01 77 00 - Closeout Procedures-R.pdf

PDF 219 KB Posted

Attached to
Alterations for Penn Township Municipal Building - Shop
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a closeout procedures document related to a construction project for Penn Township Municipal Building alterations in Pennsylvania. The project encompasses two primary contracts: Contract #1 covers general construction work including demolition, sitework, concrete, general alteration construction, exterior replacement finishes, storefront glass, replacement doors, and associated work; Contract #2 addresses electrical construction work providing heating and lighting for the new vestibule, rear entry, and side entry areas. Bids were to be received online via the PennBid Program until 10:00 AM local time on September 3, 2026, with public display of bids immediately following the deadline. The Notice of Intent to Award was scheduled for consideration by the Township Board of Supervisors at their September 14, 2026 meeting at the Township Office.

Bidding documents were available for download from https://pennbid.bonfirehub.com/, with prospective bidders urged to register as plan holders on the designated website. All official notifications, addenda, and bidding documents were to be issued exclusively through the designated website, with neither the Owner nor Engineer accepting responsibility for documents obtained from alternative sources. The document emphasizes the importance of registered plan holders monitoring the website for periodic updates regarding addenda, lists of registered plan holders, reports, and other relevant bidding information.

View the file

Other files

File Type Posted
00 01 10 - Table of Contents.pdf PDF
00 01 01 - LA Cover - need date.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
01 12 00 - Multiple Contract Summary.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
2026.07.14 - H9 - Penn Twp Office - Bid Set - SEALED.pdf PDF
00 55 00 - Notice to Proceed.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 62 76 - App for Payment.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
2026.07.14 - H9 - Penn Twp Shop - Bid Set - SEALED.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
00 72 00 - Standard General Conditions 2018.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 01 07 - Seal Page - Office Building.pdf PDF
00 63 36 - Field Order Form-R.pdf PDF
00 01 01 - LA Cover.pdf PDF
00 73 00 - Supplementary Conditions 2018.pdf PDF
00 63 13 - RFI Form.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 32 16 - Construction Progress Schedule.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 22 00 - Unit Prices.pdf PDF
01 42 00 - References.pdf PDF
00 63 63 - Change Order Form.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 77 00 - CLOSEOUT PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 77 00 - 1 006566.0459

SECTION 01 77 00 - CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Closeout procedures.

B. Testing, adjusting, and balancing.

C. Final cleaning.

1.2 SUBMITTALS

A. Product Data: For cleaning agents.

B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.

C. Closeout Submittals:

1. Certificates of Release: From authorities having jurisdiction.

2. Certificate of Insurance: For continuing coverage.

3. Submittals as required by various specification sections.

1.3 CLOSEOUT PROCEDURES

A. Prerequisites to Substantial Completion: Complete following items before requesting Certification of Substantial Completion, either for entire Work or for portions of Work:

1. Submit maintenance manuals, Project record documents and other similar final record data in compliance with this Section.

2. Complete facility startup, testing, adjusting, balancing of systems and equipment, demonstrations, and instructions to Owner's operating and maintenance personnel as specified in compliance with this Section.

3. Conduct inspection to establish basis for request that Work is substantially complete. Create comprehensive list (initial punch list) indicating items to be completed or corrected, value of incomplete or nonconforming Work, reason for being incomplete, and date of anticipated completion for each item. Include copy of list with request for Certificate of Substantial Completion.

4. Obtain and submit releases enabling Owner's full, unrestricted use of Project and access to services and utilities. Include certificate of occupancy, operating certificates, and similar releases from authorities having jurisdiction and utility companies.

5. Deliver tools, spare parts, extra stocks of material, and similar physical items to Owner.

6. Make final change-over of locks eliminating construction master-key system and transmit keys directly to Owner. Advise Owner's personnel of change-over in security provisions.

7. Discontinue or change over and remove temporary facilities and services from Project Site, along with construction tools, mockups, and similar elements.

Herbert, Rowland & Grubic, Inc. 01 77 00 - 2 006566.0459

8. Perform final cleaning according to this Section.

B. Substantial Completion Inspection:

1. When Contractor considers Work to be substantially complete, submit to

Engineer:

a. Written certificate that Work, or designated portion, is substantially complete.

b. List of items to be completed or corrected (initial punch list).

2. Upon receipt of request for Substantial Completion, Owner and Engineer will make inspection to determine whether Work or designated portion is substantially complete.

3. Should Engineer determine that Work is not substantially complete:

a. Engineer will promptly notify Contractor in writing, stating reasons for its opinion.

b. Contractor shall remedy deficiencies in Work and send second written request for Substantial Completion to Engineer.

c. Engineer will re-inspect Work.

d. Redo and Inspection of Deficient Work: Repeated until Work passes

Engineer's inspection.

4. When Engineer finds that Work is substantially complete, Engineer will:

a. Prepare Certificate of Substantial Completion on EJCDC C-625 - Certificate of Substantial Completion, accompanied by Contractor's list of items to be completed or corrected as verified and amended by Engineer and Owner (final punch list).

b. Submit preliminary Certificate to Owner for review.

c. Submit final Certificate to Owner and Contractor for their written acceptance of responsibilities assigned to them in Certificate.

5. After Work is substantially complete, Contractor shall:

a. Allow Owner occupancy of Project under provisions stated in Certificate of Substantial Completion.

b. Complete Work listed for completion or correction within time period stipulated.

C. Prerequisites for Final Completion: Complete following items before requesting final acceptance and final payment:

1. When Contractor considers Work to be complete, submit written certification that:

a. Contract Documents have been reviewed.

b. Work has been examined for compliance with Contract Documents.

c. Work has been completed according to Contract Documents.

d. Work is completed and ready for final inspection.

2. Submittals: Submit following:

a. Final punch list indicating all items have been completed or corrected.

b. Final payment request with final releases and supporting documentation not previously submitted and accepted. Include certificates of insurance for products and completed operations where required.

c. Specified warranties, workmanship/maintenance bonds, maintenance agreements, and other similar documents.

Herbert, Rowland & Grubic, Inc. 01 77 00 - 3 006566.0459

d. Accounting statement for final changes to Contract Sum.

e. Contractor's affidavit of payment of debts and claims on form in Section

00 65 19.16.

f. Contractor affidavit of release of liens on form in Section 00 65 19.16.

g. Consent of surety to final payment on form in Section 00 65 19.19.

3. Perform final cleaning for Contractor-soiled areas according to this Section.

D. Final Completion Inspection:

1. After receipt of request for final inspection, Engineer will make inspection to determine whether Work or designated portion is complete.

2. Should Engineer or Owner consider Work to be incomplete or defective:

a. Engineer will promptly notify Contractor in writing, listing incomplete or defective Work.

b. Contractor shall remedy stated deficiencies and send second written request to Engineer that Work is complete.

c. Engineer and Owner will re-inspect Work.

d. Redo and Inspection of Deficient Work: Repeated until Work passes

Engineer's and Owner's inspection. Contractor shall reimburse Owner for the costs of Engineer for re-inspections due to incomplete work.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION

3.1 FINAL CLEANING

A. Execute final cleaning prior to final Project assessment:

1. Employ experienced personnel or professional cleaning firm.

B. Clean interior and exterior glass and surfaces exposed to view; remove temporary labels, stains, and foreign substances; polish transparent and glossy surfaces; and vacuum carpeted and soft surfaces.

C. Clean equipment and fixtures to sanitary condition with appropriate cleaning materials.

D. Replace filters of operating equipment.

E. Clean debris from roofs, gutters, downspouts, and drainage systems.

F. Clean Site; sweep paved areas, rake clean landscaped surfaces.

G. Remove waste and surplus materials, rubbish, and construction facilities from Site.

END OF SECTION