03 35 00 - Concrete Finishing (VPR).pdf

PDF 237 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This file is a technical specification section for concrete finishing work prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 at Ephrata Borough Authority in Pennsylvania. The specification details finishing requirements for concrete floors and floor toppings, including surface treatments and slip-resistant applications. Work includes steel-troweled exposed surfaces, light broom finishing for walking surfaces, and the application of a colorless, low-VOC water-based sealer containing acrylic copolymers meeting ASTM C1315 Class A specifications with minimum 30 percent solids. The specification requires compliance with American Concrete Institute standards ACI 301 and ACI 302.1, with sealer application occurring after concrete has cured for a minimum of 28 days. Floor surfaces must maintain a maximum variation of flatness of 1/8 inch in 10 feet, and sloped surfaces to floor drains must be uniformly graded at nominal 1/8 inch per foot. The specification mandates that manufacturers and installers/applicators possess minimum three years of documented experience in their respective fields, with installer approval required from the product manufacturer.

The specification identifies L&M Construction Chemicals Inc. Dress & Seal WB 30 as the specified sealer product or approved substitutes. Materials must be delivered in manufacturer's original packaging, inspected upon receipt, and stored in clean, dry locations protected from moisture and dust. Ambient conditions during installation must maintain a minimum temperature of 50 degrees Fahrenheit with sufficient ventilation. Quality control requires the Engineer to identify any areas not meeting specifications, with defects corrected through grinding or removal and replacement of defective work. Operation and maintenance data must be submitted during closeout procedures, and product data, manufacturer's certificates, and applicator qualifications require submittal according to Section 01 33 00 procedures.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

03 35 00 - CONCRETE FINISHING

Herbert, Rowland & Grubic, Inc. 03 35 00 - 1 011139.0465

SECTION 03 35 00 - CONCRETE FINISHING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Finishing concrete floors and floor toppings.

2. Floor surface treatment.

B. Related Requirements:

1. Section 03 30 00 - Cast-in-Place Concrete

2. Section 03 39 00 - Concrete Curing

1.2 REFERENCE STANDARDS

A. American Concrete Institute:

1. ACI 301 - Specifications for Structural Concrete for Buildings.

2. ACI 302.1 - Guide to Concrete Floor and Slab Construction.

B. ASTM International:

1. ASTM C1315 – Standard Specification for Liquid Membrane-Forming Compounds having Special Properties for Curing and Sealing Concrete.

1.3 COORDINATION

A. Section 01 31 13 – Project Coordination: Requirements for coordination.

B. Coordinate Work of this Section with concrete floor placement and concrete floor curing.

1.4 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Product Data: Submit manufacturer information on concrete hardener, sealer, curing compounds, curing papers, slip-resistant treatment, compatibilities, and limitations.

C. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.

D. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections.

E. Qualifications Statements:

1. Submit qualifications for manufacturer and applicator/installer.

1.5 CLOSEOUT SUBMITTALS

A. Section 01 77 00 - Closeout Procedures. Requirements for submittals.

Herbert, Rowland & Grubic, Inc. 03 35 00 - 2 011139.0465

B. Operation and Maintenance Data: Submit information on maintenance renewal of applied coatings.

1.6 QUALITY ASSURANCE

A. Perform Work according to ACI 301 and 302.1.

1.7 QUALIFICATIONS

A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum three years' documented experience.

B. Installer/Applicator: Company specializing in performing Work of this Section with minimum three years' documented experience and approved by manufacturer.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Section 01 61 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products.

B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.

C. Store materials according to manufacturer instructions.

D. Protection:

1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.

2. Provide additional protection according to manufacturer instructions.

1.9 AMBIENT CONDITIONS

A. Section 01 50 00 - Temporary Facilities and Controls: Requirements for ambient condition control facilities for product storage and installation.

B. Temporary Heat: Maintain minimum ambient temperature of 50 deg. F.

C. Ventilation: Sufficient to prevent injurious gases from temporary heat or other sources from affecting personnel or concrete.

PART 2 - PRODUCTS

2.1 COMPOUNDS - HARDENERS AND SEALERS

A. Sealer:

1. Colorless low VOC water-based solution containing acrylic copolymers.

a. ASTM C1315, Class A, minimum 30 percent solids.

b. Shall be compatible with specified coating and floor treatments.

2. Manufacturers:

a. L&M Construction Chemicals Inc. Dress & Seal WB 30.

Herbert, Rowland & Grubic, Inc. 03 35 00 - 3 011139.0465

b. Or approved substitute.

2.2 SLIP-RESISTANT TREATMENT

A. Description:

1. Material: Silica sand.

2. Color: As selected by owner/architect from manufacturer's standard range.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 - Execution Requirements: Requirements for application examination.

B. Verify that floor surfaces are acceptable to receive Work of this Section.

3.2 APPLICATION

A. Concrete Floor Finishing:

1. Comply with ACI 301 and ACI 302.1.

2. Steel-trowel surfaces which are indicated to be exposed unless otherwise scheduled.

3. Light Broom Finish for walking surfaces not receiving coatings.

a. Provide uniform slip-resistant texture suitable for pedestrian traffic and washdown condition.

b. Apply perpendicular to the primary path of travel.

c. Excessive rough broom finishes will not be accepted.

4. Floor Drains:

a. In areas with floor drains, maintain design floor elevation at walls.

b. Slope surfaces uniformly to drains at nominal 1/8 in./ft or as indicated on drawings.

B. Floor Surface Treatment:

1. Apply sealer on floor surfaces- one coat minimum or as recommended by manufacturer after concrete has cured for a minimum of 28 days.

3.3 TOLERANCES

A. Section 01 40 00 - Quality Requirements: Requirements for tolerances.

B. Maximum Variation of Surface Flatness for Exposed Concrete Floors: 1/8 inch in 10 feet.

3.4 FIELD QUALITY CONTROL

A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.

B. Acceptance:

1. Areas not meeting specified requirements will be identified by the Engineer and shall be corrected.

Herbert, Rowland & Grubic, Inc. 03 35 00 - 4 011139.0465

2. Correct defects in defined traffic floor by grinding or removal and replacement of defective Work.

3. Remeasure corrected areas by procedure as specified in TOLERANCES Article.

3.5 ATTACHMENTS

A. Floor Finish Schedule

1. Light Broom Finish

a. Interior Equipment Pads

b. Framed Floor Slabs

c. Exterior Slabs on Grade

d. Sidewalks and exterior walking surfaces.

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Finishing concrete floors and floor toppings.
2. Floor surface treatment.
B. Related Requirements:
1. Section 03 30 00 - Cast-in-Place Concrete
2. Section 03 39 00 - Concrete Curing
1.2 REFERENCE STANDARDS
A. American Concrete Institute:
1. ACI 301 - Specifications for Structural Concrete for Buildings.
2. ACI 302.1 - Guide to Concrete Floor and Slab Construction.
B. ASTM International:
1. ASTM C1315 – Standard Specification for Liquid Membrane-Forming Compounds having Special Properties for Curing and Sealing Concrete.
1.3 COORDINATION
A. Section 01 31 13 – Project Coordination: Requirements for coordination.
B. Coordinate Work of this Section with concrete floor placement and concrete floor curing.
1.4 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data: Submit manufacturer information on concrete hardener, sealer, curing compounds, curing papers, slip-resistant treatment, compatibilities, and limitations.
C. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.
D. Field Quality-Control Submittals: Indicate results of Contractor-furnished tests and inspections.
E. Qualifications Statements:
1. Submit qualifications for manufacturer and applicator/installer.
1.5 CLOSEOUT SUBMITTALS
A. Section 01 77 00 - Closeout Procedures. Requirements for submittals.
B. Operation and Maintenance Data: Submit information on maintenance renewal of applied coatings.
1.6 QUALITY ASSURANCE
A. Perform Work according to ACI 301 and 302.1.
1.7 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum three years' documented experience.
B. Installer/Applicator: Company specializing in performing Work of this Section with minimum three years' documented experience and approved by manufacturer.
1.8 DELIVERY, STORAGE, AND HANDLING
A. Section 01 61 00 - Product Requirements: Requirements for transporting, handling, storing, and protecting products.
B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.
C. Store materials according to manufacturer instructions.
D. Protection:
1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.
2. Provide additional protection according to manufacturer instructions.
1.9 AMBIENT CONDITIONS
A. Section 01 50 00 - Temporary Facilities and Controls: Requirements for ambient condition control facilities for product storage and installation.
B. Temporary Heat: Maintain minimum ambient temperature of 50 deg. F.
C. Ventilation: Sufficient to prevent injurious gases from temporary heat or other sources from affecting personnel or concrete.
PART 2 - PRODUCTS
2.1 COMPOUNDS - HARDENERS AND SEALERS
A. Sealer:
1. Colorless low VOC water-based solution containing acrylic copolymers.
2. Manufacturers:
a. L&M Construction Chemicals Inc. Dress & Seal WB 30.
b. Or approved substitute.
2.2 SLIP-RESISTANT TREATMENT
A. Description:
1. Material: Silica sand.
2. Color: As selected by owner/architect from manufacturer's standard range.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution Requirements: Requirements for application examination.
B. Verify that floor surfaces are acceptable to receive Work of this Section.
3.2 APPLICATION
A. Concrete Floor Finishing:
1. Comply with ACI 301 and ACI 302.1.
2. Steel-trowel surfaces which are indicated to be exposed unless otherwise scheduled.
3. Light Broom Finish for walking surfaces not receiving coatings.
a. Provide uniform slip-resistant texture suitable for pedestrian traffic and washdown condition.
b. Apply perpendicular to the primary path of travel.
c. Excessive rough broom finishes will not be accepted.
4. Floor Drains:
a. In areas with floor drains, maintain design floor elevation at walls.
b. Slope surfaces uniformly to drains at nominal 1/8 in./ft or as indicated on drawings.
B. Floor Surface Treatment:
1. Apply sealer on floor surfaces- one coat minimum or as recommended by manufacturer after concrete has cured for a minimum of 28 days.
3.3 TOLERANCES
A. Section 01 40 00 - Quality Requirements: Requirements for tolerances.
B. Maximum Variation of Surface Flatness for Exposed Concrete Floors: 1/8 inch in 10 feet.
3.4 FIELD QUALITY CONTROL
A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.
B. Acceptance:
1. Areas not meeting specified requirements will be identified by the Engineer and shall be corrected.
2. Correct defects in defined traffic floor by grinding or removal and replacement of defective Work.
3. Remeasure corrected areas by procedure as specified in TOLERANCES Article.
3.5 ATTACHMENTS
A. Floor Finish Schedule
1. Light Broom Finish
a. Interior Equipment Pads
b. Framed Floor Slabs
c. Exterior Slabs on Grade
d. Sidewalks and exterior walking surfaces.

File details come from the government source that posted it. Updated .