This is a Construction Progress Schedule specification document prepared by Herbert, Rowland & Grubic, Inc. for the Alterations for Penn Township Municipal Building project in Pennsylvania. The specification establishes administrative and procedural requirements for the contractor to prepare, submit, and maintain a construction progress schedule using a horizontal bar chart (Gantt) format in Microsoft Project software. The contractor must submit a preliminary schedule within seven days of contract award covering all work from project start to completion, with monthly revisions required thereafter and additional updates whenever actual progress varies more than seven days from the proposed schedule. The schedule must identify the critical path, major work elements organized by specification section numbers, submittal dates for shop drawings and product data, delivery dates for owner-furnished materials, and accumulated completion percentages as of the first day of each month. The contractor is required to employ a Construction Scheduler with minimum five years of verifiable experience in projects of similar size and nature, who must attend all scheduling and progress meetings. Four copies of each revised schedule must be distributed to the engineer, owner, other contractors, subcontractors, suppliers, and concerned parties.
The specification requires the contractor to use the latest version of Microsoft Project software and comply with procedures contained in the AGC's "Construction Planning & Scheduling" standards. The schedule must include a separately identifiable activity on the critical path for foreseeable bad weather days based on normal anticipated weather conditions for the project location, with weather delays considered allowable but non-compensable. The contractor bears full responsibility for determining the appropriate number of weather delay days to include while meeting minimum requirements specified in the General Conditions or Supplementary Conditions. The document establishes the schedule as the primary tool for evaluating all time-related issues, identifying work paths critical to timely completion, analyzing time impacts of changes, and documenting actual construction progress and project history.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 32 16 – CONSTRUCTION PROGRESS SCHEDULE
Herbert, Rowland & Grubic, Inc. 01 32 16 - 1 006566.0459
SECTION 01 32 16 – CONSTRUCTION PROGRESS SCHEDULE
PART 1 – GENERAL
1.1. SECTION INCLUDES
A. This Section includes administrative and procedural requirements for the preparation, submittal, and maintenance of the progress schedule, reporting progress of the Work, and Contract Time adjustments, including the following:
1. Format.
2. Content.
3. Revisions to schedules.
4. Submittals.
5. Distribution.
B. Refer to the General Conditions and the Agreement for definitions and specific dates of Contract Time.
C. The Project schedules shall be used for evaluating all issues related to time for this
Contract. The Project schedules shall be updated in accordance with the requirements of this Section to reflect the actual progress of the Work and the Contractor’s current plan for the timely completion of the Work. The Project schedules shall be used by the Owner and Contractor for the following purposes as well as any other purpose where the issue of time is relevant:
1. To communicate to the Owner the Contractor’s current plan for carrying out the
Work.
2. To identify work paths that is critical to the timely completion of the Work.
3. To identify upcoming activities on the Critical Path(s).
4. To evaluate the best course of action for mitigating the impact of unforeseen events.
5. As the basis for analyzing the time impact of changes in the Work.
6. As a reference in determining the cost associated with increases or decreases in the Work.
7. To identify when submittals will be submitted.
8. To prioritize the review of submittals.
9. To document the actual progress of the Work.
10. To evaluate resource requirements of the Contractor and the Owner.
11. To integrate the Work with the operational requirements of the Owner’s facilities.
12. To facilitate efforts to complete the Work in a timely manner.
13. To document the history of the Work.
1.2. RELATED SECTIONS
A. Section 01 10 00 – Project Summary: Summary of Work.
Herbert, Rowland & Grubic, Inc. 01 32 16 - 2 006566.0459
B. Section 01 22 00 – Unit Prices.
C. Section 01 33 00 – Submittal Procedures.
D. Section 01 40 00 – Quality Requirements.
1.3. DEFINITIONS
A. Construction Schedule: A method of planning and scheduling a construction project utilizing a horizontal bar chart with a separate bar for each major portion of the Work or operation to make the schedule an effective tool for planning and monitoring the progress of the work.
B. Critical Path: The longest continuous chain of activities through the network at a given data date for the Schedule to a Contract Milestone or Contract Completion. Where the path to a specific Milestone has become negative, the Critical Path shall be the longest continuous chain of activities with the greatest amount of negative float.
C. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources:
1. Critical activities are activities on the critical path.
2. Predecessor activity is an activity that must be completed before a given activity can be started.
D. Event: An event is the starting or ending point of an activity.
E. Milestone: A key or critical point in time for reference or measurement.
1.4. QUALITY ASSURANCE
A. Construction Scheduler:
1. Contractor is required to employ or retain the services of an individual skilled in construction scheduling ("Construction Scheduler"). The Construction Scheduler shall have at least five (5) years of verifiable experience as the person primarily responsible for preparing and maintaining project schedules on projects of the same or similar size and nature as this project. The Construction Scheduler is required to attend meetings pertaining to scheduling and progress of the work including all progress meetings.
2. Should the Construction Scheduler leave the employ of the Contractor or be re-assigned or relieved of his/her responsibilities as the Construction Scheduler on the project, the Contractor shall submit the qualifications of the proposed replacement Construction Scheduler within 10 days after the date the former Construction Scheduler is no longer responsible for his/her duties on this Project.
Herbert, Rowland & Grubic, Inc. 01 32 16 - 3 006566.0459
B. Scheduling Software:
1. The Contractor shall use the latest version of Microsoft Project as the scheduling software system for use on this Project.
2. Standards: Comply with procedures contained in AGC's "Construction Planning & Scheduling."
1.5. PRELIMINARY SCHEDULE
A. Preliminary Gantt schedule is to be prepared by the General Contractor and submitted to the Engineer within seven (7) days of award of contract. This schedule is to cover all items of Work from the start of the project up to the completion of the project. This schedule must be revised when the actual schedule of significant items varies more than one week from the proposed schedule.
1.6. CONSTRUCTION SCHEDULE FORMAT
A. Format: Utilize a horizontal bar chart (Gantt) with a separate bar for each major portion of the Work or operation, identifying first work day of each week. NOTE: Insert a specific computer program and hardware configuration if Microsoft Project programs are unacceptable.
B. Program: Use Microsoft Project, latest version.
C. Sequence of Listings: Utilize the Table of Contents of this Project Manual and the chronological order of the start of each item of work.
D. Scale and Spacing: Provide space for notations and revisions.
E. Sheet Size: To be coordinated with Construction Administrator.
F. Foreseeable Bad Weather Days Allowance: The Contractor shall include a separate identifiable activity on the Critical Path labeled "Foreseeable Bad Weather Days:"
1. The Contractor shall be fully responsible for determining the number of weather delay days to be included in the Schedule. This determination shall be based on the normal anticipated weather for the project location and the nature of the project work. The Schedule shall be based on the Contractor’s determined weather delay allowance, but must meet the minimum shown in the General Conditions or Supplementary Conditions.
2. The Contractor shall insert an activity in the Schedule to reflect weather day occurrences when weather days are experienced. Identify this activity as a foreseeable weather delay.
3. The Contractor shall reduce duration of Foreseeable Bad Weather Days Allowance activity as weather delays are experienced and inserted into the schedule. Remaining days in Foreseeable Bad Weather Day Allowance at
Herbert, Rowland & Grubic, Inc. 01 32 16 - 4 006566.0459 completion of project is considered float. Weather delay, when justified, are considered allowable, and non-compensable.
1.7. CONTENT
A. Show complete sequence of construction by activity, with dates beginning and completion of each element of construction.
B. Identify each item by specification section numbers.
C. Identify work of separate phases and other logically grouped activities.
D. Show accumulated percentages of completion of each item, and total percentage of
Work completed, as of the first day of each month.
E. Provide separate schedule of submittal dates for shop drawings, product data, and samples, Owner/Agency furnished products and any products identified as under
Allowances, and dates reviewed submittals will be required from Engineer. Indicate decision dates for selection of finishes.
F. Indicate delivery dates for Owner/Agency furnished products and any products identified as under Allowances.
G. Indicate critical path with original baseline indicated.
1.8. SUBMITTALS AND REVISIONS TO SCHEDULES
A. An initial bar graph schedule is to be prepared by the General Contractor and submitted.
B. Indicate progress of each activity to date of submittal, and projected completion date of each activity.
C. Identify activities modified since previous submittal, major changes in scope, and other identifiable changes.
D. Provide narrative report to define problem areas, anticipated delays, and impact on
Schedule. Report corrective action taken, or proposed, and its effect.
E. Schedules must be revised monthly and when the actual schedule of significant items varies more than seven (7) days from the proposed schedule.
F. Submit revised Construction Schedules for each Application for Payment.
G. Submit four (4) copies of the Construction Schedule.
Herbert, Rowland & Grubic, Inc. 01 32 16 - 5 006566.0459
1.9. DISTRIBUTION
A. Distribute copies of the computer generated schedules to Engineer, Owner, other
Contractors, Subcontractors, suppliers, and other concerned parties.
B. Instruct recipients to promptly report, in writing, problem anticipated by projections indicated in schedules.
PART 2 - PRODUCTS - Not Used.
PART 3 – EXECUTION – Not Used.
END OF SECTION