01 26 00 - Contract Modifications.pdf

PDF 217 KB Posted

Attached to
Alterations for Penn Township Municipal Building - Shop
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a Contract Modification Procedures document from Herbert, Rowland & Grubic, Inc. applicable to the Penn Township Municipal Building Alterations project in Pennsylvania. The document establishes standardized procedures for managing changes to the contract throughout the construction process. The modification framework includes four primary change mechanisms: minor changes issued via Field Order without price or time adjustments, Proposal Requests initiated by the Owner's Engineer with five working days for contractor estimates, contractor-proposed changes with full documentation and scheduling updates, and Work Change Directives signed by the Owner authorizing work to proceed pending subsequent Change Order execution. All changes require detailed documentation including quantities, unit costs, applicable taxes, delivery charges, equipment rental, labor and equipment costs directly attributable to the change, and updated Construction Schedules reflecting project impacts. The document mandates that contractors designate an authorized individual to receive change documents and promptly notify relevant parties of modifications.

The procedures require contractors to submit comprehensive proposals within five working days of Proposal Requests, with Change Orders executed only upon Owner approval through the Engineer. Contractors must maintain detailed records of time and material costs for all change work to substantiate expenses. All modifications must be promptly recorded in Schedule of Values, Applications for Payment, Progress Schedules, and Record Documents. The document references related sections including Requests for Interpretation procedures, Work Change Directive Forms, and Change Order Forms, establishing a formal change management system designed to control scope creep, document cost impacts, and maintain accurate project scheduling throughout the construction of the Penn Township Municipal Building alterations project, which includes General Construction and Electrical Construction contracts with bids due September 3, 2026.

View the file

Other files

File Type Posted
00 01 10 - Table of Contents.pdf PDF
00 01 01 - LA Cover - need date.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
01 12 00 - Multiple Contract Summary.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
2026.07.14 - H9 - Penn Twp Office - Bid Set - SEALED.pdf PDF
00 55 00 - Notice to Proceed.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 62 76 - App for Payment.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
2026.07.14 - H9 - Penn Twp Shop - Bid Set - SEALED.pdf PDF
01 77 00 - Closeout Procedures-R.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
00 72 00 - Standard General Conditions 2018.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 01 07 - Seal Page - Office Building.pdf PDF
00 63 36 - Field Order Form-R.pdf PDF
00 01 01 - LA Cover.pdf PDF
00 73 00 - Supplementary Conditions 2018.pdf PDF
00 63 13 - RFI Form.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 32 16 - Construction Progress Schedule.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 22 00 - Unit Prices.pdf PDF
01 42 00 - References.pdf PDF
00 63 63 - Change Order Form.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 26 00 – CONTRACT MODIFICATION PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 26 00 - 1 006566.0459

SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes :

1. Change procedures.

B. Related Sections:

1. Document 00 60 00 - Project Forms.

2. Document 00 63 13 - RFI Form.

3. Document 00 63 49 - Work Change Directive Form.

4. Document 00 63 63 - Change Order Form.

5. Section 01 26 13 - Requests for Interpretation.

1.2 CHANGE PROCEDURES

A. Submittals: Submit name of individual who is authorized to receive change documents and is responsible for informing others in Contractor's employ or Subcontractors of changes to the Work.

B. Carefully study and compare Contract Documents before proceeding with fabrication and installation of Work. Promptly advise Engineer of any error, inconsistency, omission, or apparent discrepancy.

C. Requests for Interpretation (RFI) and Clarifications: Allot time in construction scheduling for liaison with Engineer; establish procedures for handling queries and clarifications:

1. Refer to Section 01 26 13 - Requests for Interpretation.

2. Engineer may respond with a direct answer on the Requests for Interpretation form, Field Order, or Proposal Request.

1.3 MINOR CHANGES IN THE WORK

A. Engineer will advise of minor changes in the Work not involving adjustment to Contract Price or Contract Time by issuing supplemental instructions on Field Order.

1.4 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Engineer may issue Proposal Request including a detailed description of proposed change with supplementary or revised Drawings and Specifications with the period of time during which the requested price will be considered valid:

1. Proposal Requests issued by Engineer are not instructions either to stop work in progress or to execute the proposed change:

2. Contractor will prepare and submit estimate within 5 working days:

a. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.

Herbert, Rowland & Grubic, Inc. 01 26 00 - 2 006566.0459

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and equipment directly attributable to the change.

d. Include an updated Construction Schedule that indicates the effect of the change.

B. Contractor may propose changes by submitting a Change Proposal to Engineer, describing proposed change and its full effect on the Work. Include a statement describing reason for the change and the effect on Contract Price and Contract Time with full documentation and a statement describing effect on the Work by separate or other Contractors:

1. Notice: Comply with General Conditions where latent or changed conditions require modifications to the Contract.

2. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and equipment directly attributable to the change.

5. Include an updated Construction Schedule that indicates the effect of the change.

C. Document requested substitutions according to Section 01 25 00 - Substitution Procedures.

1.5 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Proposal Request, Engineer will issue a Change Order for execution by Owner and Contractor:

1. Change Order Forms: Document 00 63 63 - Change Order Form.

B. Stipulated Price Change Order: Based on Proposal Request and Contractor's price quotation or Contractor's request for Change Order as approved by Engineer.

C. Unit Price Change Order: For Contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of that which are not predetermined, execute Work under Work Directive Change.

D. Correlation of Contractor Submittals:

1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as separate line item and adjust Contract Price.

2. Promptly revise Progress Schedules to reflect change in Contract Time, adjust times for other items of Work affected by the change, and resubmit.

3. Promptly enter changes in Record Documents.

1.6 WORK CHANGE DIRECTIVE

A. Engineer may issue directive, on Work Change Directive signed by Owner, instructing Contractor to proceed with change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work and designate method of determining any change in Contract Price or Contract Time. Promptly execute change.

Herbert, Rowland & Grubic, Inc. 01 26 00 - 3 006566.0459

B. Maintain detailed records of Work done on time and material basis. Provide full information required for evaluation of proposed changes and to substantiate costs for changes in the Work.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION