01 31 19 - Project Meetings.pdf
PDF 211 KB Posted
- Solicitation number
- Not on record
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a project meetings document related to Penn Township's alterations to its Municipal Building in Pennsylvania. The project encompasses two separate contracts: Contract #1 covers general construction work including demolition, sitework, concrete, general alteration construction, exterior replacement finishes, storefront glass, replacement doors, and associated work; Contract #2 addresses electrical construction work including providing heating and lighting for the new vestibule, rear entry, and side entry, plus other associated work. Bids will be received online via the PennBid Program until 10:00 AM local time on September 3, 2026, with all bids publicly displayed immediately following the deadline. The Township Board of Supervisors will consider the Notice of Intent to Award at its September 14, 2026 meeting at the Township Office.
Bidding documents are available exclusively through the designated website at https://pennbid.bonfirehub.com/, where prospective bidders are urged to register as plan holders. All official notifications, addenda, and bidding documents will be provided only through this website, and neither the Owner nor Engineer will be responsible for documents obtained from other sources. The website will be updated periodically with addenda, lists of registered plan holders, reports, and other information relevant to bid submission.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 31 19 - PROJECT MEETINGS
Herbert, Rowland & Grubic, Inc. 01 31 19 - 1 006566.0459
SECTION 01 31 19 - PROJECT MEETINGS
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Preconstruction meeting.
B. Progress meetings.
C. Pre-installation meetings.
1.2 PRECONSTRUCTION MEETING
A. Engineer will schedule and preside over meeting prior to commencement of Work at the site.
B. Attendance Required: Engineer, Owner, and Contractor:
1. Contractor representation: person vested with the authority to make necessary decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules.
C. Agenda:
1. Engineer's Status During Construction.
2. Resident Project Representative (RPR).
3. Project Communication Procedures.
4. Contract Times.
5. Project Site: Access and Rights-of-Way.
6. Permits and Approvals.
7. Field Engineering.
8. Changes in the Work procedures.
9. Work Schedule.
10. Shop Drawings.
11. Substitutions.
12. Job Conference Schedule.
13. Payment Applications.
14. Temporary Utilities.
15. Emergency Phone Numbers.
16. Field Office Facilities.
17. Subcontractors.
18. Prevailing Wage and Payroll Certifications.
19. Insurances.
20. Steel Products Procurement Act Certifications.
21. Safety and OSHA.
22. Control of Work.
D. Engineer will record minutes and distribute copies to participants, with copies each to Contractor(s), Owner, and those affected by decisions made.
01 31 19 - PROJECT MEETINGS
Herbert, Rowland & Grubic, Inc. 01 31 19 - 2 006566.0459
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION – Not Used.
END OF SECTION