This is a technical specification document for trenching work associated with the Biosolids Project 011139.0465 for Ephrata Borough Authority in Pennsylvania. The specification outlines the excavation, backfilling, and compaction requirements for utility trenches, including the materials, procedures, and quality control standards that contractors must follow. The work includes excavating subsoil for utilities, placing compacted fill from utility bedding to subgrade elevations, and backfilling and compaction operations. Key requirements include calling Pennsylvania One Call System at least three working days before work begins to locate underground utilities, maintaining maximum trench widths of 2 feet wider than pipe outside diameter, limiting open trenches to a maximum of 200 feet ahead of installed pipe, and not leaving more than 50 feet of trench open at the end of each working day. Sheeting and shoring are required for trenches deeper than 5 feet excavated through unstable material. The specification establishes tolerances of plus or minus 1 inch from required elevations for backfilled surfaces.

The specification requires multiple submittals including an Excavation Protection Plan with structural calculations, product data for geotextile fabric, and materials source documentation for imported fill. Backfilling must occur in continuous 8-inch maximum compacted depth layers using specified materials: subsoil fill, PennDOT 2A structural fill, and AASHTO No. 57 granular fill. Compaction testing is mandatory using ASTM D1557 for laboratory tests, ASTM D2922 for density, and ASTM D3017 for moisture content, with a minimum of one site visit per sewer pipe run between manhole structures and one visit per 400-foot section of force main or low-pressure sewer main installation. All compaction tests must achieve minimum 100 percent of maximum density for sanitary piping cover material, and test results must be submitted to the Engineer following each site visit.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

31 23 16.13 - TRENCHING

Herbert, Rowland & Grubic, Inc. 31 23 16.13 - 1 011139.0465

SECTION 31 23 16.13 - TRENCHING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Excavating trenches for utilities.

2. Compacted fill from top of utility bedding to subgrade elevations.

3. Backfilling and compaction.

B. Related Sections:

1. Section 03 30 00 - Cast-In-Place Concrete: Concrete materials.

2. Section 31 05 13 - Soils for Earthwork: Soils for fill.

3. Section 31 05 16 - Aggregates for Earthwork: Aggregates for fill.

4. Section 31 22 13 - Rough Grading: Topsoil and subsoil removal from site surface.

5. Section 31 23 16.26 - Rock Removal: Removal of rock during excavating.

6. Section 31 23 23 - Fill: General backfilling.

7. Section 32 91 19 - Landscape Grading: Filling of topsoil over backfilled trenches to finish grade elevation.

1.2 REFERENCES

A. American Association of State Highway and Transportation Officials:

1. AASHTO T180 - Standard Specification for Moisture-Density Relations of Soils

Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop.

B. ASTM International:

1. ASTM D698 - Standard Test Method for Laboratory Compaction Characteristics of

Soil Using Standard Effort (12,400 ft-lbf/ft3 (600 kN-m/m3).

2. ASTM D1557 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3).

3. ASTM D2922 - Standard Test Method for Density of Soil and Soil-Aggregate in

Place by Nuclear Methods (Shallow Depth).

4. ASTM D3017 - Standard Test Method for Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth).

1.3 DEFINITIONS

A. Utility: Any buried pipe, duct, conduit, or cable.

1.4 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Excavation Protection Plan: Describe sheeting, shoring, and bracing materials and installation required to protect excavations and adjacent structures and property; include structural calculations to support plan.

Herbert, Rowland & Grubic, Inc. 31 23 16.13 - 2 011139.0465

C. Product Data: Submit data for geotextile fabric indicating fabric and construction.

D. Materials Source: Submit name of imported fill materials suppliers.

1.5 FIELD MEASUREMENTS

A. Verify field measurements prior to fabrication.

1.6 COORDINATION

A. Section 01 31 13 – Project Coordination: Coordination and project conditions.

B. Verify Work associated with lower elevation utilities is complete before placing higher elevation utilities.

PART 2 - PRODUCTS

2.1 FILL MATERIALS

A. Subsoil Fill: Suitable Backfill and Embankment Material as specified in Section 31 05 13 – Soils for Earthwork.

B. Structural Fill: Type PennDOT 2A as specified in Section 31 05 16 – Aggregates for Earthwork.

C. Granular Fill: Type AASHTO No. 57 as specified in Section 31 05 16 – Aggregates for Earthwork.

D. Concrete: Structural concrete as specified in Section 03 30 00 – Cast-in-Place Concrete with compressive strength of 4,000 psi.

PART 3 - EXECUTION

3.1 LINES AND GRADES

A. Lay pipes to lines and grades indicated on Drawings.

1. Owner reserves right to make changes in lines, grades, and depths of utilities when changes are required for Project conditions.

2. Contractor shall not be entitled to extra compensation or to a claim for damages if change does not involve abandonment of an excavated trench.

B. Use laser-beam instrument with qualified operator to establish lines and grades.

3.2 PREPARATION

A. Call Pennsylvania One Call System, Inc. at 1-800-242-1776 not less than three working days before performing Work.

1. Request underground utilities to be located and marked within and surrounding construction areas.

Herbert, Rowland & Grubic, Inc. 31 23 16.13 - 3 011139.0465

B. Identify required lines, levels, contours, and datum locations.

C. Protect plant life, lawns, and other features remaining as portion of final landscaping.

D. Protect bench marks, existing structures, fences, sidewalks, paving, and curbs from excavating equipment and vehicular traffic.

E. Maintain and protect above and below grade utilities indicated to remain.

3.3 TRENCHING

A. Excavate subsoil required for utilities to locations shown on Drawings and necessary to complete work

B. Remove lumped subsoil, boulders, and rock up of 1/6 cubic yard, measured by volume.

Remove larger material as specified in Section 31 23 16.26 – Rock Removal.

C. Perform excavation within 24 inches of existing utility service in accordance with utility's requirements.

D. Do not advance open trench more than 200 feet ahead of installed pipe.

E. Cut trenches sufficiently wide to enable installation and allow inspection. Remove water or materials that interfere with Work.

F. Excavate bottom of trenches maximum 2 feet wider than outside diameter of pipe.

G. Excavate trenches to depth indicated on Drawings. Provide uniform and continuous bearing and support for bedding material and pipes.

H. Do not interfere with 45 degree bearing splay of foundations.

I. When Project conditions permit, side wall of excavation may be sloped starting 2 feet above top of pipe. When side walls cannot be sloped, provide sheeting and shoring to protect excavation as specified in this section.

J. When subsurface materials at bottom of trench are loose or soft, notify Engineer, and request instructions.

K. Cut out soft areas of subgrade not capable of compaction in place. Backfill with Fill AASHTO No. 3 coarse aggregate to within 6 inches of subgrade followed by AASHTO No.

57 coarse aggregate wrapped in non-woven geotextile and compact to density equal to or greater than requirements for subsequent backfill material.

L. Trim excavation. Hand trim for bell and spigot pipe joints. Remove loose matter.

M. Correct areas over excavated areas with compacted backfill as specified for authorized excavation or replace with fill concrete as directed by Engineer.

N. Remove excess subsoil not intended for reuse, from site.

Herbert, Rowland & Grubic, Inc. 31 23 16.13 - 4 011139.0465

3.4 SHEETING AND SHORING

A. Sheet, shore, and brace excavations to prevent danger to persons, structures and adjacent properties and to prevent caving, erosion, and loss of surrounding subsoil.

B. Support trenches more than 5 feet deep excavated through unstable, loose, or soft material. Provide sheeting, shoring, bracing, or other protection to maintain stability of excavation.

C. Design sheeting and shoring to be removed at completion of excavation work.

D. Repair damage caused by failure of the sheeting, shoring, or bracing and for settlement of filled excavations or adjacent soil and subsurface material.

E. Repair damage to new and existing Work from settlement, water or earth pressure or other causes resulting from inadequate sheeting, shoring, or bracing.

3.5 BACKFILLING

A. Backfill trenches to contours and elevations with unfrozen fill materials.

B. Systematically backfill to allow maximum time for natural settlement. Do not backfill over porous, wet, frozen, or spongy subgrade surfaces.

C. Place material in continuous layers as follows:

1. Subsoil Fill: Maximum 8 inches compacted depth.

2. Structural Fill: Maximum 8 inches compacted depth.

3. Granular Fill: Maximum 8 inches compacted depth.

D. Employ placement method that does not disturb or damage utilities in trench.

E. Maintain optimum moisture content of fill materials to attain required compaction density.

F. Do not leave more than 50 feet of trench open at end of working day.

G. Protect open trench to prevent danger to Owner and the public

3.6 TOLERANCES

A. Section 01 40 00 - Quality Requirements: Tolerances.

B. Top Surface of Backfilling: Plus or minus 1 inch from required elevations.

3.7 FIELD QUALITY CONTROL

A. Section 01 40 00 - Quality Requirements: Field inspecting, testing, adjusting, and balancing.

B. Perform laboratory material tests in accordance with ASTM D1557.

Herbert, Rowland & Grubic, Inc. 31 23 16.13 - 5 011139.0465

C. Perform in place compaction tests in accordance with the following:

1. Density Tests: ASTM D2922.

2. Moisture Tests: ASTM D3017.

D. When tests indicate Work does not meet specified requirements, remove Work, replace, compact, and retest.

E. Frequency of Tests:

1. On the 1st day of backfilling to determine the level of effort required to achieve the contract required compaction requirements.

2. Provide a minimum of one (1) site visit per sewer pipe run installation between manhole structures.

3. Provide a minimum of one (1) site visit per each 400-foot section of force main pipe and low pressure sewer main installation.

4. Compaction tests shall be performed at varying depths and locations per site visit, as determined by the Engineer.

5. Contractor and Contractors certified testing agent shall complete and submit compaction test results to Engineer following each site visit.

3.8 PROTECTION OF FINISHED WORK

A. Section 01 73 00 - Execution Requirements: Protecting finished work.

B. Reshape and re-compact fills subjected to vehicular traffic during construction.

3.9 SCHEDULE

A. Sanitary Piping:

1. Cover pipe and bedding with Fill Type: PennDOT 2A aggregate to subgrade elevation.

2. Compact uniformly to minimum 100 percent of maximum density.

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Excavating trenches for utilities.
2. Compacted fill from top of utility bedding to subgrade elevations.
3. Backfilling and compaction.
B. Related Sections:
1. Section 03 30 00 - Cast-In-Place Concrete: Concrete materials.
2. Section 31 05 13 - Soils for Earthwork: Soils for fill.
3. Section 31 05 16 - Aggregates for Earthwork: Aggregates for fill.
4. Section 31 22 13 - Rough Grading: Topsoil and subsoil removal from site surface.
5. Section 31 23 16.26 - Rock Removal: Removal of rock during excavating.
6. Section 31 23 23 - Fill: General backfilling.
7. Section 32 91 19 - Landscape Grading: Filling of topsoil over backfilled trenches to finish grade elevation.
1.2 REFERENCES
A. American Association of State Highway and Transportation Officials:
1. AASHTO T180 - Standard Specification for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop.
B. ASTM International:
1. ASTM D698 - Standard Test Method for Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/ft3 (600 kN-m/m3).
2. ASTM D1557 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3).
3. ASTM D2922 - Standard Test Method for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth).
4. ASTM D3017 - Standard Test Method for Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth).
1.3 DEFINITIONS
A. Utility: Any buried pipe, duct, conduit, or cable.
1.4 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Excavation Protection Plan: Describe sheeting, shoring, and bracing materials and installation required to protect excavations and adjacent structures and property; include structural calculations to support plan.
C. Product Data: Submit data for geotextile fabric indicating fabric and construction.
D. Materials Source: Submit name of imported fill materials suppliers.
1.5 FIELD MEASUREMENTS
A. Verify field measurements prior to fabrication.
1.6 COORDINATION
A. Section 01 31 13 – Project Coordination: Coordination and project conditions.
B. Verify Work associated with lower elevation utilities is complete before placing higher elevation utilities.
PART 2 - PRODUCTS
2.1 FILL MATERIALS
A. Subsoil Fill: Suitable Backfill and Embankment Material as specified in Section 31 05 13 – Soils for Earthwork.
B. Structural Fill: Type PennDOT 2A as specified in Section 31 05 16 – Aggregates for Earthwork.
C. Granular Fill: Type AASHTO No. 57 as specified in Section 31 05 16 – Aggregates for Earthwork.
D. Concrete: Structural concrete as specified in Section 03 30 00 – Cast-in-Place Concrete with compressive strength of 4,000 psi.
PART 3 - EXECUTION
3.1 LINES AND GRADES
A. Lay pipes to lines and grades indicated on Drawings.
1. Owner reserves right to make changes in lines, grades, and depths of utilities when changes are required for Project conditions.
2. Contractor shall not be entitled to extra compensation or to a claim for damages if change does not involve abandonment of an excavated trench.

B. Use laser-beam instrument with qualified operator to establish lines and grades.

3.2 PREPARATION
A. Call Pennsylvania One Call System, Inc. at 1-800-242-1776 not less than three working days before performing Work.
1. Request underground utilities to be located and marked within and surrounding construction areas.
B. Identify required lines, levels, contours, and datum locations.
C. Protect plant life, lawns, and other features remaining as portion of final landscaping.
D. Protect bench marks, existing structures, fences, sidewalks, paving, and curbs from excavating equipment and vehicular traffic.
E. Maintain and protect above and below grade utilities indicated to remain.
3.3 TRENCHING
A. Excavate subsoil required for utilities to locations shown on Drawings and necessary to complete work
B. Remove lumped subsoil, boulders, and rock up of 1/6 cubic yard, measured by volume. Remove larger material as specified in Section 31 23 16.26 – Rock Removal.
C. Perform excavation within 24 inches of existing utility service in accordance with utility's requirements.
D. Do not advance open trench more than 200 feet ahead of installed pipe.
E. Cut trenches sufficiently wide to enable installation and allow inspection. Remove water or materials that interfere with Work.
F. Excavate bottom of trenches maximum 2 feet wider than outside diameter of pipe.
G. Excavate trenches to depth indicated on Drawings. Provide uniform and continuous bearing and support for bedding material and pipes.
H. Do not interfere with 45 degree bearing splay of foundations.
I. When Project conditions permit, side wall of excavation may be sloped starting 2 feet above top of pipe. When side walls cannot be sloped, provide sheeting and shoring to protect excavation as specified in this section.
J. When subsurface materials at bottom of trench are loose or soft, notify Engineer, and request instructions.
K. Cut out soft areas of subgrade not capable of compaction in place. Backfill with Fill AASHTO No. 3 coarse aggregate to within 6 inches of subgrade followed by AASHTO No. 57 coarse aggregate wrapped in non-woven geotextile and compact to density equ...
L. Trim excavation. Hand trim for bell and spigot pipe joints. Remove loose matter.
M. Correct areas over excavated areas with compacted backfill as specified for authorized excavation or replace with fill concrete as directed by Engineer.
N. Remove excess subsoil not intended for reuse, from site.
3.4 SHEETING AND SHORING
A. Sheet, shore, and brace excavations to prevent danger to persons, structures and adjacent properties and to prevent caving, erosion, and loss of surrounding subsoil.
B. Support trenches more than 5 feet deep excavated through unstable, loose, or soft material. Provide sheeting, shoring, bracing, or other protection to maintain stability of excavation.
C. Design sheeting and shoring to be removed at completion of excavation work.
D. Repair damage caused by failure of the sheeting, shoring, or bracing and for settlement of filled excavations or adjacent soil and subsurface material.
E. Repair damage to new and existing Work from settlement, water or earth pressure or other causes resulting from inadequate sheeting, shoring, or bracing.
3.5 BACKFILLING
A. Backfill trenches to contours and elevations with unfrozen fill materials.
B. Systematically backfill to allow maximum time for natural settlement. Do not backfill over porous, wet, frozen, or spongy subgrade surfaces.
C. Place material in continuous layers as follows:
1. Subsoil Fill: Maximum 8 inches compacted depth.
2. Structural Fill: Maximum 8 inches compacted depth.
3. Granular Fill: Maximum 8 inches compacted depth.
D. Employ placement method that does not disturb or damage utilities in trench.
E. Maintain optimum moisture content of fill materials to attain required compaction density.
F. Do not leave more than 50 feet of trench open at end of working day.
G. Protect open trench to prevent danger to Owner and the public
3.6 TOLERANCES
A. Section 01 40 00 - Quality Requirements: Tolerances.
B. Top Surface of Backfilling: Plus or minus 1 inch from required elevations.
3.7 FIELD QUALITY CONTROL
A. Section 01 40 00 - Quality Requirements: Field inspecting, testing, adjusting, and balancing.
B. Perform laboratory material tests in accordance with ASTM D1557.
C. Perform in place compaction tests in accordance with the following:
1. Density Tests: ASTM D2922.
2. Moisture Tests: ASTM D3017.
D. When tests indicate Work does not meet specified requirements, remove Work, replace, compact, and retest.
E. Frequency of Tests:
1. On the 1st day of backfilling to determine the level of effort required to achieve the contract required compaction requirements.
2. Provide a minimum of one (1) site visit per sewer pipe run installation between manhole structures.
3. Provide a minimum of one (1) site visit per each 400-foot section of force main pipe and low pressure sewer main installation.
4. Compaction tests shall be performed at varying depths and locations per site visit, as determined by the Engineer.
5. Contractor and Contractors certified testing agent shall complete and submit compaction test results to Engineer following each site visit.
3.8 PROTECTION OF FINISHED WORK
A. Section 01 73 00 - Execution Requirements: Protecting finished work.
B. Reshape and re-compact fills subjected to vehicular traffic during construction.
3.9 SCHEDULE
A. Sanitary Piping:
1. Cover pipe and bedding with Fill Type: PennDOT 2A aggregate to subgrade elevation.
2. Compact uniformly to minimum 100 percent of maximum density.