This is a Dewatering Specification Section (31 23 19) prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 in Ephrata Borough, Pennsylvania. The specification details requirements for dewatering systems and surface water control systems necessary to support excavation and trenching operations during construction. The contractor must furnish standby dewatering equipment including at minimum one each of dewatering pumps, pump power units, portable electric generators, filter bags, and associated hoses and fittings. The dewatering system must be designed to remove accumulated water from excavations and trenches, prevent damage to adjacent properties and utilities, and maintain stability of excavation sides and bottoms. Surface water control systems must collect and remove surface water and seepage entering excavations. The specification requires compliance with all applicable authorities having jurisdiction and mandates obtaining an EPA National Pollutant Discharge Elimination System (NPDES) permit for storm water discharge from the construction site. Additionally, contractors must contact the Pennsylvania One Call System at least three working days before performing work to have underground utilities located and marked.
The specification establishes comprehensive operational and maintenance requirements including continuous dewatering system operation until backfilling is complete, daily observation and monitoring, and bi-weekly testing of emergency generators. Contractors must maintain fuel tanks above 25 percent capacity and cease excavation work if the dewatering system cannot control water levels, notifying the Engineer and implementing supplemental measures before resuming operations. Water disposal must occur through existing storm sewer systems, drainage channels, or settling basins as specified in Section 31 25 00 - Erosion and Sedimentation Controls. After system installation, contractors must perform a pumping test to verify proper operation and adjust pump speed and discharge volume accordingly. Contractors are responsible for removing all dewatering and surface water control systems upon completion and repairing any damage caused by system operation or failure.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
31 23 19 - DEWATERING
Herbert, Rowland & Grubic, Inc. 31 23 19 - 1 011139.0465
SECTION 31 23 19 - DEWATERING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Dewatering system.
2. Surface water control system.
3. System operation and maintenance.
4. Water disposal.
B. Related Sections:
1. Section 31 05 16 - Aggregates for Earthwork: Filter sand.
2. Section 31 23 33 – Trenching and Backfilling for Utilities: Trenching for utilities below ground water table.
3. Section 31 25 00 - Erosion and Sedimentation Controls: Surface water runoff control.
1.2 REFERENCES
A. ASTM International:
1. ASTM C33 - Standard Specification for Concrete Aggregates.
1.3 DEFINITIONS
A. Dewatering includes the following:
1. Lowering of ground water table and intercepting horizontal water seepage to prevent ground water from entering excavations and trenches.
2. Reducing piezometric pressure within strata to prevent failure or heaving of excavations and trenches.
3. Disposing of removed water.
B. Surface Water Control: Removal of surface water within open excavations.
1.4 SYSTEM DESCRIPTION
A. Furnish standby equipment stored at Project site. Provide the following standby equipment, but not less than one of each type:
1. Dewatering Pumps.
2. Pump Power Units.
3. Portable Electric Generators.
4. Filter bags.
5. Associated hoses and fittings.
1.5 PERFORMANCE REQUIREMENTS
A. Design dewatering systems to:
Herbert, Rowland & Grubic, Inc. 31 23 19 - 2 011139.0465
1. Remove accumulated water from excavations and trenches.
2. Prevent damage to adjacent properties, buildings, structures, utilities, and facilities from construction operations.
3. Maintain stability of sides and bottoms of excavations and trenches.
B. Design surface water control systems to:
1. Collect and remove surface water and seepage entering excavation.
1.6 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data: Submit data for each of the following:
1. Dewatering Pumps: Indicate sizes, capacities, priming method, motor characteristics.
2. Pumping equipment for control of surface water within excavation.
1.7 CLOSEOUT SUBMITTALS
A. Section 01 77 00 - Closeout Procedures: Requirements for submittals.
B. Project Record Documents: Record actual locations and depths of capped wells and piping abandoned in place.
1.8 QUALITY ASSURANCE
A. Comply with authorities having jurisdiction for the following:
1. Water discharge and disposal from pumping operations.
B. Obtain permit from EPA under National Pollutant Discharge Elimination System (NPDES), for storm water discharge from construction sites.
C. Maintain one copy of document on site.
1.9 SEQUENCING
A. Section 01 10 00 - Summary: Requirements for sequencing.
B. Sequence work to obtain required permits before start of dewatering operations.
1.10 COORDINATION
A. Section 01 31 13 – Project Coordination: Requirements for coordination.
B. Coordinate work to permit the following construction operations to be completed on dry stable substrate.
1. Trenching and Backfilling for utilities specified in Section 31 23 33.
Herbert, Rowland & Grubic, Inc. 31 23 19 - 3 011139.0465
PART 2 - PRODUCTS
2.1 DEWATERING EQUIPMENT
A. Select dewatering equipment to meet specified performance requirements.
B. Surface Water Pumps: Self priming, diaphragm or centrifugal semi-open clog resistant impeller; engine driven type.
1. Furnish pumps with screened suction hose and discharge hoses as required to suit application.
2.2 ACCESSORIES
A. Filter bag: Non-woven geotextile. As specified in the Drawings.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution Requirements: Verification of existing conditions before starting work.
B. Call Pennsylvania One Call System, Inc. at 1-800-242-1776 not less than three working days before performing Work.
1. Request underground utilities to be located and marked within and surrounding construction areas.
3.2 PREPARATION
A. Protect existing adjacent buildings, structures, and improvements from damage caused by dewatering operations.
3.3 DEWATERING SYSTEM
A. Locate system components to allow continuous dewatering operations without interfering with installation of permanent Work and existing public rights-of-way, sidewalks, and adjacent buildings, structures, and improvements.
B. Install pumps in accordance with manufacturer's instructions.
3.4 SURFACE WATER CONTROL SYSTEM
A. Provide ditches, berms, and other devices to divert and drain surface water from excavation area as specified in Section 31 25 00 – Erosion and Sedimentation Controls.
B. Divert surface water and seepage water within excavation areas into sumps and pump water into drainage channels, storm drains, and settling basins in accordance with requirements of agencies having jurisdiction. Protect storm water appurtenances as specified in Section 31 25 00 – Erosion and Sedimentation Controls.
Herbert, Rowland & Grubic, Inc. 31 23 19 - 4 011139.0465
C. Control and remove unanticipated water seepage into excavation.
3.5 SYSTEM OPERATION AND MAINTENANCE
A. Operate dewatering system continuously as needed until backfilling is complete.
B. Provide supervision of dewatering system by personnel skilled in operation, maintenance, and replacement of system components.
C. Conduct daily observation of dewatering system and monitoring system. Make required repairs and perform scheduled maintenance.
D. Fill fuel tanks before tanks reach 25 percent capacity.
E. Start emergency generators at least twice each week to check operating condition.
F. When dewatering system cannot control water within excavation, notify Engineer and stop excavation work.
1. Supplement or modify dewatering system and provide other remedial measures to control water within excavation.
2. Demonstrate dewatering system operation complies with performance requirements before resuming excavation operations.
G. Modify dewatering and surface water control systems when operation causes or threatens to cause damage to new construction, existing site improvements, adjacent property, or adjacent water wells.
H. Correct unanticipated pressure conditions affecting dewatering system performance.
I. Do not discontinue dewatering operations without Engineer's approval.
3.6 WATER DISPOSAL
A. Discharge water into existing storm sewer system, drainage channels, or settling basins as specified in Section 31 25 00 – Erosion and Sedimentation Controls.
3.7 SYSTEM REMOVAL
A. Remove dewatering and surface water control systems after dewatering operations are discontinued.
B. Repair damage caused by dewatering and surface water control systems or resulting from failure of systems to protect property.
3.8 FIELD QUALITY CONTROL
A. Section 01 40 00 - Quality Requirements: Field inspecting, testing, adjusting, and balancing.
Herbert, Rowland & Grubic, Inc. 31 23 19 - 5 011139.0465
B. After dewatering system is installed, perform pumping test to determine when selected pumping rate lowers water level in well below pump intake. Adjust pump speed, discharge volume, or both to ensure proper operation of each pump.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes: |
| 1. Dewatering system. |
| 2. Surface water control system. |
| 3. System operation and maintenance. |
| 4. Water disposal. |
| B. Related Sections: |
| 1. Section 31 05 16 - Aggregates for Earthwork: Filter sand. |
| 2. Section 31 23 33 – Trenching and Backfilling for Utilities: Trenching for utilities below ground water table. |
| 3. Section 31 25 00 - Erosion and Sedimentation Controls: Surface water runoff control. |
| 1.2 REFERENCES |
| A. ASTM International: |
| 1. ASTM C33 - Standard Specification for Concrete Aggregates. |
| 1.3 DEFINITIONS |
| A. Dewatering includes the following: |
| 1. Lowering of ground water table and intercepting horizontal water seepage to prevent ground water from entering excavations and trenches. |
| 2. Reducing piezometric pressure within strata to prevent failure or heaving of excavations and trenches. |
| 3. Disposing of removed water. |
B. Surface Water Control: Removal of surface water within open excavations.
| 1.4 SYSTEM DESCRIPTION |
| A. Furnish standby equipment stored at Project site. Provide the following standby equipment, but not less than one of each type: |
| 1. Dewatering Pumps. |
| 2. Pump Power Units. |
| 3. Portable Electric Generators. |
| 4. Filter bags. |
| 5. Associated hoses and fittings. |
| 1.5 PERFORMANCE REQUIREMENTS |
| A. Design dewatering systems to: |
| 1. Remove accumulated water from excavations and trenches. |
| 2. Prevent damage to adjacent properties, buildings, structures, utilities, and facilities from construction operations. |
| 3. Maintain stability of sides and bottoms of excavations and trenches. |
| B. Design surface water control systems to: |
| 1. Collect and remove surface water and seepage entering excavation. |
| 1.6 SUBMITTALS |
| A. Section 01 33 00 - Submittal Procedures: Requirements for submittals. |
| B. Product Data: Submit data for each of the following: |
| 1. Dewatering Pumps: Indicate sizes, capacities, priming method, motor characteristics. |
| 2. Pumping equipment for control of surface water within excavation. |
| 1.7 CLOSEOUT SUBMITTALS |
| A. Section 01 77 00 - Closeout Procedures: Requirements for submittals. |
| B. Project Record Documents: Record actual locations and depths of capped wells and piping abandoned in place. |
| 1.8 QUALITY ASSURANCE |
| A. Comply with authorities having jurisdiction for the following: |
| 1. Water discharge and disposal from pumping operations. |
| B. Obtain permit from EPA under National Pollutant Discharge Elimination System (NPDES), for storm water discharge from construction sites. |
| C. Maintain one copy of document on site. |
| 1.9 SEQUENCING |
| A. Section 01 10 00 - Summary: Requirements for sequencing. |
| B. Sequence work to obtain required permits before start of dewatering operations. |
| 1.10 COORDINATION |
| A. Section 01 31 13 – Project Coordination: Requirements for coordination. |
| B. Coordinate work to permit the following construction operations to be completed on dry stable substrate. |
| 1. Trenching and Backfilling for utilities specified in Section 31 23 33. |
| PART 2 - PRODUCTS |
| 2.1 DEWATERING EQUIPMENT |
| A. Select dewatering equipment to meet specified performance requirements. |
| B. Surface Water Pumps: Self priming, diaphragm or centrifugal semi-open clog resistant impeller; engine driven type. |
| 1. Furnish pumps with screened suction hose and discharge hoses as required to suit application. |
| 2.2 ACCESSORIES |
| A. Filter bag: Non-woven geotextile. As specified in the Drawings. |
| PART 3 - EXECUTION |
| 3.1 EXAMINATION |
| A. Section 01 73 00 - Execution Requirements: Verification of existing conditions before starting work. |
| B. Call Pennsylvania One Call System, Inc. at 1-800-242-1776 not less than three working days before performing Work. |
| 1. Request underground utilities to be located and marked within and surrounding construction areas. |
| 3.2 PREPARATION |
| A. Protect existing adjacent buildings, structures, and improvements from damage caused by dewatering operations. |
| 3.3 DEWATERING SYSTEM |
| A. Locate system components to allow continuous dewatering operations without interfering with installation of permanent Work and existing public rights-of-way, sidewalks, and adjacent buildings, structures, and improvements. |
| B. Install pumps in accordance with manufacturer's instructions. |
| 3.4 SURFACE WATER CONTROL SYSTEM |
| A. Provide ditches, berms, and other devices to divert and drain surface water from excavation area as specified in Section 31 25 00 – Erosion and Sedimentation Controls. |
| B. Divert surface water and seepage water within excavation areas into sumps and pump water into drainage channels, storm drains, and settling basins in accordance with requirements of agencies having jurisdiction. Protect storm water appurtenances as... |
| C. Control and remove unanticipated water seepage into excavation. |
| 3.5 SYSTEM OPERATION AND MAINTENANCE |
| A. Operate dewatering system continuously as needed until backfilling is complete. |
| B. Provide supervision of dewatering system by personnel skilled in operation, maintenance, and replacement of system components. |
| C. Conduct daily observation of dewatering system and monitoring system. Make required repairs and perform scheduled maintenance. |
| D. Fill fuel tanks before tanks reach 25 percent capacity. |
| E. Start emergency generators at least twice each week to check operating condition. |
| F. When dewatering system cannot control water within excavation, notify Engineer and stop excavation work. |
| 1. Supplement or modify dewatering system and provide other remedial measures to control water within excavation. |
| 2. Demonstrate dewatering system operation complies with performance requirements before resuming excavation operations. |
| G. Modify dewatering and surface water control systems when operation causes or threatens to cause damage to new construction, existing site improvements, adjacent property, or adjacent water wells. |
| H. Correct unanticipated pressure conditions affecting dewatering system performance. |
| I. Do not discontinue dewatering operations without Engineer's approval. |
| 3.6 WATER DISPOSAL |
| A. Discharge water into existing storm sewer system, drainage channels, or settling basins as specified in Section 31 25 00 – Erosion and Sedimentation Controls. |
| 3.7 SYSTEM REMOVAL |
| A. Remove dewatering and surface water control systems after dewatering operations are discontinued. |
| B. Repair damage caused by dewatering and surface water control systems or resulting from failure of systems to protect property. |
| 3.8 FIELD QUALITY CONTROL |
| A. Section 01 40 00 - Quality Requirements: Field inspecting, testing, adjusting, and balancing. |
| B. After dewatering system is installed, perform pumping test to determine when selected pumping rate lowers water level in well below pump intake. Adjust pump speed, discharge volume, or both to ensure proper operation of each pump. |