01 26 13 - Requests for Interpretation.pdf

PDF 217 KB Posted

Attached to
Alterations for Penn Township Municipal Building - Shop
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a Requests for Interpretation (RFI) specification document for the Alterations for Penn Township Municipal Building project in Pennsylvania, establishing procedures for contractor requests for clarification on contract documents and engineer responses. The specification outlines that contractors must submit RFIs using the designated RFI Form (Document 00 63 13) through the Project Documentation Website or correspondence, with requests requiring detailed written statements identifying specific drawings by number and location or specifications by section number, page, and paragraph. RFIs must be submitted in consecutive numerical order with all attachments bearing the RFI number and chronological page numbering. The contractor is responsible for reviewing all contract documents before submitting an RFI and must ensure that subcontractor and supplier RFIs are reviewed and approved before submission to the engineer. For coordination issues, contractors must submit suggested solutions with drawings or sketches drawn to scale. RFIs cannot be used to request approval of submittals or substitutions, request changes with known additional costs, or request different work methods.

The engineer will respond to properly prepared RFIs directly on the RFI form or through a Request for Proposal, while improper or frivolous RFIs will be processed at the engineer's standard hourly rate with costs deducted from monies due to the contractor. Answers to RFIs do not constitute approval for extra work, and contractors believing a clarification results in additional cost or time must submit a Change Proposal before proceeding with work. The engineer will endeavor to respond to RFIs in a timely fashion, though requested response dates are not guaranteed if deemed too expeditious. Unanswered RFIs will be returned with a "Not Reviewed" notation, and the engineer may retain RFIs for discussion during regularly scheduled project meetings with responses included in meeting minutes.

View the file

Other files

File Type Posted
00 01 10 - Table of Contents.pdf PDF
00 01 01 - LA Cover - need date.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
01 12 00 - Multiple Contract Summary.pdf PDF
2026.07.14 - H9 - Penn Twp Office - Bid Set - SEALED.pdf PDF
00 55 00 - Notice to Proceed.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 62 76 - App for Payment.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
2026.07.14 - H9 - Penn Twp Shop - Bid Set - SEALED.pdf PDF
01 77 00 - Closeout Procedures-R.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
00 72 00 - Standard General Conditions 2018.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 01 07 - Seal Page - Office Building.pdf PDF
00 63 36 - Field Order Form-R.pdf PDF
00 01 01 - LA Cover.pdf PDF
00 73 00 - Supplementary Conditions 2018.pdf PDF
00 63 13 - RFI Form.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 32 16 - Construction Progress Schedule.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 22 00 - Unit Prices.pdf PDF
01 42 00 - References.pdf PDF
00 63 63 - Change Order Form.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 26 13 – REQUESTS FOR INTERPRETATION

Herbert, Rowland & Grubic, Inc. 01 26 13 - 1 006566.0459

SECTION 01 26 13 – REQUESTS FOR INTERPRETATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Requests For Interpretation.

B. Related Sections:

1. Document 00 60 00 – Project Forms.

2. Document 00 63 13 – RFI Form.

3. Section 01 26 00 – Contract Modification Procedures.

1.2 DEFINITIONS

A. Request For Information / Interpretation (RFI):

1. A properly prepared request for information / interpretation shall include a detailed written statement that indicates the specific Drawings or Specification in need of clarification and the nature of the clarification requested:

a. Drawings shall be identified by drawing number and location on the drawing sheet.

b. Specifications shall be identified by Section number, page and paragraph.

2. Requests for Information: Request made by Contractor concerning items not indicated on drawings or contained in Contract Documents that is required to properly perform the work.

B. Improper and Frivolous RFIs:

1. RFIs that are not properly prepared, or

2. RFIs that request information that is clearly shown on the Contract Documents.

1.3 CONTRACTOR'S REQUESTS FOR INFORMATION

A. Format: use form Document 00 63 13 – RFI Form:

1. Forms shall be completely filled in, and if prepared by hand, shall be fully legible after photocopying or scanning.

2. RFIs shall be submitted in numerical order with no breaks in the consecutive numbering.

3. Each page of attachments to RFIs shall bear the RFI number and shall be consecutively numbered in chronological order.

4. Submit RFI through Project Documentation Website or correspondence.

B. Contractor shall carefully study the Contract Documents to assure that the requested information is not available therein. RFIs which request information available in the Contract Documents will be deemed either "improper" or "frivolous":

1. Improper or Frivolous RFIs will be processed by the Engineer at the Engineer's standard hourly rate and Engineer will charge the Owner, and such costs will be deducted from monies still due the Contractor. The Contractor will be notified by the Engineer prior to the processing of improper RFIs.

Herbert, Rowland & Grubic, Inc. 01 26 13 - 2 006566.0459

C. When the Contractor is unable to determine from the Contract Documents, the material, process or system to be installed, the Engineer shall be requested to make a clarification of the indeterminate item.

D. RFIs shall be originated by the Contractor:

1. RFIs from subcontractors or suppliers shall be submitted through, reviewed by, and approved by the Contractor prior to submittal to the Engineer.

2. RFIs from subcontractors or material suppliers sent directly to the Engineer shall not be accepted and will be returned unanswered.

E. In cases where RFIs are issued to request clarification of coordination issues, the Contractor shall fully lay out a suggested solution using drawings or sketches drawn to scale and submit same with the RFI. RFIs which fail to include a suggested solution will be returned unanswered with a requirement that the Contractor submit a complete request.

F. RFIs shall not be used for the following purposes:

1. To request approval of submittals.

2. To request approval of substitutions.

3. To request changes which are known to entail additional cost or credit.

4. To request different methods of performing work.

G. Contractor shall allow a reasonable time for review and response time for RFIs:

1. The Engineer will endeavor to respond in a timely fashion to RFIs.

2. RFI shall state requested date/time for response, however, this requested date/time for response is not a guarantee that the RFI will be answered by that date/time if that date/time is too expeditious.

1.4 ENGINEER'S RESPONSE TO RFIs

A. Engineer will respond to RFIs on one of the following forms:

1. Properly prepared RFIs:

a. Response directly upon Request for Information / Interpretation form.

b. Request for Proposal.

2. Improper or Frivolous RFIs:

a. Notification of Processing Fee(s).

b. Unanswered RFIs will be returned with a notation: Not Reviewed.

3. Answers to properly prepared RFIs will be directly upon the RFI form as deemed appropriate by the Engineer.

B. Engineer may opt to retain RFIs for discussion during regularly scheduled project meetings for inclusion of responses in meeting minutes.

C. In the event the Contractor believes that a clarification by the Engineer results in additional cost or time, Contractor shall submit a Change Proposal and not proceed with the Work indicated by the RFI until a Change Order (or Work Change Directive) is prepared and approved. RFIs shall not justify a cost increase in the work or a change in the project schedule:

1. Answered RFIs shall not be construed as approval to perform extra work.

2. Unanswered RFIs will be returned with a stamp or notation: Not Reviewed.

Herbert, Rowland & Grubic, Inc. 01 26 13 - 3 006566.0459

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION