01 31 19 - Project Meetings.pdf

PDF 228 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This file is a specification section for project meetings prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 in Ephrata Borough Authority, Pennsylvania. The specification establishes requirements for three types of meetings: a preconstruction meeting scheduled by the Engineer after Notice of Award and prior to work commencement, progress meetings administered by the Engineer at maximum monthly intervals throughout the project duration, and pre-installation meetings required before starting work on specific specification sections. The preconstruction meeting requires attendance from the Engineer, Owner, Resident Project Representative, Owner Procured Equipment Representative, and Contractor representatives vested with decision-making authority. The meeting agenda encompasses 22 items including contract times, site access, permits, shop drawings, prevailing wage certifications, insurance requirements, and safety protocols. Progress meetings require attendance from contractors, job superintendent, major subcontractors and suppliers, the Engineer, and the Owner, with a minimum agenda of ten items focused on work progress, schedule maintenance, quality standards, and coordination. The Engineer is responsible for recording minutes and distributing copies to all participants within two days of each meeting.

The specification does not address pricing terms, set-asides, or funding information, as this section is limited to procedural meeting requirements. The document is part of the bidding documents for the Biosolids Project, which includes general construction (Contract No. EBA26-2) and electrical construction (Contract No. EBA26-3) components. Bidding documents are available through PennBid at https://pennbid.bonfirehub.com/, with bids due December 8, 2026 at 10:00 AM local time. A pre-bid open house is scheduled for November 18, 2026 from 8:00 AM to 10:00 AM to allow bidders to view the facility.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 31 19 - PROJECT MEETINGS

Herbert, Rowland & Grubic, Inc. 01 31 19 - 1 011139.0465

SECTION 01 31 19 - PROJECT MEETINGS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Preconstruction meeting.

B. Progress meetings.

C. Pre-installation meetings.

1.2 PRECONSTRUCTION MEETING

A. Engineer will schedule and preside over meeting after Notice of Award and prior to commencement of Work at the site.

B. Attendance Required: Engineer, Owner, Resident Project Representative, Owner Procured Equipment Representative, and Contractor.

1. Contractor representation: person vested with the authority to make necessary decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules.

C. Agenda:

1. Engineer's Status During Construction.

2. Resident Project Representative (RPR).

3. Project Communication Procedures.

4. Contract Times.

5. Project Site: Access and Rights-of-Way.

6. Permits and Approvals.

7. Field Engineering.

8. Changes in the Work procedures.

9. Work Schedule.

10. Shop Drawings.

11. Substitutions.

12. Job Conference Schedule.

13. Payment Applications.

14. Temporary Utilities.

15. Emergency Phone Numbers.

16. Field Office Facilities.

17. Subcontractors.

18. Prevailing Wage and Payroll Certifications.

19. Insurances.

20. Steel Products Procurement Act Certifications.

21. Safety and OSHA.

22. Control of Work.

Herbert, Rowland & Grubic, Inc. 01 31 19 - 2 011139.0465

D. Engineer will record minutes and distribute copies to participants, with copies each to Contractor(s), Owner, and those affected by decisions made.

1.3 PROGRESS MEETINGS

A. Engineer will schedule and administer meetings throughout progress of the Work at maximum monthly intervals.

B. Attendance Required: Contractors and job superintendent, major Subcontractors and suppliers, Engineer, and Owner.

1. Contractors representative shall be vested with the authority to make any decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules

C. Minimum Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Planned progress during succeeding work period.

4. Maintenance of Progress Schedule.

5. Field observations, problems, and decisions.

6. Identification of problems impeding planned progress.

7. Review of submittal schedule and status of submittals.

8. Coordination of projected progress.

9. Maintenance of quality and work standards.

10. Other business relating to Work.

D. Engineer will record minutes and distribute copies to participants within two days after meeting, electronic copies each to Engineer, Owner, and those affected by decisions made.

1.4 PREINSTALLATION MEETINGS

A. When required in individual Specification Sections, convene pre-installation meetings at Project Site before starting Work of specific Section.

B. Require attendance of parties directly affecting, or affected by, Work of specific Section.

C. Notify Engineer fourteen days in advance of meeting date.

D. Prepare agenda and preside over meeting:

1. Review conditions of installation, preparation, and installation procedures.

2. Review coordination with related Work.

E. Record minutes and distribute copies to participants within two days after meeting, to Engineer, Owner, and those affected by decisions made.

Herbert, Rowland & Grubic, Inc. 01 31 19 - 3 011139.0465

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION – Not Used.

END OF SECTION

PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Preconstruction meeting.
B. Progress meetings.
C. Pre-installation meetings.
1.2 PRECONSTRUCTION MEETING
A. Engineer will schedule and preside over meeting after Notice of Award and prior to commencement of Work at the site.
B. Attendance Required: Engineer, Owner, Resident Project Representative, Owner Procured Equipment Representative, and Contractor.
1. Contractor representation: person vested with the authority to make necessary decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules.
C. Agenda:
1. Engineer's Status During Construction.
2. Resident Project Representative (RPR).
3. Project Communication Procedures.
4. Contract Times.
5. Project Site: Access and Rights-of-Way.
6. Permits and Approvals.
7. Field Engineering.
8. Changes in the Work procedures.
9. Work Schedule.
10. Shop Drawings.
11. Substitutions.
12. Job Conference Schedule.
13. Payment Applications.
14. Temporary Utilities.
15. Emergency Phone Numbers.
16. Field Office Facilities.
17. Subcontractors.
18. Prevailing Wage and Payroll Certifications.
19. Insurances.
20. Steel Products Procurement Act Certifications.
21. Safety and OSHA.
22. Control of Work.

D. Engineer will record minutes and distribute copies to participants, with copies each to Contractor(s), Owner, and those affected by decisions made.

1.3 PROGRESS MEETINGS
A. Engineer will schedule and administer meetings throughout progress of the Work at maximum monthly intervals.
B. Attendance Required: Contractors and job superintendent, major Subcontractors and suppliers, Engineer, and Owner.
1. Contractors representative shall be vested with the authority to make any decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules
C. Minimum Agenda:
1. Review minutes of previous meetings.
2. Review of Work progress.
3. Planned progress during succeeding work period.
4. Maintenance of Progress Schedule.
5. Field observations, problems, and decisions.
6. Identification of problems impeding planned progress.
7. Review of submittal schedule and status of submittals.
8. Coordination of projected progress.
9. Maintenance of quality and work standards.
10. Other business relating to Work.

D. Engineer will record minutes and distribute copies to participants within two days after meeting, electronic copies each to Engineer, Owner, and those affected by decisions made.

1.4 PREINSTALLATION MEETINGS
A. When required in individual Specification Sections, convene pre-installation meetings at Project Site before starting Work of specific Section.
B. Require attendance of parties directly affecting, or affected by, Work of specific Section.
C. Notify Engineer fourteen days in advance of meeting date.
D. Prepare agenda and preside over meeting:
1. Review conditions of installation, preparation, and installation procedures.
2. Review coordination with related Work.

E. Record minutes and distribute copies to participants within two days after meeting, to Engineer, Owner, and those affected by decisions made.

PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION – Not Used.

File details come from the government source that posted it. Updated .