33 05 05.31 - Hydrostatic Testing.pdf
PDF 235 KB Posted
- Attached to
- Biosolids Project 011139.0465
- Solicitation number
- US.260443
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a technical specification document for hydrostatic testing procedures prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 at Ephrata Borough Authority in Pennsylvania. The specification details the hydrostatic testing requirements for pressure piping systems, including ductile iron, polyvinyl chloride (PVC), and polyethylene (PE) piping. The testing procedures must be submitted prior to the start of testing and include testing procedures, test equipment lists, testing sequence schedules, provisions for water disposal, pressure gage calibration certification, and applicator qualifications. The applicator performing this work must be a company specializing in hydrostatic testing with a minimum of three years documented experience. Testing must be conducted according to AWWA C600 standards for ductile iron or PVC piping and ASTM F 2164 standards for PE piping, with all results documented in test and evaluation reports submitted upon completion.
The hydrostatic testing specification requires pressurizing piping systems to 1.5 times the working pressure for a minimum of two hours for ductile iron or PVC piping, with pressure maintained within plus or minus 5.0 psi of the test pressure. Maximum allowable leakage for ductile iron or PVC piping is calculated using the formula L = [SD x sqrt(P)]/C, where leakage greater than computed allowable rates requires location and correction of sources followed by retesting. For PE piping, testing includes an initial expansion phase of four hours at maximum test pressure followed by a one-hour monitoring phase at reduced pressure (10 psi below target), with success indicated by no visual leakage and pressure remaining within 5% of target pressure. All required equipment, including pressure pumps, pressure hoses, water meters, test connections, pressure relief valves, and pressure gages calibrated to 0.1 psi, must be provided by the contractor. Any visible leaks must be corrected and sections retested after an eight-hour depressurization period regardless of calculated allowable leakage rates.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
33 05 05.31 - HYDROSTATIC TESTING
Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 1 011139.0465
SECTION 33 05 05.31 - HYDROSTATIC TESTING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes: Hydrostatic testing of pressure piping.
B. Related Requirements:
1. Section 33 31 23 - Sanitary Sewerage Force Main Piping: Pipe materials and accessories normally encountered with municipal sanitary sewage force mains.
1.2 REFERENCE STANDARDS
A. American Water Works Association:
1. AWWA C600 - Installation of Ductile-Iron Water Mains and Their Appurtenances.
B. American Standard Testing Methods
1. ASTM F 2164 - Standard Practice for Field Leak Testing of Polyethylene (PE) and
Crosslinked Polyethylene (PEX) Pressure Piping Systems Using Hydrostatic Pressure.
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Submit following items prior to start of testing:
1. Testing procedures.
2. List of test equipment.
3. Testing sequence schedule.
4. Provisions for disposal of flushing and test water.
5. Certification of test gage calibration.
C. Test and Evaluation Reports: Indicate results of piping tests.
D. Qualifications Statement:
1. Submit qualifications for applicator.
1.4 QUALIFICATIONS
A. Applicator: Company specializing in performing Work of this Section with minimum three years' documented experience.
PART 2 - PRODUCTS
2.1 HYDROSTATIC TESTING
A. Equipment:
1. Pressure pump.
Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 2 011139.0465
2. Pressure hose.
3. Water meter.
4. Test connections.
5. Pressure relief valve.
6. Pressure Gage: Calibrated to 0.1 psi.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution and Closeout Requirements: Requirements for installation examination.
B. Verify that piping is ready for testing.
C. Verify that trenches are backfilled.
D. Verify that pressure piping thrust restraints have been installed.
3.2 FIELD QUALITY CONTROL
A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.
B. Testing of Pressure Ductile Iron or PVC Piping:
1. Test system according to AWWA C600 and following:
a. Hydrostatically test each portion of pressure piping, including valved section, at 1.5 times working pressure of piping, based on elevation of lowest point in piping corrected to elevation of test gage.
b. Conduct hydrostatic testing for at least two hours.
c. Slowly fill with water portion of piping to be tested, expelling air from piping at high points.
d. Install corporation cocks at high points.
e. Close air vents and corporation cocks after air is expelled.
f. Raise pressure to specified test pressure.
g. Observe joints, fittings, and valves undergoing testing.
h. Remove and renew cracked pipes, joints, fittings, and valves that show visible leakage.
i. Retest.
j. Correct visible deficiencies and continue testing at same test pressure for additional two hours to determine leakage rate.
k. Maintain pressure within plus or minus 5.0 psi of test pressure.
l. Leakage is defined as quantity of water supplied to piping necessary to maintain test pressure during period of testing.
m. Compute maximum allowable leakage using following formula:
1) L = [SD x sqrt(P)]/C.
2) L = testing allowance, gph.
3) S = length of pipe tested, feet.
4) D = nominal diameter of pipe, inches.
5) P = average test pressure during hydrostatic testing, psig.
Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 3 011139.0465
6) C = 148,000.
7) If pipe undergoing testing contains sections of various diameters, calculate allowable leakage from sum of computed leakage for each pipe size.
2. If testing of piping indicates leakage greater than that allowed, locate source of leakage, make corrections, and retest until leakage is within acceptable limits.
3. Correct visible leaks regardless of quantity of leakage.
C. Testing of Pressure PE Piping:
1. Test system according to ASTM F 2164 and following:
a. Hydrostatically test each portion of pressure piping, including valved section, at 1.5 times working pressure of piping, based on elevation of lowest point in piping corrected to elevation of test gage.
b. Initial expansion phase
1) Slowly fill with water portion of piping to be tested, expelling air from piping at high points.
2) Install corporation cocks at high points.
3) Close air vents and corporation cocks after air is expelled.
4) Raise pressure to specified test pressure.
5) Observe joints, fittings, and valves undergoing testing.
6) Add make-up water as necessary to maintain maximum test pressure for 4 hours.
c. Test Phase:
1) Immediately after expansion phase, reduce test pressure by 10 psi and stop adding makeup water.
2) Monitor pressure for 1 hour.
d. Remove and renew cracked pipes, joints, fittings, and valves that show visible leakage.
e. Retest after section is depressurized for 8 hours, minimum.
f. If no visual leakage is observed and test pressure remains within 5% of the target pressure, no leakage is indicated.
2. If testing of piping indicates leakage, locate source of leakage, make corrections, and retest until leakage is within acceptable limits.
3. Correct visible leaks regardless of quantity of leakage.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes: Hydrostatic testing of pressure piping. |
| B. Related Requirements: |
| 1. Section 33 31 23 - Sanitary Sewerage Force Main Piping: Pipe materials and accessories normally encountered with municipal sanitary sewage force mains. |
| 1.2 REFERENCE STANDARDS |
| A. American Water Works Association: |
| 1. AWWA C600 - Installation of Ductile-Iron Water Mains and Their Appurtenances. |
| B. American Standard Testing Methods |
| 1. ASTM F 2164 - Standard Practice for Field Leak Testing of Polyethylene (PE) and Crosslinked Polyethylene (PEX) Pressure Piping Systems Using Hydrostatic Pressure. |
| 1.3 SUBMITTALS |
| A. Section 01 33 00 - Submittal Procedures: Requirements for submittals. |
| B. Submit following items prior to start of testing: |
| 1. Testing procedures. |
| 2. List of test equipment. |
| 3. Testing sequence schedule. |
| 4. Provisions for disposal of flushing and test water. |
| 5. Certification of test gage calibration. |
| C. Test and Evaluation Reports: Indicate results of piping tests. |
| D. Qualifications Statement: |
| 1. Submit qualifications for applicator. |
| 1.4 QUALIFICATIONS |
| A. Applicator: Company specializing in performing Work of this Section with minimum three years' documented experience. |
| PART 2 - PRODUCTS |
| 2.1 HYDROSTATIC TESTING |
| A. Equipment: |
| 1. Pressure pump. |
| 2. Pressure hose. |
| 3. Water meter. |
| 4. Test connections. |
| 5. Pressure relief valve. |
| 6. Pressure Gage: Calibrated to 0.1 psi. |
| PART 3 - EXECUTION |
| 3.1 EXAMINATION |
| A. Section 01 73 00 - Execution and Closeout Requirements: Requirements for installation examination. |
| B. Verify that piping is ready for testing. |
| C. Verify that trenches are backfilled. |
| D. Verify that pressure piping thrust restraints have been installed. |
| 3.2 FIELD QUALITY CONTROL |
| A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing. |
| B. Testing of Pressure Ductile Iron or PVC Piping: |
| 1. Test system according to AWWA C600 and following: |
| a. Hydrostatically test each portion of pressure piping, including valved section, at 1.5 times working pressure of piping, based on elevation of lowest point in piping corrected to elevation of test gage. |
| b. Conduct hydrostatic testing for at least two hours. |
| c. Slowly fill with water portion of piping to be tested, expelling air from piping at high points. |
| d. Install corporation cocks at high points. |
| e. Close air vents and corporation cocks after air is expelled. |
| f. Raise pressure to specified test pressure. |
| g. Observe joints, fittings, and valves undergoing testing. |
| h. Remove and renew cracked pipes, joints, fittings, and valves that show visible leakage. |
| i. Retest. |
| j. Correct visible deficiencies and continue testing at same test pressure for additional two hours to determine leakage rate. |
| k. Maintain pressure within plus or minus 5.0 psi of test pressure. |
| l. Leakage is defined as quantity of water supplied to piping necessary to maintain test pressure during period of testing. |
| m. Compute maximum allowable leakage using following formula: |
| 1) L = [SD x sqrt(P)]/C. |
| 2) L = testing allowance, gph. |
| 3) S = length of pipe tested, feet. |
| 4) D = nominal diameter of pipe, inches. |
| 5) P = average test pressure during hydrostatic testing, psig. |
| 6) C = 148,000. |
| 7) If pipe undergoing testing contains sections of various diameters, calculate allowable leakage from sum of computed leakage for each pipe size. |
| 2. If testing of piping indicates leakage greater than that allowed, locate source of leakage, make corrections, and retest until leakage is within acceptable limits. |
| 3. Correct visible leaks regardless of quantity of leakage. |
| C. Testing of Pressure PE Piping: |
| 1. Test system according to ASTM F 2164 and following: |
| a. Hydrostatically test each portion of pressure piping, including valved section, at 1.5 times working pressure of piping, based on elevation of lowest point in piping corrected to elevation of test gage. |
| b. Initial expansion phase |
| 1) Slowly fill with water portion of piping to be tested, expelling air from piping at high points. |
| 2) Install corporation cocks at high points. |
| 3) Close air vents and corporation cocks after air is expelled. |
| 4) Raise pressure to specified test pressure. |
| 5) Observe joints, fittings, and valves undergoing testing. |
| 6) Add make-up water as necessary to maintain maximum test pressure for 4 hours. |
| c. Test Phase: |
| 1) Immediately after expansion phase, reduce test pressure by 10 psi and stop adding makeup water. |
| 2) Monitor pressure for 1 hour. |
| d. Remove and renew cracked pipes, joints, fittings, and valves that show visible leakage. |
| e. Retest after section is depressurized for 8 hours, minimum. |
| f. If no visual leakage is observed and test pressure remains within 5% of the target pressure, no leakage is indicated. |
| 2. If testing of piping indicates leakage, locate source of leakage, make corrections, and retest until leakage is within acceptable limits. |
| 3. Correct visible leaks regardless of quantity of leakage. |