This file is a specification section for project meetings prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 in Ephrata Borough Authority, Pennsylvania. The specification establishes requirements for three types of meetings: a preconstruction meeting scheduled by the Engineer after Notice of Award and prior to work commencement, progress meetings administered by the Engineer at maximum monthly intervals throughout the project duration, and pre-installation meetings required before starting work on specific specification sections. The preconstruction meeting requires attendance from the Engineer, Owner, Resident Project Representative, Owner Procured Equipment Representative, and Contractor representatives vested with decision-making authority. The meeting agenda encompasses 22 items including contract times, site access, permits, shop drawings, prevailing wage certifications, insurance requirements, and safety protocols. Progress meetings require attendance from contractors, job superintendent, major subcontractors and suppliers, the Engineer, and the Owner, with a minimum agenda of ten items focused on work progress, schedule maintenance, quality standards, and coordination. The Engineer is responsible for recording minutes and distributing copies to all participants within two days of each meeting.
The specification does not address pricing terms, set-asides, or funding information, as this section is limited to procedural meeting requirements. The document is part of the bidding documents for the Biosolids Project, which includes general construction (Contract No. EBA26-2) and electrical construction (Contract No. EBA26-3) components. Bidding documents are available through PennBid at https://pennbid.bonfirehub.com/, with bids due December 8, 2026 at 10:00 AM local time. A pre-bid open house is scheduled for November 18, 2026 from 8:00 AM to 10:00 AM to allow bidders to view the facility.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 31 19 - PROJECT MEETINGS
Herbert, Rowland & Grubic, Inc. 01 31 19 - 1 011139.0465
SECTION 01 31 19 - PROJECT MEETINGS
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Preconstruction meeting.
B. Progress meetings.
C. Pre-installation meetings.
1.2 PRECONSTRUCTION MEETING
A. Engineer will schedule and preside over meeting after Notice of Award and prior to commencement of Work at the site.
B. Attendance Required: Engineer, Owner, Resident Project Representative, Owner Procured Equipment Representative, and Contractor.
1. Contractor representation: person vested with the authority to make necessary decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules.
C. Agenda:
1. Engineer's Status During Construction.
2. Resident Project Representative (RPR).
3. Project Communication Procedures.
4. Contract Times.
5. Project Site: Access and Rights-of-Way.
6. Permits and Approvals.
7. Field Engineering.
8. Changes in the Work procedures.
9. Work Schedule.
10. Shop Drawings.
11. Substitutions.
12. Job Conference Schedule.
13. Payment Applications.
14. Temporary Utilities.
15. Emergency Phone Numbers.
16. Field Office Facilities.
17. Subcontractors.
18. Prevailing Wage and Payroll Certifications.
19. Insurances.
20. Steel Products Procurement Act Certifications.
21. Safety and OSHA.
22. Control of Work.
Herbert, Rowland & Grubic, Inc. 01 31 19 - 2 011139.0465
D. Engineer will record minutes and distribute copies to participants, with copies each to Contractor(s), Owner, and those affected by decisions made.
1.3 PROGRESS MEETINGS
A. Engineer will schedule and administer meetings throughout progress of the Work at maximum monthly intervals.
B. Attendance Required: Contractors and job superintendent, major Subcontractors and suppliers, Engineer, and Owner.
1. Contractors representative shall be vested with the authority to make any decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules
C. Minimum Agenda:
1. Review minutes of previous meetings.
2. Review of Work progress.
3. Planned progress during succeeding work period.
4. Maintenance of Progress Schedule.
5. Field observations, problems, and decisions.
6. Identification of problems impeding planned progress.
7. Review of submittal schedule and status of submittals.
8. Coordination of projected progress.
9. Maintenance of quality and work standards.
10. Other business relating to Work.
D. Engineer will record minutes and distribute copies to participants within two days after meeting, electronic copies each to Engineer, Owner, and those affected by decisions made.
1.4 PREINSTALLATION MEETINGS
A. When required in individual Specification Sections, convene pre-installation meetings at Project Site before starting Work of specific Section.
B. Require attendance of parties directly affecting, or affected by, Work of specific Section.
C. Notify Engineer fourteen days in advance of meeting date.
D. Prepare agenda and preside over meeting:
1. Review conditions of installation, preparation, and installation procedures.
2. Review coordination with related Work.
E. Record minutes and distribute copies to participants within two days after meeting, to Engineer, Owner, and those affected by decisions made.
Herbert, Rowland & Grubic, Inc. 01 31 19 - 3 011139.0465
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION – Not Used.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SECTION INCLUDES |
| A. Preconstruction meeting. |
| B. Progress meetings. |
| C. Pre-installation meetings. |
| 1.2 PRECONSTRUCTION MEETING |
| A. Engineer will schedule and preside over meeting after Notice of Award and prior to commencement of Work at the site. |
| B. Attendance Required: Engineer, Owner, Resident Project Representative, Owner Procured Equipment Representative, and Contractor. |
| 1. Contractor representation: person vested with the authority to make necessary decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules. |
| C. Agenda: |
| 1. Engineer's Status During Construction. |
| 2. Resident Project Representative (RPR). |
| 3. Project Communication Procedures. |
| 4. Contract Times. |
| 5. Project Site: Access and Rights-of-Way. |
| 6. Permits and Approvals. |
| 7. Field Engineering. |
| 8. Changes in the Work procedures. |
| 9. Work Schedule. |
| 10. Shop Drawings. |
| 11. Substitutions. |
| 12. Job Conference Schedule. |
| 13. Payment Applications. |
| 14. Temporary Utilities. |
| 15. Emergency Phone Numbers. |
| 16. Field Office Facilities. |
| 17. Subcontractors. |
| 18. Prevailing Wage and Payroll Certifications. |
| 19. Insurances. |
| 20. Steel Products Procurement Act Certifications. |
| 21. Safety and OSHA. |
| 22. Control of Work. |
D. Engineer will record minutes and distribute copies to participants, with copies each to Contractor(s), Owner, and those affected by decisions made.
| 1.3 PROGRESS MEETINGS |
| A. Engineer will schedule and administer meetings throughout progress of the Work at maximum monthly intervals. |
| B. Attendance Required: Contractors and job superintendent, major Subcontractors and suppliers, Engineer, and Owner. |
| 1. Contractors representative shall be vested with the authority to make any decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules |
| C. Minimum Agenda: |
| 1. Review minutes of previous meetings. |
| 2. Review of Work progress. |
| 3. Planned progress during succeeding work period. |
| 4. Maintenance of Progress Schedule. |
| 5. Field observations, problems, and decisions. |
| 6. Identification of problems impeding planned progress. |
| 7. Review of submittal schedule and status of submittals. |
| 8. Coordination of projected progress. |
| 9. Maintenance of quality and work standards. |
| 10. Other business relating to Work. |
D. Engineer will record minutes and distribute copies to participants within two days after meeting, electronic copies each to Engineer, Owner, and those affected by decisions made.
| 1.4 PREINSTALLATION MEETINGS |
| A. When required in individual Specification Sections, convene pre-installation meetings at Project Site before starting Work of specific Section. |
| B. Require attendance of parties directly affecting, or affected by, Work of specific Section. |
| C. Notify Engineer fourteen days in advance of meeting date. |
| D. Prepare agenda and preside over meeting: |
| 1. Review conditions of installation, preparation, and installation procedures. |
| 2. Review coordination with related Work. |
E. Record minutes and distribute copies to participants within two days after meeting, to Engineer, Owner, and those affected by decisions made.
| PART 2 - PRODUCTS - Not Used. |
| PART 3 - EXECUTION – Not Used. |