40 23 40 - Sanitary Wastewater Process Piping.pdf
PDF 250 KB Posted
- Attached to
- Biosolids Project 011139.0465
- Solicitation number
- US.260443
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a technical specification document for sanitary wastewater process piping related to the Biosolids Project 011139.0465 being undertaken by Ephrata Borough Authority in Pennsylvania. The specification details the requirements for pipes, tubes, valves, and related components used to convey sanitary wastewater within the project. The work includes the installation of ductile iron process pipe, plug valves, and swing check valves for shutoff, drain, isolation, and bypass services as indicated on project drawings. The specification requires that manufacturers have a minimum of three years of documented experience in manufacturing the specified products and that installers have equivalent experience in performing this type of work. Bidding documents are available through PennBid at https://pennbid.bonfirehub.com/, with bids due by December 8, 2026 at 10:00 AM local time. A pre-bid open house is scheduled for November 18, 2026 from 8:00 AM to 10:00 AM. The project involves two separate contracts: Contract No. EBA26-2 for General Construction and Contract No. EBA26-3 for Electrical Construction.
The specification establishes comprehensive submittal requirements including product data, shop drawings, manufacturer's certificates, welder certifications, and manufacturer instructions for installation, storage, and handling. Installation must comply with ASME B31.3 Process Piping Design standards and AWS D1.1/D1.1M Structural Welding Code standards. The document requires field quality control through inspection for damage to pipe lining and coatings, pressure testing as indicated on pipe schedules, and repair of damaged coatings with materials equal to the original coating. Contractors must demonstrate valve operation and maintenance procedures to the Owner's personnel and maintain clean piping and valve interiors throughout installation. The specification references related sections for couplings, adapters, hangers, supports, and common valve requirements, indicating this is one component of a larger, coordinated project involving demolition and replacement of dewatered solids conveyor systems, wall demolition, utility replacements, and associated improvements.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
40 23 40 - SANITARY WASTEWATER PROCESS PIPING
Herbert, Rowland & Grubic, Inc. 40 23 40 - 1 011139.0465
SECTION 40 23 40 - SANITARY WASTEWATER PROCESS PIPING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Pipes and tubes for conveying sanitary wastewater.
2. Valves for conveying sanitary wastewater.
B. Related Requirements:
1. Section 40 05 06 - Couplings, Adapters, and Specials for Process Piping: Pipe penetrations, restrained joints, flexible connections, expansion joints and loops, and sleeve-type couplings.
2. Section 40 05 07 - Hangers and Supports for Process Piping: Supports, hangers, anchors, and guides.
3. Section 40 05 51 - Common Requirements for Process Valves: Common product requirements for valves for placement by this Section.
4. Section 40 05 62 - Plug Valves: Valves and accessories.
5. Section 40 05 65.23 - Swing Check Valves: Valves and accessories.
1.2 REFERENCE STANDARDS
A. American Welding Society:
1. AWS D1.1/D1.1M - Structural Welding Code - Steel.
B. ASME International:
1. ASME A13.1 - Scheme for the Identification of Piping Systems.
2. ASME B31.3 - Process Piping Design.
C. ASTM International:
1. ASTM A780/A780M - Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings.
D. SSPC: Society for Protective Coatings:
1. SSPC-Paint 20 - Zinc-Rich Coating (Type I - Inorganic and Type II - Organic).
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data:
1. Piping: Submit manufacturer information on pipe materials, fittings, and accessories.
2. Hangers and Supports: Submit manufacturer catalog information, including load capacity.
Herbert, Rowland & Grubic, Inc. 40 23 40 - 2 011139.0465
3. System Components: Submit manufacturer catalog information including capacity, component sizes, rough-in requirements, and service sizes.
4. Valves: Submit manufacturer information for actuators with model number and size indicated.
C. Shop Drawings:
1. Piping:
a. Indicate piping system schematic with general assembly of components and mounting and installation details.
b. Submit list of wording, symbols, letter size, and color-coding for pipe identification; comply with ASME A13.1.
2. Submit layout drawings showing piece numbers and location.
3. Valves: Submit assembly drawings indicating parts list, materials, sizes, position indicators, limit switches, control system, actuator mounting, wiring diagrams, and control system schematics.
D. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.
E. Welder Certificates: Certify welders and welding procedures employed on Work, verifying AWS qualification within previous 12 months.
F. Manufacturer Instructions: Submit detailed instructions on installation requirements, including storage and handling procedures.
G. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections.
H. Qualifications Statements:
1. Welders: Qualify procedures and personnel according to AWS D1.1/D1.1M.
1.4 CLOSEOUT SUBMITTALS
A. Section 01 77 00 - Closeout Requirements: Requirements for submittals.
B. Project Record Documents: Record actual locations of piping and valves.
C. Operation and Maintenance Data: Submit assembly views and replacement part numbers and availability.
1.5 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum three years' documented experience.
B. Installer: Company specializing in performing Work of this Section with minimum three years' documented experience.
Herbert, Rowland & Grubic, Inc. 40 23 40 - 3 011139.0465
1.6 DELIVERY, STORAGE, AND HANDLING
A. Section 01 61 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products.
B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.
C. Store materials according to manufacturer instructions.
D. Protection:
1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.
2. Provide additional protection according to manufacturer instructions.
1.7 EXISTING CONDITIONS
A. Field Measurements:
1. Verify field measurements prior to fabrication.
2. Indicate field measurements on Shop Drawings.
1.8 WARRANTY
A. Section 01 78 36 - Warranty Requirements: Requirements for warranties.
PART 2 - PRODUCTS
2.1 PIPING AND VALVES FOR CONVEYING SANITARY WASTEWATER
A. Piping: Ductile iron as specified in Section 40 05 19 – Ductile Iron Process Pipe.
B. Valves:
1. Plug as specified in Section 40 05 62 - Plug Valves.
2. Swing check as specified in Section 40 05 65.23 - Swing Check Valves.
C. Valve Service:
1. Shutoff, Drain, and Isolation:
a. As indicated on Drawings.
2. Bypass: As indicated on Drawings.
2.2 PIPE HANGERS AND SUPPORTS
A. As specified in Section 40 05 07 - Hangers and Supports for Process Piping.
Herbert, Rowland & Grubic, Inc. 40 23 40 - 4 011139.0465
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.
B. Verify that field dimensions are as indicated on Shop Drawings.
3.2 PREPARATION
A. Section 01 73 00 - Execution Requirements: Requirements for installation preparation.
B. Protect materials and equipment from damage and intrusion of water and other materials.
3.3 INSTALLATION
A. As indicated on Shop Drawings, according to manufacturer instructions, and ASME B31.3.
B. Use minimum number of joints.
C. Field Fabrication of Fittings: According to manufacturer instructions.
D. Flexible Couplings:
1. Location: At connections to equipment and where indicated on Shop Drawings.
2. As specified in Section 40 05 06 - Couplings, Adapters, and Specials for Process Piping.
E. Couplings and Anchors: According to manufacturer instructions.
F. Local Indicators:
1. Install direct-reading indicator devices such as thermometers as indicated on Drawings and according to manufacturer instructions.
2. Location: Capable of being read from floor level and accessible for maintenance.
G. Orientate valves to permit operation and maintenance access to valve operator and to avoid interferences with other equipment.
3.4 FIELD QUALITY CONTROL
A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.
B. Inspection:
1. Inspect for damage to pipe lining or coating and for other defects that may be detrimental as determined by Engineer.
2. Repair damaged piping, or provide new, undamaged pipe.
3. After installation, inspect for proper supports and interferences.
Herbert, Rowland & Grubic, Inc. 40 23 40 - 5 011139.0465
C. Pressure Testing:
1. As indicated on pipe schedule.
D. Equipment Acceptance: Adjust, repair, modify, or replace components failing to perform as specified and rerun tests.
E. Damaged Coatings:
1. Repair damaged coatings with material equal to original coating.
3.5 ADJUSTING
A. Section 01 73 00 - Execution Requirements: Requirements for starting and adjusting.
B. Field-calibrate local indicators at time of piping installation.
3.6 CLEANING
A. Section 01 73 00 - Execution Requirements: Requirements for cleaning.
B. Keep piping and valve interiors clean as installation progresses.
3.7 DEMONSTRATION
A. Section 01 73 00 - Execution Requirements: Requirements for demonstration and training.
B. Demonstrate valve operation, routine maintenance, and emergency repair procedures to Owner's personnel.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes: |
| 1. Pipes and tubes for conveying sanitary wastewater. |
| 2. Valves for conveying sanitary wastewater. |
| B. Related Requirements: |
| 1. Section 40 05 06 - Couplings, Adapters, and Specials for Process Piping: Pipe penetrations, restrained joints, flexible connections, expansion joints and loops, and sleeve-type couplings. |
| 2. Section 40 05 07 - Hangers and Supports for Process Piping: Supports, hangers, anchors, and guides. |
| 3. Section 40 05 51 - Common Requirements for Process Valves: Common product requirements for valves for placement by this Section. |
| 4. Section 40 05 62 - Plug Valves: Valves and accessories. |
| 5. Section 40 05 65.23 - Swing Check Valves: Valves and accessories. |
| 1.2 REFERENCE STANDARDS |
| A. American Welding Society: |
| 1. AWS D1.1/D1.1M - Structural Welding Code - Steel. |
| B. ASME International: |
| 1. ASME A13.1 - Scheme for the Identification of Piping Systems. |
| 2. ASME B31.3 - Process Piping Design. |
| C. ASTM International: |
| 1. ASTM A780/A780M - Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings. |
| D. SSPC: Society for Protective Coatings: |
| 1. SSPC-Paint 20 - Zinc-Rich Coating (Type I - Inorganic and Type II - Organic). |
| 1.3 SUBMITTALS |
| A. Section 01 33 00 - Submittal Procedures: Requirements for submittals. |
| B. Product Data: |
| 1. Piping: Submit manufacturer information on pipe materials, fittings, and accessories. |
| 2. Hangers and Supports: Submit manufacturer catalog information, including load capacity. |
| 3. System Components: Submit manufacturer catalog information including capacity, component sizes, rough-in requirements, and service sizes. |
| 4. Valves: Submit manufacturer information for actuators with model number and size indicated. |
| C. Shop Drawings: |
| 1. Piping: |
| a. Indicate piping system schematic with general assembly of components and mounting and installation details. |
| b. Submit list of wording, symbols, letter size, and color-coding for pipe identification; comply with ASME A13.1. |
| 2. Submit layout drawings showing piece numbers and location. |
| 3. Valves: Submit assembly drawings indicating parts list, materials, sizes, position indicators, limit switches, control system, actuator mounting, wiring diagrams, and control system schematics. |
| D. Manufacturer's Certificate: Certify that products meet or exceed specified requirements. |
| E. Welder Certificates: Certify welders and welding procedures employed on Work, verifying AWS qualification within previous 12 months. |
| F. Manufacturer Instructions: Submit detailed instructions on installation requirements, including storage and handling procedures. |
| G. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections. |
| H. Qualifications Statements: |
| 1. Welders: Qualify procedures and personnel according to AWS D1.1/D1.1M. |
| 1.4 CLOSEOUT SUBMITTALS |
| A. Section 01 77 00 - Closeout Requirements: Requirements for submittals. |
| B. Project Record Documents: Record actual locations of piping and valves. |
| C. Operation and Maintenance Data: Submit assembly views and replacement part numbers and availability. |
| 1.5 QUALIFICATIONS |
| A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum three years' documented experience. |
| B. Installer: Company specializing in performing Work of this Section with minimum three years' documented experience. |
| 1.6 DELIVERY, STORAGE, AND HANDLING |
| A. Section 01 61 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products. |
| B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage. |
| C. Store materials according to manufacturer instructions. |
| D. Protection: |
| 1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas. |
| 2. Provide additional protection according to manufacturer instructions. |
| 1.7 EXISTING CONDITIONS |
| A. Field Measurements: |
| 1. Verify field measurements prior to fabrication. |
| 2. Indicate field measurements on Shop Drawings. |
| 1.8 WARRANTY |
| A. Section 01 78 36 - Warranty Requirements: Requirements for warranties. |
| PART 2 - PRODUCTS |
| 2.1 PIPING AND VALVES FOR CONVEYING SANITARY WASTEWATER |
| A. Piping: Ductile iron as specified in Section 40 05 19 – Ductile Iron Process Pipe. |
| B. Valves: |
| 1. Plug as specified in Section 40 05 62 - Plug Valves. |
| 2. Swing check as specified in Section 40 05 65.23 - Swing Check Valves. |
| C. Valve Service: |
| 1. Shutoff, Drain, and Isolation: |
| a. As indicated on Drawings. |
2. Bypass: As indicated on Drawings.
| 2.2 PIPE HANGERS AND SUPPORTS |
| A. As specified in Section 40 05 07 - Hangers and Supports for Process Piping. |
| PART 3 - EXECUTION |
| 3.1 EXAMINATION |
| A. Section 01 73 00 - Execution Requirements: Requirements for installation examination. |
| B. Verify that field dimensions are as indicated on Shop Drawings. |
| 3.2 PREPARATION |
| A. Section 01 73 00 - Execution Requirements: Requirements for installation preparation. |
| B. Protect materials and equipment from damage and intrusion of water and other materials. |
| 3.3 INSTALLATION |
| A. As indicated on Shop Drawings, according to manufacturer instructions, and ASME B31.3. |
| B. Use minimum number of joints. |
| C. Field Fabrication of Fittings: According to manufacturer instructions. |
| D. Flexible Couplings: |
| 1. Location: At connections to equipment and where indicated on Shop Drawings. |
| 2. As specified in Section 40 05 06 - Couplings, Adapters, and Specials for Process Piping. |
| E. Couplings and Anchors: According to manufacturer instructions. |
| F. Local Indicators: |
| 1. Install direct-reading indicator devices such as thermometers as indicated on Drawings and according to manufacturer instructions. |
| 2. Location: Capable of being read from floor level and accessible for maintenance. |
G. Orientate valves to permit operation and maintenance access to valve operator and to avoid interferences with other equipment.
| 3.4 FIELD QUALITY CONTROL |
| A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing. |
| B. Inspection: |
| 1. Inspect for damage to pipe lining or coating and for other defects that may be detrimental as determined by Engineer. |
| 2. Repair damaged piping, or provide new, undamaged pipe. |
| 3. After installation, inspect for proper supports and interferences. |
| C. Pressure Testing: |
| 1. As indicated on pipe schedule. |
| D. Equipment Acceptance: Adjust, repair, modify, or replace components failing to perform as specified and rerun tests. |
| E. Damaged Coatings: |
| 1. Repair damaged coatings with material equal to original coating. |
| 3.5 ADJUSTING |
| A. Section 01 73 00 - Execution Requirements: Requirements for starting and adjusting. |
| B. Field-calibrate local indicators at time of piping installation. |
| 3.6 CLEANING |
| A. Section 01 73 00 - Execution Requirements: Requirements for cleaning. |
| B. Keep piping and valve interiors clean as installation progresses. |
| 3.7 DEMONSTRATION |
| A. Section 01 73 00 - Execution Requirements: Requirements for demonstration and training. |
| B. Demonstrate valve operation, routine maintenance, and emergency repair procedures to Owner's personnel. |
File details come from the government source that posted it. Updated .