This is a Submittal Procedures specification document for the Alterations for Penn Township Municipal Building project in Pennsylvania, establishing the requirements and processes that the contractor must follow when submitting materials, shop drawings, product data, samples, and other documentation to the engineer for review and approval. The submittal procedures outline two categories of submissions—action submittals requiring engineer responsive action and informational submittals for engineer knowledge—and mandate that all submittals be transmitted electronically via PDF email with proper identification, certification stamps, and sequential numbering. The contractor must submit a proposed product list within 15 days of the Notice to Proceed, and all shop drawings, product data, and samples require engineer approval before fabrication or construction work can proceed; the engineer will return submittals marked as "Approved," "Approved as Corrected," "Revise and Resubmit," or "Not Approved," with the contractor prohibited from proceeding on any work requiring submittal approval until receiving approved documentation.
The procedures prohibit "mass submittals" of six or more items in one day or 20 or more items in one week, with engineer review time extended as necessary and priority-based review determination. Submittals must include clear, readable information with no blurred or pixilated text, include 4-inch by 4-inch spaces for review stamps, and identify variations in contract documents or product limitations that may affect work performance. The contractor bears full responsibility for verifying material specifications, field measurements, dimensional accuracy, coordination with all trades, and compliance with contract documents before submission; the contractor must also review construction progress schedules per Section 01 32 16 and provide labeled, dated construction photographs on a thumb drive prior to construction start. Starting with the second resubmission, the owner may charge the contractor for engineer time and expenses at standard rates, with such charges offset from contractor payment.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 33 00 - SUBMITTAL PROCEDURES
Herbert, Rowland & Grubic, Inc. 01 33 00 - 1 006566.0459
SECTION 01 33 00 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Definitions.
B. Submittal procedures.
C. Construction progress schedules.
D. Proposed product and Subcontractor lists.
E. Product data.
F. Use of electronic CAD files of Project Drawings.
G. Shop Drawings.
H. Samples.
I. Other submittals.
J. Design data.
K. Test reports.
L. Certificates.
M. Manufacturer's instructions.
N. Manufacturer's field reports.
O. Erection Drawings.
P. Construction photographs.
Q. Contractor review.
R. Engineer review.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require Engineer's responsive action.
B. Informational Submittals: Written and graphic information and physical Samples that do not require Engineer's responsive action. Submittals may be rejected for not complying with requirements.
Herbert, Rowland & Grubic, Inc. 01 33 00 - 2 006566.0459
1.3 SUBMITTAL PROCEDURES
A. Transmit each submittal with Submittal Transmittal.
B. Sequentially number transmittal forms. Mark revised submittals with original number and sequential alphabetic suffix.
C. Identify: Project, Contractor, Subcontractor and supplier, pertinent Drawing and detail number, and Specification Section number appropriate to submittal:
1. Specification: Specification Number, Article Number (include the Paragraph
Letter if more than one item is included in the Article section) dash submittal number. Example: 03 30 00, 2.02-01 (1st submittal).
2. Plan Sheet: Plan and Sheet Number dash submittal number.
3. Mark revised resubmittals with original number and sequential alphabetic suffix.
D. Apply Contractor's stamp, signed or initialed, certifying that review, approval, verification of products required, field dimensions, adjacent construction Work, and coordination of information is according to requirements of the Work and Contract Documents.
Submittals not containing an executed certification stamp shall be returned.
E. Submit electronic submittals via email as PDF electronic files. Coordinate submission of related items:
1. Email submittals shall have the Contract Name, Contract Number, “Shop
Drawing,” and Submittal Identification Number in the subject line.
2. Contractor shall note (on the PDF submittal) that the Contractor has reviewed the submittal and confirms the submittal complies with the Contract documents.
3. Engineer will review Submittal as received. PDF Submittal will be returned to
Contractor with comment(s) and Action using the same method as submitted.
4. PDF electronic files: Where documents are scanned, all text shall be clearly readable and no information blurred/pixilated. Any non-readable text, blurred/pixilated information on a submittal will cause it to be rejected.
F. For each submittal for review, allow reasonable time for Engineer.
G. Identify variations in Contract Documents and product or system limitations that may be detrimental to successful performance of completed Work.
H. Allow 4”x4” space on submittals for Contractor and Engineer review stamps.
I. When revised for resubmission, identify changes made since previous submission.
J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report inability to comply with requirements.
K. Submittals not requested will not be recognized nor processed.
L. Incomplete Submittals: Engineer will not review. Complete submittals for each item are required. Delays resulting from incomplete submittals are not the responsibility of Engineer.
Herbert, Rowland & Grubic, Inc. 01 33 00 - 3 006566.0459
1.4 CONSTRUCTION PROGRESS SCHEDULES
A. Comply with Section 01 32 16 - Construction Progress Schedule.
1.5 PROPOSED PRODUCT LIST
A. Within 15 days after date of Notice to Proceed, submit list of major products proposed for use, with name of manufacturer, trade name, and model number of each product.
B. For products specified only by reference standards, indicate manufacturer, trade name, model or catalog designation, and reference standards.
1.6 PRODUCT DATA
A. Product Data: Action Submittal: Submit to Engineer for review for assessing conformance with information given and design concept expressed in Contract Documents.
B. Submit electronic submittals via email as PDF electronic files.
C. Mark each copy to identify applicable products, models, options, and other data.
Supplement manufacturers' standard data to provide information specific to this Project.
D. Indicate product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
E. After review, produce copies and distribute according to "Submittal Procedures" Article and for record documents described in Section 01 73 00 - Execution Requirements.
1.7 ELECTRONIC CAD FILES OF PROJECT DRAWINGS
A. N/A.
1.8 SHOP DRAWINGS
A. Shop Drawings: Action Submittal: Submit to Engineer for assessing conformance with information given and design concept expressed in Contract Documents.
B. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
C. When required by individual Specification Sections, provide Shop Drawings signed and sealed by a professional Engineer responsible for designing components shown on Shop Drawings.
1. Include signed and sealed calculations to support design.
2. Submit Shop Drawings and calculations in form suitable for submission to and approval by authorities having jurisdiction.
3. Make revisions and provide additional information when required by authorities having jurisdiction.
Herbert, Rowland & Grubic, Inc. 01 33 00 - 4 006566.0459
D. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information:
1. Dimensions.
2. Identification of products.
3. Fabrication and installation drawings.
4. Roughing-in and setting diagrams.
5. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
6. Shopwork manufacturing instructions.
7. Templates and patterns.
8. Schedules.
9. Compliance with specified standards.
10. Notation of coordination requirements.
11. Notation of dimensions established by field measurement.
12. Relationship to adjoining construction clearly indicated.
13. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
E. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 40 inches.
F. Submit electronic submittals via email as PDF electronic files.
G. After review, produce copies and distribute according to "Submittal Procedures" Article and for record documents described in Section 01 77 00 - Closeout Procedures.
1.9 SAMPLES
A. Samples: Action Submittal: Submit to Engineer for assessing conformance with information given and design concept expressed in Contract Documents.
B. Samples for Selection as Specified in Product Sections:
1. Submit to Engineer for aesthetic, color, and finish selection.
2. Submit Samples of finishes, textures, and patterns for Engineer selection.
C. Submit Samples to illustrate functional and aesthetic characteristics of products, with integral parts and attachment devices. Coordinate Sample submittals for interfacing work.
D. Include identification on each Sample, with full Project information.
E. Submit number of Samples specified in individual Specification Sections; Engineer will retain one Sample.
F. Reviewed Samples that may be used in the Work are indicated in individual Specification Sections.
G. Samples will not be used for testing purposes unless specifically stated in Specification Section.
Herbert, Rowland & Grubic, Inc. 01 33 00 - 5 006566.0459
H. After review, produce copies and distribute according to "Submittal Procedures" Article and for record documents described in Section 01 77 00 - Closeout Requirements.
1.10 OTHER SUBMITTALS
A. Closeout Submittals: Comply with Section 01 77 00 - Closeout Procedures.
B. Informational Submittal: Submit data for Engineer's knowledge as Contract administrator or for Owner.
C. Submit information for assessing conformance with information given and design concept expressed in Contract Documents.
1.11 TEST REPORTS
A. Informational Submittal: Submit reports for Engineer's knowledge as Contract administrator or for Owner.
B. Submit test reports for information for assessing conformance with information given and design concept expressed in Contract Documents.
1.12 CERTIFICATES
A. Informational Submittal: Submit certification by manufacturer, installation/application Subcontractor, or Contractor to Engineer, in quantities specified for Product Data.
B. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
C. Certificates may be recent or previous test results on material or product but must be acceptable to Engineer.
1.13 MANUFACTURER'S INSTRUCTIONS
A. Informational Submittal: Submit manufacturer's installation instructions for Engineer's knowledge as Contract administrator or for Owner.
B. Submit printed instructions for delivery, storage, assembly, installation, startup, adjusting, and finishing, to Engineer in quantities specified for Product Data.
C. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.
1.14 MANUFACTURER'S FIELD REPORTS
A. Informational Submittal: Submit reports for Engineer's knowledge as Contract administrator or for Owner.
Herbert, Rowland & Grubic, Inc. 01 33 00 - 6 006566.0459
1.15 ERECTION DRAWINGS
A. N/A.
1.16 CONSTRUCTION PHOTOGRAPHS
A. Take photographs as evidence of existing Project conditions and provide to Engineer on a labeled and dated thumb drive, prior to the start of construction.
1.17 CONTRACTOR REVIEW
A. Review for compliance with Contract Documents and approve submittals before transmitting to Engineer.
B. Contractor: Responsible for:
1. Determination and verification of materials including manufacturer's catalog numbers.
2. Determination and verification of field measurements and field construction criteria.
3. Checking and coordinating information in submittal with requirements of Work and of Contract Documents.
4. Determination of accuracy and completeness of dimensions and quantities.
5. Confirmation and coordination of dimensions and field conditions at Site.
6. Construction means, techniques, sequences, and procedures.
7. Safety precautions.
8. Coordination and performance of Work of all trades.
C. Stamp, sign (or initial), and date each submittal to certify compliance with requirements of Contract Documents.
D. Do not fabricate products or begin Work for which submittals are required until approved submittals have been received from Engineer.
1.18 ENGINEER REVIEW
A. Do not make "mass submittals" to Engineer. "Mass submittals" are defined as six or more submittals or items in one day or 20 or more submittals or items in one week. If "mass submittals" are received, Engineer's review time will be extended as necessary to perform proper review. Engineer will review "mass submittals" based on priority determined by Engineer after consultation with Owner and Contractor.
B. Informational submittals and other similar data are for Engineer's information, do not require Engineer's responsive action, and will not be reviewed or returned with comment.
C. Submittals made by Contractor that are not required by Contract Documents may be returned without action.
D. Submittal approval does not authorize changes to Contract requirements unless accompanied by Change Order.
Herbert, Rowland & Grubic, Inc. 01 33 00 - 7 006566.0459
E. Engineer's Action: Where action and return is required, Engineer will provide timely review of each submittal in accordance with the accepted Schedule of Submittals:
1. Submittals returned with "APPROVED" action indicates that the information submitted was found to be in conformance with the design concept and in compliance with the requirements of the Contract Documents. Contractor may proceed with performance of the work covered by the submittal.
2. Submittals returned with "APPROVED AS CORRECTED" action indicates that the information submitted was found to be in conformance with the design concept and in compliance with the requirements of the Contract Documents, provided the noted clarifications or corrections are completed. Submission of a corrected submittal indicating the changes noted by Engineer is required as part of the Project Record Documents. Contractor may proceed with performance of the work covered by the corrected submittal.
3. Submittals returned with "REVISE AND RESUBMIT" action indicate that: (1) information submitted is at least partially not in conformance with the design concept, (2) information submitted is at least partially not in compliance with the requirements of the Contract Documents, (3) submittal is incomplete and does not include all items required by the individual specification Sections, or (4) certifications or computations required by the individual specification Sections have not been included in the submittal. Submittal will be returned to Contractor noting the reasons for noncompliance. Contractor shall not proceed with the performance of the work covered by submittal until corrected information is submitted and approved.
4. Submittals returned with "NOT APPROVED" action indicates that the Engineer interprets the information submitted to be not in conformance with the design concept or not in compliance with the Contract Documents. Performance of the work shall not proceed until submittal is revised, resubmitted and approved.
F. Owner may offset payment due to Contractor to cover additional costs beyond the first resubmission review. Starting with the second resubmission, Contractor may be charged, by Owner, for the time and expenses of Engineer at Engineer's standard rates. Such charge shall be offset from Contractor's payment.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION - Not Used.