31 25 00 - Erosion And Sedimentation Controls.pdf

PDF 224 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This is a technical specification document for Erosion and Sedimentation Controls prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 in Ephrata Borough, Lancaster County, Pennsylvania. The specification outlines mandatory erosion control requirements that the contractor must implement to minimize soil erosion, sedimentation, and stormwater pollution during and after construction. The work must comply with Pennsylvania Department of Environmental Protection regulations and Lancaster County Conservation District requirements, with any fines or costs resulting from inadequate erosion protection to be borne by the contractor. Key execution requirements include installation of sediment barriers such as compost filter socks and weighted sediment filter tubes placed parallel to contours with proper anchoring; limitation of stockpile and waste pile heights to 35 feet with 2:1 or flatter slopes; stabilization of disturbed areas remaining exposed for more than 20 days; weekly inspection of erosion control devices and inspections following each runoff event; and removal of accumulated sediment when sedimentation structures reach one-third depth capacity or when channel sediment reaches approximately one-half channel depth.

The specification does not address pricing, set-asides, or contract award information, as it functions as a technical requirements document incorporated into the overall Biosolids Project bidding process. The document references additional contract sections for submittal procedures, quality requirements, and execution standards, establishing that all work must be verified, properly documented through manufacturer certifications, and maintained in good working order throughout the construction period. The contractor is responsible for implementing additional erosion controls beyond those shown in contract drawings if problem areas develop during construction.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

31 25 00 – EROSION AND SEDIMENTATION CONTROLS

Herbert, Rowland & Grubic, Inc. 31 25 00-1 011139.0465

SECTION 31 25 00 - EROSION AND SEDIMENTATION CONTROLS

PART 1 – GENERAL

1.1 EROSION AND SEDIMENTATION CONTROLS

A. Purpose: The purpose of this Erosion and Sedimentation Controls is to provide the Contractor with general guidelines as well as specific techniques for minimizing erosion and sedimentation and stormwater pollution during and after construction of the project.

B. Project location is in Ephrata Borough, Lancaster County, Pennsylvania as shown on the

Contract Drawings.

C. Additional controls may be required at problem areas that develop during construction above and beyond those included in the Contract Drawings.

1.2 QUALITY ASSURANCE

A. Regulatory agency requirements.

1. The Contractor is advised that all work will be completed in compliance with the requirements of the details and the rules and regulations of the Pennsylvania Department of Environmental Protection and the Lancaster County Conservation District. Any fines and associated costs resulting from the Contractor's failure to provide adequate protection against soil erosion and sedimentation shall be borne by the Contractor.

1.3 SUBMITTALS

A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.

B. Product Data: Product Data: Submit data on geotextile and sediment barriers.

C. Manufacturer's Certificate: Certify Products meet or exceed specified requirements.

PART 2 – PRODUCTS - MATERIALS: (See Contract Drawings).

PART 3 – EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 – Execution Requirements: Verification of existing conditions before starting work.

B. Verify compacted subgrade or stabilized soil is acceptable and ready to support devices and imposed loads.

C. Verify gradients and elevations of base or foundation for other work are correct.

Herbert, Rowland & Grubic, Inc. 31 25 00-2 011139.0465

3.2 SEDIMENT BARRIERS

A. Compost Filter Socks and Weighted Sediment Filter Tubes:

1. Prepare placement area by removing all debris.

2. Place parallel to contour with both ends of the sock extended upslope at a 45 degree angle to the rest of the sock to prevent end-arounds.

3. Socks placed on earthen slopes should be anchored with stakes driven through the center of the sock or immediately downslope of the sock at intervals recommended by the manufacturer.

4. Where socks are placed on paved surfaces, concrete blocks should be used immediately downslope of the socks (at the same intervals recommended for the stakes) to help hold the sock in place.

3.3 SITE STABILIZATION

A. Incorporate erosion control devices indicated on the Drawings into the Project at the earliest practicable time.

B. Construct, stabilize and activate erosion controls before site disturbance within tributary areas of those controls.

C. Stockpile and waste pile heights shall not exceed 35 feet. Slope stockpile sides at 2:1 or flatter.

D. Stabilize any disturbed area of affected erosion control devices on which activity has ceased and which will remain exposed for more than 20 days:

1. During non-germinating periods, apply mulch at recommended rates.

2. Stabilize disturbed areas which are not at finished grade and which will be disturbed within one year.

3. Stabilize disturbed areas which are either at finished grade or will not be disturbed within one year in accordance with Section 32 92 19 – Seeding.

E. Stabilize stockpiles immediately.

3.4 FIELD QUALITY CONTROL

A. Section 01 40 00 – Quality Requirements: Field inspecting, testing, adjusting, and balancing.

B. Inspect erosion control devices on a weekly basis and after each runoff event. Make necessary repairs to ensure erosion and sediment controls are in good working order.

3.5 CLEANING

A. Section 01 73 00 – Execution Requirements: Requirements for cleaning.

B. When sediment accumulation in sedimentation structures has reached a point one-third depth of sediment structure or device, remove and dispose of sediment.

C. Do not damage structure or device during cleaning operations.

Herbert, Rowland & Grubic, Inc. 31 25 00-3 011139.0465

D. Do not permit sediment to erode into construction or site areas or natural waterways.

E. Clean channels when depth of sediment reaches approximately one-half channel depth.

3.6 PROTECTION

A. Section 01 73 00 – Execution Requirements: Requirements for protecting finished Work.

END OF SECTION

A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.
B. Product Data: Product Data: Submit data on geotextile and sediment barriers.
C. Manufacturer's Certificate: Certify Products meet or exceed specified requirements.
PART 3 – EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 – Execution Requirements: Verification of existing conditions before starting work.
B. Verify compacted subgrade or stabilized soil is acceptable and ready to support devices and imposed loads.
C. Verify gradients and elevations of base or foundation for other work are correct.
3.2 SEDIMENT BARRIERS
A. Compost Filter Socks and Weighted Sediment Filter Tubes:
1. Prepare placement area by removing all debris.
2. Place parallel to contour with both ends of the sock extended upslope at a 45 degree angle to the rest of the sock to prevent end-arounds.
3. Socks placed on earthen slopes should be anchored with stakes driven through the center of the sock or immediately downslope of the sock at intervals recommended by the manufacturer.
4. Where socks are placed on paved surfaces, concrete blocks should be used immediately downslope of the socks (at the same intervals recommended for the stakes) to help hold the sock in place.
3.3 SITE STABILIZATION
A. Incorporate erosion control devices indicated on the Drawings into the Project at the earliest practicable time.
B. Construct, stabilize and activate erosion controls before site disturbance within tributary areas of those controls.
C. Stockpile and waste pile heights shall not exceed 35 feet. Slope stockpile sides at 2:1 or flatter.
D. Stabilize any disturbed area of affected erosion control devices on which activity has ceased and which will remain exposed for more than 20 days:
1. During non-germinating periods, apply mulch at recommended rates.
2. Stabilize disturbed areas which are not at finished grade and which will be disturbed within one year.
3. Stabilize disturbed areas which are either at finished grade or will not be disturbed within one year in accordance with Section 32 92 19 – Seeding.

E. Stabilize stockpiles immediately.

3.4 FIELD QUALITY CONTROL
A. Section 01 40 00 – Quality Requirements: Field inspecting, testing, adjusting, and balancing.
B. Inspect erosion control devices on a weekly basis and after each runoff event. Make necessary repairs to ensure erosion and sediment controls are in good working order.
3.5 CLEANING
A. Section 01 73 00 – Execution Requirements: Requirements for cleaning.
B. When sediment accumulation in sedimentation structures has reached a point one-third depth of sediment structure or device, remove and dispose of sediment.
C. Do not damage structure or device during cleaning operations.
D. Do not permit sediment to erode into construction or site areas or natural waterways.
E. Clean channels when depth of sediment reaches approximately one-half channel depth.
3.6 PROTECTION
A. Section 01 73 00 – Execution Requirements: Requirements for protecting finished Work.

File details come from the government source that posted it. Updated .