00 60 00 - Project Forms.pdf

PDF 249 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This is a Project Forms document for the Biosolids Project 011139.0465 prepared by Herbert, Rowland & Grubic, Inc. for Ephrata Borough Authority in Pennsylvania. The project encompasses coordination and interconnection of two new owner-procured biodryers, demolition and replacement of dewatered solids conveyor systems, select wall demolition and replacement, indoor utility replacements, site piping replacement/relocation, a dumpster loading canopy, and associated electrical improvements. Separate bids are requested for two contracts: Contract No. EBA26-2 for General Construction and Contract No. EBA26-3 for Electrical Construction. Bidding documents are available through PennBid at https://pennbid.bonfirehub.com/, with bids due December 8, 2026 at 10:00 AM local time. A pre-bid open house is scheduled for November 18, 2026 from 8:00 AM to 10:00 AM to allow prospective bidders to view the facility.

The document specifies the contractual framework and administrative procedures for the project, utilizing modified EJCDC C-520 agreement and modified EJCDC C-700 general conditions, along with supplementary conditions. Standard preconstruction requirements include performance bonds (EJCDC C-610) and payment bonds (EJCDC C-615). The project will employ standard construction administration forms including Requests for Information, Substitution Request Forms, Field Orders, Work Change Directives, and Change Orders, with an Application for Payment Form for contractor reimbursement. Closeout procedures include Certificate of Substantial Completion, Affidavit of Release of Liens, Consent of Surety to Final Payment, and Notice of Acceptability of Work. All forms will be available in native format through the Project Documentation Website or upon request.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00 60 00 – PROJECT FORMS

Herbert, Rowland & Grubic, Inc. 00 60 00 - 1 011139.0465

SECTION 00 60 00 – PROJECT FORMS

PART 1 - GENERAL

1.1 FORM OF AGREEMENT AND GENERAL CONDITIONS

A. The following form of Owner/Contractor Agreement and form of the General Conditions shall be used for Project:

1. The Agreement between the Owner and Contractor is included in the Project

Manual, modified EJCDC C-520.

2. The General Conditions are included in the Project Manual, modified EJCDC C-

700.

3. The Supplementary Conditions for Project are incorporated into a modified copy of the General Conditions included in the Project Manual.

1.2 ADMINISTRATIVE FORMS

A. Preconstruction Forms:

1. Performance Bond: Section 00 61 13.13 of Project Manual, EJCDC C-610.

2. Payment Bond: Section 00 61 13.16 of the Project Manual, EJCDC C-615.

B. Information and Modification Forms: The following forms contained in the Project

Manual will be utilized:

1. Requests for Information (RFIs): Section 00 63 13, modified CSI 13.2A.

2. Substitution Request Form (During Construction): Section 00 63 25.

3. Field Order: Section 00 63 36, modified EJCDC C-942.

4. Work Change Directive: Section 00 63 49, modified EJCDC C-940.

5. Change Order Form: Section 00 63 63, modified EJCDC C-941.

6. Forms identified above will be available in their native format will be made available on the Project Documentation Website or upon request.

C. Application for Payment: The following forms contained in the Project Manual will be utilized:

1. Application for Payment Form: Section 00 62 76, EJCDC C-620.

2. Forms identified above will be available in their native format will be made available on the Project Documentation Website or upon request.

D. Closeout Forms: The following forms contained in the Project Manual will be utilized:

1. Certificate of Substantial Completion: Section 00 65 16, modified EJCDC C-625.

2. Affidavit of Release of Liens: Section 00 65 19.16.

3. Consent of Surety to Final Payment: Section 00 65 19.19.

4. Notice of Acceptability of Work: Section 00 65 19.23, modified EJCDC C-626.

END OF SECTION

PART 1 - GENERAL
1. The Agreement between the Owner and Contractor is included in the Project Manual, modified EJCDC C-520.
2. The General Conditions are included in the Project Manual, modified EJCDC C-700.
3. The Supplementary Conditions for Project are incorporated into a modified copy of the General Conditions included in the Project Manual.
1. Performance Bond: Section 00 61 13.13 of Project Manual, EJCDC C-610.
2. Payment Bond: Section 00 61 13.16 of the Project Manual, EJCDC C-615.
1. Requests for Information (RFIs): Section 00 63 13, modified CSI 13.2A.
2. Substitution Request Form (During Construction): Section 00 63 25.
3. Field Order: Section 00 63 36, modified EJCDC C-942.
4. Work Change Directive: Section 00 63 49, modified EJCDC C-940.
5. Change Order Form: Section 00 63 63, modified EJCDC C-941.
6. Forms identified above will be available in their native format will be made available on the Project Documentation Website or upon request.
1. Application for Payment Form: Section 00 62 76, EJCDC C-620.
2. Forms identified above will be available in their native format will be made available on the Project Documentation Website or upon request.
1. Certificate of Substantial Completion: Section 00 65 16, modified EJCDC C-625.
2. Affidavit of Release of Liens: Section 00 65 19.16.
3. Consent of Surety to Final Payment: Section 00 65 19.19.
4. Notice of Acceptability of Work: Section 00 65 19.23, modified EJCDC C-626.
END OF SECTION