2. AF Form 66.pdf

PDF 107 KB Posted

Attached to
Replace Spill Buckets at 4 Launch Facilities (FE Warren AFB, WY) AMENDMENT 01 Federal contract opportunity
Solicitation number
FA461325R0002
Issued by
Department of the Air Force Global Strike Command

About this file

This is an AF Form 66 Schedule of Material Submittals form for a project to replace UST spill buckets at locations M-02, O-04, O-09, and O-10 (Project GHLN 25-0240). The form details 26 required submittals with their corresponding submission requirements and deadlines.

Key submittals include EAL Documentation Safety Requirements (due when NTP is issued), various permits including AF Form 103-Dig Permit and AF Form 592-Burn Permit (due 3-14 days prior to site NTP), Safety Plan and Material Safety Data Sheets (due 10 days after NTP), and specific equipment requirements such as OPW 1SC-3122D Spill Bucket, Man-way Sump OPW 44CD-PL10, and TLS 350/450 Prob/Sensor Card (all due 10 days after NTP). The form also requires various construction materials submittals including backfill material, asphalt mix formula, concrete specifications, and paint striping details. Final documentation requirements include warranties, as-built drawings, and operations/maintenance documents, which are due 30 days prior to Delivery Order close-out.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Spill Buckets at 4 Launch Facilities (FE Warren AFB, WY) AMENDMENT 01, newest first.
File Type Posted
Notice ID FA461325R0002 AMD 01.pdf PDF
Conformed Copy.pdf PDF
Request for Proposal AMD 01.pdf PDF
8. MFR UNCI Receipt for Post Site Visit Photos.pdf PDF
7. Post Site Visit Question and Answer.pdf PDF
Request for Proposal.pdf PDF
3a. SPRS Registration.pdf PDF
3b. NIST SP 800-171 Assessment.pdf PDF
4. Combined Wage Determinations.pdf PDF
Solicitation - FA461325R0002.pdf PDF
1. SOW 25 Feb 2025.pdf PDF
3c. Quick Entry Guide.pdf PDF
5. SF 24 Bid Bond Form.pdf PDF
6. Cost Estimate Breakdown.xlsx XLSX spreadsheet
3. MFR UNCI Control & Receipt.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT NUMBER SOLICITATION/CONTRACT NUMBER

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NUMBER OF COPIES REQUIRED

LI

N

E N

U M

B

ER

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE OF

SUBMITTAL

C

ER

TI

FI

C A

TI

O

N O

F C

O M

PL

IA

N C

E

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

C O

LO

R

S

EL

EC

TI

O N

M A

N U

FA

C

TU

R

E' S

R

EC

O M

M

EN

D A

TI

O

N S

M A

N U

FA

C

TU

R

ER

'S

W

A R

R A

N

TY

C A

TA

LO

G D

A

TA

O

PE

R A

TI

N

G

IN

ST

R U

C

TI

O N

S

TE

ST

S

R

EP

O R

TS

R

EQ

U

IR

ED

S

U B

M

IS

SI

O

D

TE

TE

R

EC

EI

VE

C

N

TR

A C

TI

N

G

D A

TE

T

O C

IV

IL

EN

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D A

TE

FO

LL

O W

-U P

DATE CONTRACTOR NOTIFIED

C O

N

TR

A C

TO

R

ES

U

B M

IT

TA

L

FI

N

A L

A

PP

R O

VA

L

REMARKS

APPROVED DISAPPROVED

1 EAL Documentation Safety Requirements

1 When NTP is issued SOW SECURITY REQUIREMENTS

2 Tempory blocked access 1 21 days prior to interuption

SOW SECURITY REQUIREMENTS item #11

3 AF Form 103-Dig Permit General CSI 01B

14 Days

Prior to site

NTP

SOW CSI 01, Item #9

4 AF Form 592-Burn Permit General CSI 01C

3 Days

Prior to Site

NTP

SOW CSI 01, Item #10

All Permits (Local, State and Federal) NPDES, ROW, or Other

3 Days

Prior to Site

NTP

SOW

6 Safety Plan 4 10 Days after NTP SOW CSI01, Item #13

7 Material Safety Data Sheets 4 10 Days after NTP SOW CSI 01, Items #2-4

Land Owner Release/Agreement (If Required)

3 Days

Prior to Site

NTP

If required per the scope of work ; SOW SECURITY REQUIREMENTS , items #9

9 Hazardous Materials 4 10 Days after NTP SOW CSI 01, Item #12-14

10 Warranties 2 30 Days

Prior to DO Close Out

SOW CSI 01, Items #2, 19

11 Storage Plan (If Required) 4 10 Days after NTP SOW

12 Project Schedule 4 10 Days after NTP SOW CSI 01, Items #2, 19

13 As-Built Drawings For Each Site General

30 Days

Prior to DO Close Out

SOW CSI 01, items 17-18

14 Testing Documentation General

30 Days

Prior to DO Close Out

SOW

Concrete - Type, PSI, Ration, Air

10 Days after

NTP

SOW

AF Form 66, OCT 89 PREVIOUS EDITION WILL BE USED See Specifications for Frequency

Replace UST Spill Buckets M-02, O-04, O-09, and O-10

GHLN 25-0240

PROJECT TITLE

PROJECT NUMBER SOLICITATION/CONTRACT NUMBER

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NUMBER OF COPIES REQUIRED

LI

N

E N

U M

B

ER

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE OF

SUBMITTAL

C

ER

TI

FI

C A

TI

O

N O

F C

O M

PL

IA

N C

E

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

C O

LO

R

S

EL

EC

TI

O N

M A

N U

FA

C

TU

R

E' S

R

EC

O M

M

EN

D A

TI

O

N S

M A

N U

FA

C

TU

R

ER

'S

W

R

R A

N

TY

C A

TA

LO

G D

A

TA

O

PE

R A

TI

ST

R U

C

TI

O N

S

TE

ST

S

R

EP

O R

TS

R

EQ

U

IR

ED

S

U B

M

IS

SI

TE

TE

R

EC

EI

VE

C

N

TR

A C

TI

N

G

D A

TE

T

O C

IV

IL

EN

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D A

TE

FO

LL

O W

-U P

DATE CONTRACTOR NOTIFIED

C O

N

TR

A C

TO

ES

U

B M

IT

TA

L

FI

N

A L

A

PP

R O

VA

L

REMARKS

APPROVED DISAPPROVED

16 Spill Bucket - OPW 1SC-3122D 2 2 2 10 Days after NTP

SOW, Drawings

17 Man-way Sump, OPW 44CD-

PL10

2 2 2 10 Days after NTP

SOW, Drawings

18 #18 AWG stranded and shielded Belden 300V wire

2 2 10 Days after NTP

SOW, Drawings

19 PVC Coated Conduit 2 2 10 Days after NTP

SOW, Drawings

20 Prob/Sensor Card - TLS 350/450

2 2 2 2 10 Days after NTP

SOW, Drawings

21 NEMA Weatherproof Enclosure

2 2 2 10 Days after NTP

SOW, Drawings

22 Backfill Material 4 10 Days after NTP

SOW, Drawings

23 Asphalt - Job Mix Formula 4 10 Days after NTP

SOW, Drawings

24 Flowable Mix Concrete (If used)

4 10 Days after NTP

SOW, Drawings

25 Paint Striping 4 10 Days after NTP

SOW, Drawings

26 Operations and Maintenance Docs

30 days prior to DO Close Out

SOW, Drawings

AF Form 66, OCT 89 PREVIOUS EDITION WILL BE USED See Specifications for Frequency

Replace UST Spill Buckets M-02, O-04, O-09, and O-10

GHLN 25-0240

PROJECT TITLE

Form 66 (GHLN 25-0240 pg 1)
Sheet 1
Form 66 (GHLN 25-0240 pg 2)
Sheet 1

File details come from the government source that posted it. Updated .