31 22 13 - Rough Grading.pdf
PDF 225 KB Posted
- Attached to
- Biosolids Project 011139.0465
- Solicitation number
- US.260443
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a specification document for Section 31 22 13 - Rough Grading, prepared by Herbert, Rowland & Grubic, Inc., for the Biosolids Project 011139.0465 at Ephrata Borough Authority in Pennsylvania. The scope of work includes excavating topsoil and subsoil, cutting, grading, filling, rough contouring, and compacting the site for site utilities. The work must comply with multiple ASTM International standards and AASHTO specifications for soil testing, compaction, and density verification. Key submission requirements include identification of imported materials suppliers and manufacturer's certificates verifying products meet specified requirements. The contractor must contact Pennsylvania One Call System, Inc. at least three working days before commencing work to locate and mark underground utilities. Topsoil excavation must be performed without mixing foreign materials and cannot occur when soil is wet; excess topsoil not intended for reuse must be removed from the site. The tolerance for the top surface of subgrade is plus or minus 1/10 foot from the required elevation, and the contractor must maintain accurate project record documents documenting the actual locations of remaining utilities by horizontal dimensions, elevations, and slope gradients.
The specification references related sections for soils, aggregates, trenching, rock removal, fill materials, and landscape grading, indicating this rough grading work is part of a larger construction project. The work must be performed in accordance with State of Pennsylvania Department of Transportation standards and applicable ASTM testing methodologies. No pricing information, set-asides, incumbency status, or contract term details are contained within this technical specification document.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
31 22 13 - ROUGH GRADING
Herbert, Rowland & Grubic, Inc. 31 22 13 - 1 011139.0465
SECTION 31 22 13 - ROUGH GRADING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Excavating topsoil.
2. Excavating subsoil.
3. Cutting, grading, filling, rough contouring, and compacting site for site utilities.
B. Related Sections:
1. Section 31 05 13 - Soils for Earthwork: Soils for fill.
2. Section 31 05 16 - Aggregates for Earthwork: Aggregates for fill.
3. Section 31 23 16.13 - Trenching: Trenching and backfilling for utilities.
4. Section 31 23 16.26 - Rock Removal.
5. Section 31 23 23 - Fill: General building area backfilling.
6. Section 32 91 19 - Landscape Grading: Finish grading with topsoil to contours.
1.2 REFERENCES
A. American Association of State Highway and Transportation Officials:
1. AASHTO T180 - Standard Specification for Moisture-Density Relations of Soils
Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop.
B. ASTM International:
1. ASTM C136 - Standard Test Method for Sieve Analysis of Fine and Coarse
Aggregates.
2. ASTM D698 - Standard Test Method for Laboratory Compaction Characteristics of
Soil Using Standard Effort (12,400 ft-lbf/ft3 (600 kN-m/m3).
3. ASTM D1556 - Standard Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method.
4. ASTM D1557 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3).
5. ASTM D2167 - Standard Test Method for Density and Unit Weight of Soil in Place by the Rubber Balloon Method.
6. ASTM D2419 - Standard Test Method for Sand Equivalent Value of Soils and Fine
Aggregate.
7. ASTM D2434 - Standard Test Method for Permeability of Granular Soils (Constant
Head).
8. ASTM D2922 - Standard Test Method for Density of Soil and Soil-Aggregate in
Place by Nuclear Methods (Shallow Depth).
9. ASTM D3017 - Standard Test Method for Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth).
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
Herbert, Rowland & Grubic, Inc. 31 22 13 - 2 011139.0465
B. Materials Source: Submit name of imported materials suppliers.
C. Manufacturer's Certificate: Certify Products meet or exceed specified requirements.
1.4 CLOSEOUT SUBMITTALS
A. Section 01 77 00 - Closeout Requirements: Requirements for submittals.
B. Project Record Documents: Accurately record actual locations of utilities remaining by horizontal dimensions, elevations or inverts, and slope gradients.
1.5 QUALITY ASSURANCE
A. Perform Work in accordance with ASTM C136, ASTM D2419, and ASTM D2434.
B. Perform Work in accordance with State of Pennsylvania Department of Transportation standard.
PART 2 - PRODUCTS
2.1 MATERIALS
A. As identified in Section 31 23 23 – Fill.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution Requirements: Verification of existing conditions before starting work.
B. Verify survey bench mark and intended elevations for the Work are as indicated on Drawings.
3.2 PREPARATION
A. Call Pennsylvania One Call System, Inc. at 1-800-242 not less than three working days before performing Work.
1. Request underground utilities to be located and marked within and surrounding construction areas.
B. Identify required lines, levels, contours, and datum.
C. Notify utility company to remove and relocate utilities.
D. Protect utilities indicated to remain from damage.
Herbert, Rowland & Grubic, Inc. 31 22 13 - 3 011139.0465
3.3 TOPSOIL EXCAVATION
A. Excavate topsoil from areas to be further excavated, relandscaped, or regraded, without mixing with foreign materials for use in finish grading.
B. Do not excavate wet topsoil.
C. Stockpile should not be located at site.
D. Remove excess topsoil not intended for reuse, from site.
3.4 TOLERANCES
A. Section 01 40 00 - Quality Requirements: Tolerances.
B. Top Surface of Subgrade: Plus or minus 1/10 foot from required elevation.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes: |
| 1. Excavating topsoil. |
| 2. Excavating subsoil. |
| 3. Cutting, grading, filling, rough contouring, and compacting site for site utilities. |
| B. Related Sections: |
| 1. Section 31 05 13 - Soils for Earthwork: Soils for fill. |
| 2. Section 31 05 16 - Aggregates for Earthwork: Aggregates for fill. |
| 3. Section 31 23 16.13 - Trenching: Trenching and backfilling for utilities. |
| 4. Section 31 23 16.26 - Rock Removal. |
| 5. Section 31 23 23 - Fill: General building area backfilling. |
| 6. Section 32 91 19 - Landscape Grading: Finish grading with topsoil to contours. |
| 1.2 REFERENCES |
| A. American Association of State Highway and Transportation Officials: |
| 1. AASHTO T180 - Standard Specification for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop. |
| B. ASTM International: |
| 1. ASTM C136 - Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates. |
| 2. ASTM D698 - Standard Test Method for Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/ft3 (600 kN-m/m3). |
| 3. ASTM D1556 - Standard Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method. |
| 4. ASTM D1557 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3). |
| 5. ASTM D2167 - Standard Test Method for Density and Unit Weight of Soil in Place by the Rubber Balloon Method. |
| 6. ASTM D2419 - Standard Test Method for Sand Equivalent Value of Soils and Fine Aggregate. |
| 7. ASTM D2434 - Standard Test Method for Permeability of Granular Soils (Constant Head). |
| 8. ASTM D2922 - Standard Test Method for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth). |
| 9. ASTM D3017 - Standard Test Method for Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth). |
| 1.3 SUBMITTALS |
| A. Section 01 33 00 - Submittal Procedures: Requirements for submittals. |
| B. Materials Source: Submit name of imported materials suppliers. |
| C. Manufacturer's Certificate: Certify Products meet or exceed specified requirements. |
| 1.4 CLOSEOUT SUBMITTALS |
| A. Section 01 77 00 - Closeout Requirements: Requirements for submittals. |
| B. Project Record Documents: Accurately record actual locations of utilities remaining by horizontal dimensions, elevations or inverts, and slope gradients. |
| 1.5 QUALITY ASSURANCE |
| A. Perform Work in accordance with ASTM C136, ASTM D2419, and ASTM D2434. |
| B. Perform Work in accordance with State of Pennsylvania Department of Transportation standard. |
| PART 2 - PRODUCTS |
| 2.1 MATERIALS |
| A. As identified in Section 31 23 23 – Fill. |
| PART 3 - EXECUTION |
| 3.1 EXAMINATION |
| A. Section 01 73 00 - Execution Requirements: Verification of existing conditions before starting work. |
| B. Verify survey bench mark and intended elevations for the Work are as indicated on Drawings. |
| 3.2 PREPARATION |
| A. Call Pennsylvania One Call System, Inc. at 1-800-242 not less than three working days before performing Work. |
| 1. Request underground utilities to be located and marked within and surrounding construction areas. |
| B. Identify required lines, levels, contours, and datum. |
| C. Notify utility company to remove and relocate utilities. |
| D. Protect utilities indicated to remain from damage. |
| 3.3 TOPSOIL EXCAVATION |
| A. Excavate topsoil from areas to be further excavated, relandscaped, or regraded, without mixing with foreign materials for use in finish grading. |
| B. Do not excavate wet topsoil. |
| C. Stockpile should not be located at site. |
| D. Remove excess topsoil not intended for reuse, from site. |
| 3.4 TOLERANCES |
| A. Section 01 40 00 - Quality Requirements: Tolerances. |
| B. Top Surface of Subgrade: Plus or minus 1/10 foot from required elevation. |
File details come from the government source that posted it. Updated .