF SECTION |