This is a technical specification document for metal railings (Section 05 52 00) prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 at Ephrata Borough Authority in Pennsylvania. The specification details requirements for aluminum handrails, stair rails, and guard rails to be fabricated and installed as part of the broader biosolids facility project. The project involves coordination and interconnection of two new biodryers, demolition and replacement of conveyor systems, wall modifications, utility replacements, site piping work, a dumpster loading canopy, and electrical improvements. Separate contracts are being bid for General Construction (Contract EBA26-2) and Electrical Construction (Contract EBA26-3). Bidding documents are available through PennBid at https://pennbid.bonfirehub.com/, with bids due December 8, 2026 at 10:00 AM local time. A pre-bid open house is scheduled for November 18, 2026 from 8:00 AM to 10:00 AM to allow prospective bidders to view the facility.

The metal railings specification establishes performance and design criteria requiring handrails and guardrails to resist 200-pound concentrated loads and 50 pounds per linear foot uniform loads in any direction, with maximum deflection limited to 5/8 inches. Materials must be aluminum alloys 6061-T6 or 6063-T5/T6 meeting ASTM standards, with components shop-fabricated to minimize field assembly. Installation requirements specify vertical post spacing not exceeding four feet, expansion joints, bituminous paint protection on surfaces contacting dissimilar materials, and tolerances of 1/4 inch maximum for plumb, alignment, and positioning. Fabricators and erectors must demonstrate minimum three years of documented experience, and delegated design submittals must be signed and sealed by a Licensed Professional. The specification references the International Building Code, IBC/ASCE 7 code requirements, AWS welding standards, and ASTM International specifications for materials and fabrication quality assurance.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

05 52 00 - METAL RAILINGS

Herbert, Rowland & Grubic, Inc. 05 52 00 - 1 011139.0465

SECTION 05 52 00 - METAL RAILINGS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Aluminum Handrail.

2. Aluminum Stair Rail.

3. Aluminum Guard Rail.

B. Related Requirements:

1. Section 03 30 00 - Cast-In-Place Concrete: Execution requirements for placement of anchors, as specified in this Section, in concrete.

2. Section 05 51 00 - Metal Stairs: Handrails other than those specified in this

Section.

3. Section 09 90 00 - Painting and Coating: Paint finish.

1.2 REFERENCE STANDARDS

A. ASTM International:

1. ASTM B108, Standard Specification for Aluminum-Alloy Permanent Mold Castings

2. ASTM B209, Standard Specification for Aluminum and Aluminum-Alloy Sheet and

Plate

3. ASTM B221, Standard Specification for Aluminum-Alloy. Extruded Bars, Rods, Wire, Shapes, and Tubes

4. ASTM B247, Standard Specification for Aluminum-Alloy Die Forgings, Hand

Forgings, and Rolled Ring Forgings

5. ASTM B308, Standard Specification for Aluminum-Alloy 6061-T6 Standard

Structural Shapes

6. ASTM B429, Standard Specification for Aluminum-Alloy Extruded Structural Pipe and Tube

B. ADM-1, Aluminum Design Manual, current edition.

C. National Association of Architectural Metal Manufacturers:

1. NAAMM Metal Finishes Manual.

1.3 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Shop Drawings: Indicate profiles, sizes, connection attachments, anchorage, size and type of fasteners, and accessories.

C. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.

D. Delegated Design Submittals: Submit Shop Drawings with design calculations, Herbert, Rowland & Grubic, Inc. 05 52 00 - 2 011139.0465 assumptions, and full load path for all elements signed and sealed by a Licensed Professional in the projects Jurisdiction.

E. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections.

F. Qualifications Statements:

1. Submit qualifications for fabricator and erector.

2. Submit manufacturer's approval of fabricator and erector.

1.4 QUALITY ASSURANCE

A. Perform Work of this Section according to ASTM E985.

B. Finish joints according to NOMMA Guideline 1.

1.5 QUALIFICATIONS

A. Fabricator: Company specializing in fabricating products specified in this Section with minimum three years' documented experience.

B. Erector: Company specializing in performing Work of this Section with minimum three years' documented experience.

PART 2 - PRODUCTS

2.1 PERFORMANCE AND DESIGN CRITERIA

A. Design handrail, guardrail, and attachments to resist forces as required by applicable IBC/ASCE 7 code. Apply loads non-simultaneously to produce maximum stresses.

1. Guard Top Rail and Handrail Concentrated Load: 200 lb. applied at any point in any direction.

2. Guard Top Rail and Handrail Uniform Load: 50 plf applied in any direction.

3. Intermediate Rails, Panels, and Baluster Concentrated Load: 50 lb. applied to 1

sq. ft. area.

4. Deflection: Limit deflection of railings to 5/8” maximum at top of railing system.

2.2 MATERIALS

A. Aluminum Railing System:

1. Alloy 6061-T6, 32,000 psi tensile yield strength minimum.

a. ASTM B209 for sheets and plates.

b. ASTM B221 and ASTM B308 for shapes - beams, channels, angles, tees, and zees.

c. ASTM B247 for forgings.

2. Alloy 6063-T5 or T6, 15,000 psi tensile yield strength minimum. ASTM B221 and ASTM B429 for bars, rods, wires, pipes and tubes:

3. Cast Fittings: Aluminum, ASTM B108.

Herbert, Rowland & Grubic, Inc. 05 52 00 - 3 011139.0465

4. Shims: Aluminum of same alloy as component being shimmed.

5. Electrodes for Welding:

a. Aluminum: AWS D1.2.

b. Filler alloy 5356 or 4043. Use 5356 on members that will be anodized.

6. Accessories:

a. Bituminous paint: Cold-applied asphalt mastic complying with SSPC-Paint 12, except containing no asbestos fibers, or cold-applied asphalt emulsion complying with ASTM D1187.

2.3 FABRICATION

A. General

1. Fit and shop-assemble components in largest practical sizes for delivery to Site.

2. For fabrication of items which will be exposed to view, use only materials which are smooth and free of surface blemishes including pitting, seam marks, roller marks, rolled trade names and roughness. Remove blemishes by grinding and buffing or by welding and grinding, prior to cleaning, treating and application of surface finishes.

3. Form exposed work with smooth, short radius bends, accurate angles and straight edges. Ease exposed edges to a radius of approximately 1/32”. Form bent-metal comers to smallest radius possible without causing grain separation or otherwise impairing work. Drill or punch holes with smooth edges.

4. Form exposed connections with flush, smooth, hairline joints, using stainless steel or aluminum splice locks to splice sections together or by welding. Top rail splices and expansion joints shall be located within 8” of post or other support. Ease the edges of top rail splices and expansion joints and remove all burrs left from cutting.

5. Provide for anchorage of type indicated on Drawings or as required by field conditions. Drill or punch holes with smooth edges.

6. Design railing, supports, and anchorage system to withstand:

a. Handrails and guardrails shall be designed to resist a load of 50 PLF applied in any direction at the top of the handrail or guardrail and shall transfer that load through the supports to the structure.

b. Handrails and guardrails shall be designed to resist a single 200 lb.

concentrated load applied at any point in any direction to top of rail system and to transfer this load through the supports to the structure.

This load need not be assumed to act concurrently with the loads specified in ‘a’ above.

c. Intermediate rails shall be designed to withstand a horizontally applied normal load of 50 lb. on an area not to exceed one square foot including openings and space between rails. Reactions due to this loading are not required to be superimposed with those of ‘a’ or ‘b’ above.

d. 100 PLF vertical and 50 PLF horizontal uniform loads applied simultaneously to the top rail of the guardrail.

e. A load of 25 PSF applied horizontally at right angles over the entire tributary area including openings and spaces between rails.

f. Loading conditions need not act concurrently.

Herbert, Rowland & Grubic, Inc. 05 52 00 - 4 011139.0465

g. Maximum post spacing is four (4) feet.

7. Custom fabricate railings to dimensions and profiles as follows:

a. Fabricate handrail and handrail posts using 1-1/4” or 1-1/2” nominal DIA aluminum Schedule 40 pipe (or heavier).

b. Fabricate all guardrail top and bottom rails using 1-1/2” or 2” nominal aluminum tubing, Schedule 40 or heavier.

c. Fabricate all guardrail vertical posts using 1-1/2” or 2” nominal aluminum tubing, Schedule 80 or heavier.

1) Guardrail vertical posts that are to be side-bracket mounted to a vertical concrete surface or metal structure shall use Alloy 6063- T6.

d. All intermediate guard rails shall be fabricated using aluminum tubing of a diameter to match top and bottom rail width.

e. Base plate for vertical guardrail post mounted to flange of metal structure:

1) 3/8x3x8”plate.

2) Predrilled to accept two fasteners.

3) Provide an 8” long solid aluminum bar welded to the base plate.

Size bar to fit snug to inside of post tube.

4) Fit the vertical post over the solid rod and weld the post to the base plate.

f. Mounting bracket for vertical guardrail post mounted to vertical concrete surface or web of metal structural member:

1) Pair of 3/8” angles or bent plates.

2) Predrilled to accept two fasteners each.

3) Weld angles or bent plates to vertical posts.

g. Provide 1/8” x 4” flat bar toe-boards or ¼” minimum thickness x 4” high extruded toe-boards with stiffener ribs on the back side at all elevated walkways, platforms and stair landings, and where indicated on the Drawings or required by OSHA Standards.

8. Fit exposed ends of guardrails and handrails with solid terminations.

a. Return ends of handrail to wall, but do not attach to wall.

b. Where guardrail terminates at a wall provide a vertical post located 4” off the wall to center of post.

9. Preassemble items in shop to greatest extent possible to minimize field splicing and assembly of units at project site.

B. Finish: Aluminum Association Anodized Architectural Class I, A41, clear.

C. Welded Railing Fabrication: All welding to be continuous in accordance with AWS C5.5 and AWS D1.2. All welded railing joints shall have full penetration welds unless noted otherwise. All exposed welds to be ground and buffed smooth and flush to match and blend with adjoining surfaces. No ragged edges, surface defects, or undercutting of adjoining surfaces will be accepted. Finishing joints with filler is not acceptable.

D. Install weeps to drain water from hollow sections of railing at exterior and high humidity conditions.

1. Drill ¼” weep hole in railings closed at bottom:

Herbert, Rowland & Grubic, Inc. 05 52 00 - 5 011139.0465

a. 1” above walkway surface at bottom of posts set in concrete.

b. 1” above solid aluminum rod at posts having base plate.

c. At low point of intermediate rails.

2. Do not drill weep holes in bottom of base plate.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.

B. Verify that field conditions are acceptable and are ready to receive Work.

3.2 PREPARATION

A. Section 01 73 00 - Execution Requirements: Requirements for installation preparation.

3.3 INSTALLATION

A. Install handrails and guardrails to meet loading requirements of the International Building Code and as specified above.

B. Install products in accordance with manufacturer’s instructions.

C. Set work accurately in location, alignment and elevation; plumb, level and true. Handrail slope to match slope of stairs. Guard Rails are to slope parallel to supporting surface.

Measure from established lines and items which are to be built into concrete, masonry or similar construction.

D. Align railings prior to securing in place to assure proper matching at butting and expansion joints and correct alignment throughout their length.

1. Space vertical posts as required by loading requirements but not more than 4 ft.

on center.

2. Provide shims as required.

E. Install proper sized expansion joints based on temperature at time of installation and differential coefficient of expansion of materials in all railings as recommended by manufacturer. Joints to be designed to allow expansion and contraction of railing and still meet design loads required.

F. Provide removable railing sections where indicated on Drawings.

G. Attach handrails to guardrail with brackets designed for condition:

1. Provide brackets which provide a minimum 1-1/2” clearance between handrail and nearest obstruction.

2. Handrails shall not project more than 3-1/2” into required stairway width.

H. Anchor railings to concrete with minimum ½” stainless steel adhesive anchors with stainless steel bolts, nuts and washers unless noted otherwise in the Contract Documents.

Herbert, Rowland & Grubic, Inc. 05 52 00 - 6 011139.0465

Where exposed, bolts shall extend minimum ½” and maximum ¾”above the top nut. If bolts are cut off to required height, threads must be dressed to allow nuts to be removed without damage to the bolt or the nut. Bevel the top of the bolt after cutting to provide a smooth surface.

I. Anchor railing to metal structure with minimum ¾” stainless steel bolts, nuts and washers.

J. Apply a heavy coat of bituminous paint to all aluminum surfaces that will contact concrete or dissimilar materials such as steel. Another insulating or dielectric material may be used if approved by the Engineer. Install components plumb and level, accurately fitted, free from distortion or defects.

3.4 TOLERANCES

A. Section 01 40 00 - Quality Requirements: Requirements for tolerances.

B. Maximum Variation from Plumb: 1/4 inch.

C. Maximum Offset from Alignment: 1/4 inch.

D. Maximum Out-of-Position: 1/4 inch.

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Aluminum Handrail.
2. Aluminum Stair Rail.
3. Aluminum Guard Rail.
B. Related Requirements:
1. Section 03 30 00 - Cast-In-Place Concrete: Execution requirements for placement of anchors, as specified in this Section, in concrete.
2. Section 05 51 00 - Metal Stairs: Handrails other than those specified in this Section.
3. Section 09 90 00 - Painting and Coating: Paint finish.
1.2 REFERENCE STANDARDS
A. ASTM International:
1. ASTM B108, Standard Specification for Aluminum-Alloy Permanent Mold Castings
2. ASTM B209, Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate
3. ASTM B221, Standard Specification for Aluminum-Alloy. Extruded Bars, Rods, Wire, Shapes, and Tubes
4. ASTM B247, Standard Specification for Aluminum-Alloy Die Forgings, Hand Forgings, and Rolled Ring Forgings
5. ASTM B308, Standard Specification for Aluminum-Alloy 6061-T6 Standard Structural Shapes
6. ASTM B429, Standard Specification for Aluminum-Alloy Extruded Structural Pipe and Tube
B. ADM-1, Aluminum Design Manual, current edition.
C. National Association of Architectural Metal Manufacturers:
1. NAAMM Metal Finishes Manual.
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Shop Drawings: Indicate profiles, sizes, connection attachments, anchorage, size and type of fasteners, and accessories.
C. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.
D. Delegated Design Submittals: Submit Shop Drawings with design calculations, assumptions, and full load path for all elements signed and sealed by a Licensed Professional in the projects Jurisdiction.
E. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections.
F. Qualifications Statements:
1. Submit qualifications for fabricator and erector.
2. Submit manufacturer's approval of fabricator and erector.
1.4 QUALITY ASSURANCE
A. Perform Work of this Section according to ASTM E985.
B. Finish joints according to NOMMA Guideline 1.
1.5 QUALIFICATIONS
A. Fabricator: Company specializing in fabricating products specified in this Section with minimum three years' documented experience.
B. Erector: Company specializing in performing Work of this Section with minimum three years' documented experience.
PART 2 - PRODUCTS
2.1 PERFORMANCE AND DESIGN CRITERIA
A. Design handrail, guardrail, and attachments to resist forces as required by applicable IBC/ASCE 7 code. Apply loads non-simultaneously to produce maximum stresses.
1. Guard Top Rail and Handrail Concentrated Load: 200 lb. applied at any point in any direction.
2. Guard Top Rail and Handrail Uniform Load: 50 plf applied in any direction.
3. Intermediate Rails, Panels, and Baluster Concentrated Load: 50 lb. applied to 1 sq. ft. area.
4. Deflection: Limit deflection of railings to 5/8” maximum at top of railing system.
2.2 MATERIALS
A. Aluminum Railing System:
a. ASTM B209 for sheets and plates.
b. ASTM B221 and ASTM B308 for shapes - beams, channels, angles, tees, and zees.
c. ASTM B247 for forgings.
2. Alloy 6063-T5 or T6, 15,000 psi tensile yield strength minimum. ASTM B221 and ASTM B429 for bars, rods, wires, pipes and tubes:
3. Cast Fittings: Aluminum, ASTM B108.
4. Shims: Aluminum of same alloy as component being shimmed.
5. Electrodes for Welding:
a. Aluminum: AWS D1.2.
b. Filler alloy 5356 or 4043. Use 5356 on members that will be anodized.
6. Accessories:
a. Bituminous paint: Cold-applied asphalt mastic complying with SSPC-Paint 12, except containing no asbestos fibers, or cold-applied asphalt emulsion complying with ASTM D1187.
2.3 FABRICATION
A. General
1. Fit and shop-assemble components in largest practical sizes for delivery to Site.
2. For fabrication of items which will be exposed to view, use only materials which are smooth and free of surface blemishes including pitting, seam marks, roller marks, rolled trade names and roughness. Remove blemishes by grinding and buffing or by...
3. Form exposed work with smooth, short radius bends, accurate angles and straight edges. Ease exposed edges to a radius of approximately 1/32”. Form bent-metal comers to smallest radius possible without causing grain separation or otherwise impairi...
4. Form exposed connections with flush, smooth, hairline joints, using stainless steel or aluminum splice locks to splice sections together or by welding. Top rail splices and expansion joints shall be located within 8” of post or other support. Ease ...
5. Provide for anchorage of type indicated on Drawings or as required by field conditions. Drill or punch holes with smooth edges.
6. Design railing, supports, and anchorage system to withstand:
a. Handrails and guardrails shall be designed to resist a load of 50 PLF applied in any direction at the top of the handrail or guardrail and shall transfer that load through the supports to the structure.
b. Handrails and guardrails shall be designed to resist a single 200 lb. concentrated load applied at any point in any direction to top of rail system and to transfer this load through the supports to the structure. This load need not be assumed to a...
c. Intermediate rails shall be designed to withstand a horizontally applied normal load of 50 lb. on an area not to exceed one square foot including openings and space between rails. Reactions due to this loading are not required to be superimposed wi...
d. 100 PLF vertical and 50 PLF horizontal uniform loads applied simultaneously to the top rail of the guardrail.
e. A load of 25 PSF applied horizontally at right angles over the entire tributary area including openings and spaces between rails.
f. Loading conditions need not act concurrently.
g. Maximum post spacing is four (4) feet.
7. Custom fabricate railings to dimensions and profiles as follows:
a. Fabricate handrail and handrail posts using 1-1/4” or 1-1/2” nominal DIA aluminum Schedule 40 pipe (or heavier).
b. Fabricate all guardrail top and bottom rails using 1-1/2” or 2” nominal aluminum tubing, Schedule 40 or heavier.
c. Fabricate all guardrail vertical posts using 1-1/2” or 2” nominal aluminum tubing, Schedule 80 or heavier.
1) Guardrail vertical posts that are to be side-bracket mounted to a vertical concrete surface or metal structure shall use Alloy 6063-T6.
d. All intermediate guard rails shall be fabricated using aluminum tubing of a diameter to match top and bottom rail width.
e. Base plate for vertical guardrail post mounted to flange of metal structure:
1) 3/8x3x8”plate.
2) Predrilled to accept two fasteners.
3) Provide an 8” long solid aluminum bar welded to the base plate. Size bar to fit snug to inside of post tube.
4) Fit the vertical post over the solid rod and weld the post to the base plate.
f. Mounting bracket for vertical guardrail post mounted to vertical concrete surface or web of metal structural member:
1) Pair of 3/8” angles or bent plates.
2) Predrilled to accept two fasteners each.
3) Weld angles or bent plates to vertical posts.

g. Provide 1/8” x 4” flat bar toe-boards or ¼” minimum thickness x 4” high extruded toe-boards with stiffener ribs on the back side at all elevated walkways, platforms and stair landings, and where indicated on the Drawings or required by OSHA Standards.

8. Fit exposed ends of guardrails and handrails with solid terminations.
a. Return ends of handrail to wall, but do not attach to wall.
b. Where guardrail terminates at a wall provide a vertical post located 4” off the wall to center of post.

9. Preassemble items in shop to greatest extent possible to minimize field splicing and assembly of units at project site.

B. Finish: Aluminum Association Anodized Architectural Class I, A41, clear.
C. Welded Railing Fabrication: All welding to be continuous in accordance with AWS C5.5 and AWS D1.2. All welded railing joints shall have full penetration welds unless noted otherwise. All exposed welds to be ground and buffed smooth and flush to ...
D. Install weeps to drain water from hollow sections of railing at exterior and high humidity conditions.
1. Drill ¼” weep hole in railings closed at bottom:
a. 1” above walkway surface at bottom of posts set in concrete.
b. 1” above solid aluminum rod at posts having base plate.
c. At low point of intermediate rails.

2. Do not drill weep holes in bottom of base plate.

PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.
B. Verify that field conditions are acceptable and are ready to receive Work.
3.2 PREPARATION
A. Section 01 73 00 - Execution Requirements: Requirements for installation preparation.
3.3 INSTALLATION
A. Install handrails and guardrails to meet loading requirements of the International Building Code and as specified above.
B. Install products in accordance with manufacturer’s instructions.
C. Set work accurately in location, alignment and elevation; plumb, level and true. Handrail slope to match slope of stairs. Guard Rails are to slope parallel to supporting surface. Measure from established lines and items which are to be built int...
D. Align railings prior to securing in place to assure proper matching at butting and expansion joints and correct alignment throughout their length.
1. Space vertical posts as required by loading requirements but not more than 4 ft. on center.
2. Provide shims as required.
E. Install proper sized expansion joints based on temperature at time of installation and differential coefficient of expansion of materials in all railings as recommended by manufacturer. Joints to be designed to allow expansion and contraction of ra...
F. Provide removable railing sections where indicated on Drawings.
G. Attach handrails to guardrail with brackets designed for condition:
1. Provide brackets which provide a minimum 1-1/2” clearance between handrail and nearest obstruction.
2. Handrails shall not project more than 3-1/2” into required stairway width.
H. Anchor railings to concrete with minimum ½” stainless steel adhesive anchors with stainless steel bolts, nuts and washers unless noted otherwise in the Contract Documents. Where exposed, bolts shall extend minimum ½” and maximum ¾”above the top nu...
I. Anchor railing to metal structure with minimum ¾” stainless steel bolts, nuts and washers.
J. Apply a heavy coat of bituminous paint to all aluminum surfaces that will contact concrete or dissimilar materials such as steel. Another insulating or dielectric material may be used if approved by the Engineer. Install components plumb and level...
3.4 TOLERANCES
A. Section 01 40 00 - Quality Requirements: Requirements for tolerances.
B. Maximum Variation from Plumb: 1/4 inch.
C. Maximum Offset from Alignment: 1/4 inch.
D. Maximum Out-of-Position: 1/4 inch.

File details come from the government source that posted it. Updated .