01 40 00 - Quality Requirements.pdf

PDF 229 KB Posted

Attached to
Alterations for Penn Township Municipal Building - Shop
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a Quality Requirements specification document for the Alterations for Penn Township Municipal Building project located in Pennsylvania. The document, prepared by Herbert, Rowland & Grubic, Inc., establishes minimum quality standards and control procedures that contractors must follow throughout the project. The specification covers two primary contracts: General Construction work including demolition, sitework, concrete, exterior finishes, and storefront glass replacement; and Electrical Construction work providing heating and lighting for new vestibules and entries. Bids for both contracts were due by 10:00 AM on September 3, 2026, via the PennBid online platform, with the Notice of Intent to Award to be considered by the Township Board of Supervisors at its September 14, 2026 meeting.

The Quality Requirements specification mandates that contractors employ qualified personnel, manufacturers, and fabricators with demonstrated experience and successful in-service performance records. All work must comply with specified standards, manufacturers' recommended tolerances, and applicable reference standards current as of the bid date. An independent testing agency authorized to operate in Pennsylvania must be retained to perform required testing and inspections, with full-time specialists maintaining calibrated equipment traceable to the National Bureau of Standards. Testing reports must be submitted to the Engineer, Contractor, and authorities having jurisdiction, and any retesting due to nonconformance will be charged to the Contractor through deductions from the Contract Sum. Manufacturers' field service representatives must be approved by the Engineer and submit qualifications at least 30 days in advance of required observations, with all observations and supplemental instructions documented and reported.

View the file

Other files

File Type Posted
00 01 10 - Table of Contents.pdf PDF
00 01 01 - LA Cover - need date.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
01 12 00 - Multiple Contract Summary.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
2026.07.14 - H9 - Penn Twp Office - Bid Set - SEALED.pdf PDF
00 55 00 - Notice to Proceed.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 62 76 - App for Payment.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
2026.07.14 - H9 - Penn Twp Shop - Bid Set - SEALED.pdf PDF
01 77 00 - Closeout Procedures-R.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
00 72 00 - Standard General Conditions 2018.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 01 07 - Seal Page - Office Building.pdf PDF
00 63 36 - Field Order Form-R.pdf PDF
00 01 01 - LA Cover.pdf PDF
00 73 00 - Supplementary Conditions 2018.pdf PDF
00 63 13 - RFI Form.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 32 16 - Construction Progress Schedule.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 22 00 - Unit Prices.pdf PDF
01 42 00 - References.pdf PDF
00 63 63 - Change Order Form.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 40 00 - QUALITY REQUIREMENTS

Herbert, Rowland & Grubic, Inc. 01 40 00 - 1 006566.0459

SECTION 01 40 00 - QUALITY REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Quality control.

B. Tolerances.

C. References.

D. Labeling.

E. Mockup requirements.

F. Testing and inspection services.

G. Manufacturers' field services.

1.2 QUALITY CONTROL

A. Monitor quality control over suppliers, manufacturers, products, services, Site conditions, and workmanship, to produce Work of specified quality.

B. Comply with specified standards as the minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

C. Perform Work using persons qualified to produce required and specified quality.

D. Products, materials, and equipment may be subject to observation by Engineer at place of manufacture or fabrication. Such observations shall not relieve Contractor of complying with requirements of Contract Documents.

E. Supervise performance of Work in such manner and by such means to ensure that Work, whether completed or in progress, will not be subjected to harmful, dangerous, damaging, or otherwise deleterious exposure during construction period.

1.3 QUALITY ASSURANCE

A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.

B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

Herbert, Rowland & Grubic, Inc. 01 40 00 - 2 006566.0459

C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

D. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar to those indicated for this Project in material, design, and extent.

E. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 548; and with additional qualifications specified in individual Sections; and where required by authorities having jurisdiction, that is acceptable to authorities:

1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.

2. NVLAP: A testing agency accredited according to NIST's National Voluntary

Laboratory Accreditation Program.

F. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

1.4 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work. Do not permit tolerances to accumulate.

B. Comply with manufacturers' recommended tolerances and tolerance requirements in reference standards. When such tolerances conflict with Contract Documents, request clarification from Engineer before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

1.5 REFERENCES

A. For products or workmanship specified by association, trade, or other consensus standards, comply with requirements of standard except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current as of date for receiving Bids except where specific date is established by code.

C. Obtain copies of standards and maintain on Site when required by product Specification Sections.

D. When requirements of indicated reference standards conflict with Contract Documents or where conflicting standards are specified, request clarification from Engineer before proceeding.

Herbert, Rowland & Grubic, Inc. 01 40 00 - 3 006566.0459

E. Neither contractual relationships, duties, or responsibilities of parties in Contract nor those of Engineer shall be altered from Contract Documents by mention or inference in reference documents.

1.6 LABELING

A. Attach label from agency approved by authorities having jurisdiction for products, assemblies, and systems required to be labeled.

B. Label Information: Include manufacturer's or fabricator's identification, approved agency identification, and the following information, as applicable, on each label:

1. Model number.

2. Serial number.

3. Performance characteristics.

C. Manufacturer's Nameplates, Trademarks, Logos, and Other Identifying Marks on Products: Not allowed on surfaces exposed to view in public areas, interior or exterior.

1.7 MOCK-UP REQUIREMENTS

A. Tests will be performed under provisions identified in this Section and identified in individual product Specification Sections.

B. Assemble and erect specified or indicated items with specified or indicated attachment and anchorage devices, flashings, seals, and finishes.

C. Accepted mockups shall be comparison standard for remaining Work.

D. Where mockup has been accepted by Engineer and is specified in product Specification Sections to be removed, remove mockup and clear area when directed to do so by Engineer.

1.8 TESTING AND INSPECTION SERVICES

A. Employ and pay for services of an independent testing agency or laboratory acceptable to Owner to perform specified testing:

1. Before starting Work, submit testing laboratory name, address, and telephone number, and names of full-time specialist and responsible officer.

2. Submit copy of report of laboratory facilities' inspection made by Materials

Reference Laboratory of National Bureau of Standards during most recent inspection, with memorandum of remedies of deficiencies reported by inspection.

B. Independent firm will perform tests, inspections, and other services specified in individual Specification Sections and as required by Owner:

1. Laboratory: Authorized to operate in State of Pennsylvania.

2. Laboratory Staff: Maintain full-time specialist on staff to review services.

3. Testing Equipment: Calibrated at reasonable intervals with devices of an accuracy traceable to National Bureau of Standards or accepted values of natural physical constants.

Herbert, Rowland & Grubic, Inc. 01 40 00 - 4 006566.0459

C. Testing, inspections, and source quality control may occur on or off Project Site. Perform off-Site testing as required by Engineer or Owner.

D. Reports shall be submitted by independent firm to Engineer, Contractor, and authorities having jurisdiction, in duplicate, indicating observations and results of tests and compliance or noncompliance with Contract Documents:

1. Submit final report indicating correction of Work previously reported as noncompliant.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access, and assistance by incidental labor as requested:

1. Notify Engineer and independent firm 48 hours before expected time for operations requiring services.

2. Make arrangements with independent firm and pay for additional Samples and tests required for Contractor's use.

F. Employment of testing agency or laboratory shall not relieve Contractor of obligation to perform Work according to requirements of Contract Documents.

G. Retesting or re-inspection required because of nonconformance with specified or indicated requirements shall be performed by same independent firm on instructions from Engineer. Payment for retesting or re-inspection will be charged to Contractor by deducting testing charges from Contract Sum/Price.

H. Agency Responsibilities:

1. Test Samples of mixes submitted by Contractor.

2. Provide qualified personnel at Site. Cooperate with Engineer and Contractor in performance of services.

3. Perform indicated sampling and testing of products according to specified standards.

4. Ascertain compliance of materials and mixes with requirements of Contract

Documents.

5. Promptly notify Engineer and Contractor of observed irregularities or nonconformance of Work or products.

6. Perform additional tests required by Engineer.

7. Attend preconstruction meetings and progress meetings.

I. Agency Reports: After each test, promptly submit one copy of report to Engineer, Contractor, and authorities having jurisdiction. When requested by Engineer, provide interpretation of test results. Include the following:

1. Date issued.

2. Project title and number.

3. Name of inspector.

4. Date and time of sampling or inspection.

5. Identification of product and Specification Section.

6. Location in Project.

7. Type of inspection or test.

8. Date of test.

9. Results of tests.

Herbert, Rowland & Grubic, Inc. 01 40 00 - 5 006566.0459

10. Conformance with Contract Documents.

J. Limits on Testing Authority:

1. Agency or laboratory may not release, revoke, alter, or enlarge on requirements of Contract Documents.

2. Agency or laboratory may not approve or accept any portion of the Work.

3. Agency or laboratory may not assume duties of Contractor.

4. Agency or laboratory has no authority to stop the Work.

1.9 MANUFACTURER'S FIELD SERVICES

A. When specified in individual Specification Sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe Site conditions, conditions of surfaces and installation, quality of workmanship, and testing as applicable, and to initiate instructions when necessary.

B. Submit qualifications of observer to Engineer 30 days in advance of required observations. Observer is subject to approval of Engineer.

C. Report observations and Site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturer's written instructions.

D. Refer to Section 01 33 00 - Submittal Procedures, "Manufacturer's Field Reports" Article.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION