This document is a Temporary Facilities and Controls specification section prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 managed by Ephrata Borough Authority in Pennsylvania. The specification outlines comprehensive temporary construction requirements including utilities (electricity, lighting, heating, cooling, ventilation, water service, and sanitary facilities), construction facilities (vehicular access, parking, progress cleaning, and fire prevention), and temporary controls (barriers, security, water control, dust control, erosion and sediment control, pollution control, and temporary shelter). The contractor is responsible for providing and maintaining these facilities and controls throughout the construction period, with specific requirements for coordination with the Owner to ensure continuous facility operations. Key provisions include dust minimization through polyethylene curtains and daily debris removal, maintenance of utility water pressure inside the building at all times, and provision of temporary sanitary facilities at project mobilization. The specification also establishes unique requirements for temporary digested sludge dewatering facilities, mandating a minimum solids throughput of 250 gallons per minute at 1.5% solids for five days per week with minimum output of 15% solids, along with submittal of a Temporary Sludge Dewatering Plan for Owner review and acceptance.
The specification references applicable ASTM standards for fire and sound testing and requires compliance with the Borough Noise Ordinance and Pennsylvania Department of Environmental Protection pollution and environmental control requirements. The contractor must maintain security protocols including entry control logs for workers and visitors, implement comprehensive fire prevention measures including fire watches for hazardous operations, and ensure complete removal and restoration of all temporary facilities before final payment inspection. All costs associated with temporary facilities are included in the contractor's bid, including energy costs for temporary electricity, although the Owner will reimburse the actual cost of energy consumed. The specification emphasizes coordination with the Owner at all stages and prohibits use of existing building spaces except as necessary for work execution.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 50 00 - TEMPORARY FACILITIES AND CONTROLS
Herbert, Rowland & Grubic, Inc. 01 50 00 - 1 011139.0465
SECTION 01 50 00 - TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Temporary facilities under Construction Management Agreement.
B. Temporary Utilities:
1. Temporary electricity.
2. Temporary lighting for construction purposes.
3. Temporary heating.
4. Temporary cooling.
5. Temporary ventilation.
6. Temporary utility water service.
7. Temporary sanitary facilities.
C. Construction Facilities:
1. Vehicular access.
2. Parking.
3. Progress cleaning and waste removal.
4. Fire-prevention facilities.
D. Temporary Controls:
1. Barriers.
2. Security.
3. Water control.
4. Dust control.
5. Erosion and sediment control.
6. Pollution control.
7. Temporary shelter
E. Removal of utilities, facilities, and controls.
1.2 REFERENCES
A. ASTM International:
1. ASTM E 84 - Standard Test Method for Surface Burning Characteristics of Building
Materials.
2. ASTM E 90 - Standard Test Method for Laboratory Measurement of Airborne
Sound Transmission Loss of Building Partitions and Elements.
3. ASTM E 119 - Standard Test Methods for Fire Tests of Building Construction and
Materials.
1.3 CONTRACTOR USE OF PREMISES
A. Contractors use of the site shall at all times be coordinated with the Owner so as to ensure continuous operation.
Herbert, Rowland & Grubic, Inc. 01 50 00 - 2 011139.0465
B. Contractors shall not be provided space in any of the existing buildings, except as required, to accomplish the Work of the Contracts.
C. Contractor shall take all precautions to minimize dust, dirt, and debris while working in the areas indicated on the Contract Drawings. Provide polyethylene curtains or other barriers over opening between new work and existing work areas as required. Clean and remove debris daily before leaving work site.
1.4 TEMPORARY FACILITIES
A. Temporary Provisions Provided by Contractor:
1. Temporary barriers, barricades, covered walkways, fencing, exterior closures, and interior closures.
2. Temporary field offices.
3. Cleaning during construction.
4. Access roads and approaches.
5. Temporary sanitary facilities.
6. Temporary heating and ventilating after enclosure.
7. Temporary electrical service and distribution system for power and lighting.
8. Temporary telephone and internet service.
B. Each Contractor: Coordinate provisions with Engineer or Owner and provide the following items as necessary for execution of the Work including associated costs:
1. Construction aids.
2. Temporary fire protection, dust control, erosion and sediment control, water control, noise control, and other necessary temporary controls.
3. Temporary barriers, barricades, and similar devices as necessary for safety and protection of construction personnel and public.
4. On Owner’s approval, may provide temporary field office including electrical service and temporary telephone.
5. Temporary tree and plant protection.
6. Temporary heating before building enclosure.
7. Electrical service required.
8. Temporary provisions for protection of installed Work.
1.5 TEMPORARY ELECTRICITY
A. Owner will pay cost of energy used. Exercise measures to conserve energy. Use Owner's existing power service.
B. Complement existing power service capacity and characteristics as required for construction operations.
C. Provide power outlets with branch wiring and distribution boxes located as required for construction operations. Provide suitable, flexible power cords as required for portable construction tools and equipment.
D. Provide main service disconnect and overcurrent protection at convenient location and feeder switch at source distribution equipment.
Herbert, Rowland & Grubic, Inc. 01 50 00 - 3 011139.0465
E. Permanent convenience receptacles may be used during construction.
1.6 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES
A. Provide and maintain lighting for construction operations as necessary.
1.7 TEMPORARY HEATING
A. Existing heating systems may be used during construction. Contractor to provide additional heating as required while wall is removed. The NEC Classification of the space must be taken into account for temporary heat source selection.
1.8 TEMPORARY COOLING
A. Existing cooling systems may be used during construction (fans and louvers).
1.9 TEMPORARY VENTILATION
A. Ventilate enclosed areas to achieve curing of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.
1.10 TEMPORARY UTILITY WATER SERVICE
A. General Contractor shall be responsible for maintaining utility water pressure inside the building at all times during construction. Coordinate short term (less than 8 hours) isolations with Owner for proposed work on utility waterlines.
1.11 TEMPORARY SANITARY FACILITIES
A. Each Contractor shall provide and maintain required facilities and enclosures. Existing facility use is not permitted. Provide facilities at time of Project mobilization.
1.12 PARKING
A. Use of existing on-Site streets and driveways used for construction traffic is permitted.
Tracked vehicles are not allowed on paved areas.
B. Use of designated areas of existing parking facilities used by construction personnel is permitted. Coordinate location of parking with Owner such as not to impede operation.
C. Do not allow heavy vehicles or construction equipment in parking areas.
D. Maintenance:
1. Maintain traffic and parking areas in sound condition free of excavated material, construction equipment, products, mud, snow, ice, and the like.
2. Maintain existing paved areas used for construction; promptly repair breaks, potholes, low areas, standing water, and other deficiencies, to maintain paving and drainage in original condition.
E. Removal, Repair:
Herbert, Rowland & Grubic, Inc. 01 50 00 - 4 011139.0465
1. Repair existing facilities damaged by use, to original condition.
F. Mud from Site vehicles: Provide means of removing mud from vehicle wheels before entering streets.
1.13 PROGRESS CLEANING AND WASTE REMOVAL
A. Maintain areas free of waste materials, debris, and rubbish. Maintain Site in clean and orderly condition.
B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, before enclosing spaces.
C. Broom and vacuum clean interior areas before starting surface finishing, and continue cleaning to eliminate dust.
D. Collect and remove waste materials, debris, and rubbish from Site periodically and dispose of off-Site.
E. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.
1.14 FIRE-PREVENTION FACILITIES
A. Prohibit smoking within buildings under construction and demolition. Designate area on Site where smoking is permitted. Provide approved ashtrays in designated smoking areas.
B. Establish fire watch for cutting, welding, and other hazardous operations capable of starting fires. Maintain fire watch before, during, and after hazardous operations until threat of fire does not exist.
C. The NEC classification of the space must be taken into account at all times during construction.
D. Contractor is to reestablish sprinkler lines requiring relocation within one (1) day of proposed conveyor installation. Sprinkler lines shall be established prior to operation of conveyor system.
1.15 BARRIERS
A. Provide barriers to prevent unauthorized entry to construction areas to allow for Owner's use of Site, and to protect existing facilities and adjacent properties from damage from construction operations and demolition.
B. Tree and Plant Protection: Preserve and protect existing trees and plants designated to remain.
1.16 SECURITY
A. Security Program:
Herbert, Rowland & Grubic, Inc. 01 50 00 - 5 011139.0465
1. Protect Work on existing premises and Owner's operations from theft, vandalism, and unauthorized entry.
2. Initiate program in coordination with Owner's existing security system at Project mobilization.
3. Maintain program throughout construction period.
B. Entry Control:
1. Restrict entrance of persons and vehicles to Project Site and existing facilities.
2. Allow entrance only to authorized persons with proper identification.
3. Maintain log of workers and visitors and make available to Owner on request.
4. Owner will control entrance of persons and vehicles related to Owner's operations.
1.17 WATER CONTROL
A. Grade Site to drain. Maintain excavations free of water. Provide, operate, and maintain necessary pumping equipment.
B. Protect Site from puddles or running water.
1.18 DUST CONTROL
A. Execute Work by methods that minimize raising dust from construction operations.
B. Provide positive means to prevent airborne dust from dispersing into atmosphere and into Owner-occupied areas.
1.19 EROSION AND SEDIMENT CONTROL
A. Plan and execute construction by methods to control surface drainage from cuts and fills from borrow and waste disposal areas. Prevent erosion and sedimentation.
B. Minimize surface area of bare soil exposed at one time.
C. Provide temporary measures including berms, dikes, drains, and other devices to prevent water flow.
D. Construct fill and waste areas by selective placement to avoid erosive surface silts and clays.
E. Periodically inspect earthwork to detect evidence of erosion and sedimentation. Promptly apply corrective measures.
F. Comply with sediment and erosion control plan indicated on Drawings.
1.20 NOISE CONTROL
A. Contractor is required to comply with Borough Noise Ordinance.
Herbert, Rowland & Grubic, Inc. 01 50 00 - 6 011139.0465
1.21 PEST AND RODENT CONTROL
A. Provide methods, means, and facilities to prevent pests and insects from damaging the Work.
1.22 POLLUTION CONTROL
A. Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances and pollutants produced by construction operations.
B. Comply with pollution and environmental control requirements of PADEP.
1.23 TEMPORARY DIGESTED SLUDGE DEWATERING FACILITIES AND CONTROLS
A. General
1. The intention of solids processing during construction is described in Section 01
74 19.
B. Operational Requirements
1. Contractor shall maintain solids through the facility, at the highest percent solids possible, at all times. Contractor must maintain at minimum a solids throughput of 250 gpm at 1.5% solids 5 days per week (8 hour days) with a minimum solids output of 15% solids.
C. Environmental Protection
1. Provide secondary containment, spill prevention measures, and containment of process liquids associated with temporary sludge dewatering operations.
2. Collect and return centrate, wash water, and other process drainage flows to locations approved by Owner.
3. Conduct temporary dewatering operations in a manner that minimizes odors, aerosol generation, noise, and potential environmental impacts to plant personnel, neighboring properties, and receiving waters.
D. Submittals
1. Submit a Temporary Sludge Dewatering Plan for review prior to installation of temporary facilities, according to the requirements of Section 01 74 19.
2. Include:
a. Process description.
b. How the process will be coordinated with the Owner.
c. Provide a detailed day-to-day schedule of how centrifuge room conveyors will be installed while maintaining flow.
3. Do not place temporary dewatering facilities into service until the Temporary
Digested Sludge Dewatering Plan has been reviewed by Engineer and accepted by Owner.
4. Demonstrate reliable operation of any temporary system prior to taking existing systems out of service.
Herbert, Rowland & Grubic, Inc. 01 50 00 - 7 011139.0465
1.24 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A. Remove temporary utilities, equipment, facilities, and materials before Final Application for Payment inspection.
B. Remove underground installations to minimum depth of 2 feet.
C. Clean and repair damage caused by installation or use of temporary Work.
D. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION - Not Used.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SECTION INCLUDES |
| A. Temporary facilities under Construction Management Agreement. |
| B. Temporary Utilities: |
| 1. Temporary electricity. |
| 2. Temporary lighting for construction purposes. |
| 3. Temporary heating. |
| 4. Temporary cooling. |
| 5. Temporary ventilation. |
| 6. Temporary utility water service. |
| 7. Temporary sanitary facilities. |
| C. Construction Facilities: |
| 1. Vehicular access. |
| 2. Parking. |
| 3. Progress cleaning and waste removal. |
| 4. Fire-prevention facilities. |
| D. Temporary Controls: |
| 1. Barriers. |
| 2. Security. |
| 3. Water control. |
| 4. Dust control. |
| 5. Erosion and sediment control. |
| 6. Pollution control. |
| 7. Temporary shelter |
E. Removal of utilities, facilities, and controls.
| 1.2 REFERENCES |
| A. ASTM International: |
| 1. ASTM E 84 - Standard Test Method for Surface Burning Characteristics of Building Materials. |
| 2. ASTM E 90 - Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements. |
| 3. ASTM E 119 - Standard Test Methods for Fire Tests of Building Construction and Materials. |
| 1.3 CONTRACTOR USE OF PREMISES |
| A. Contractors use of the site shall at all times be coordinated with the Owner so as to ensure continuous operation. |
| B. Contractors shall not be provided space in any of the existing buildings, except as required, to accomplish the Work of the Contracts. |
| C. Contractor shall take all precautions to minimize dust, dirt, and debris while working in the areas indicated on the Contract Drawings. Provide polyethylene curtains or other barriers over opening between new work and existing work areas as requir... |
| 1.4 TEMPORARY FACILITIES |
| A. Temporary Provisions Provided by Contractor: |
| 1. Temporary barriers, barricades, covered walkways, fencing, exterior closures, and interior closures. |
| 2. Temporary field offices. |
| 3. Cleaning during construction. |
| 4. Access roads and approaches. |
| 5. Temporary sanitary facilities. |
| 6. Temporary heating and ventilating after enclosure. |
| 7. Temporary electrical service and distribution system for power and lighting. |
| 8. Temporary telephone and internet service. |
| B. Each Contractor: Coordinate provisions with Engineer or Owner and provide the following items as necessary for execution of the Work including associated costs: |
| 1. Construction aids. |
| 2. Temporary fire protection, dust control, erosion and sediment control, water control, noise control, and other necessary temporary controls. |
| 3. Temporary barriers, barricades, and similar devices as necessary for safety and protection of construction personnel and public. |
| 4. On Owner’s approval, may provide temporary field office including electrical service and temporary telephone. |
| 5. Temporary tree and plant protection. |
| 6. Temporary heating before building enclosure. |
| 7. Electrical service required. |
| 8. Temporary provisions for protection of installed Work. |
| 1.5 TEMPORARY ELECTRICITY |
| A. Owner will pay cost of energy used. Exercise measures to conserve energy. Use Owner's existing power service. |
| B. Complement existing power service capacity and characteristics as required for construction operations. |
| C. Provide power outlets with branch wiring and distribution boxes located as required for construction operations. Provide suitable, flexible power cords as required for portable construction tools and equipment. |
| D. Provide main service disconnect and overcurrent protection at convenient location and feeder switch at source distribution equipment. |
| E. Permanent convenience receptacles may be used during construction. |
| 1.6 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES |
| A. Provide and maintain lighting for construction operations as necessary. |
| 1.7 TEMPORARY HEATING |
| A. Existing heating systems may be used during construction. Contractor to provide additional heating as required while wall is removed. The NEC Classification of the space must be taken into account for temporary heat source selection. |
| 1.8 TEMPORARY COOLING |
| A. Existing cooling systems may be used during construction (fans and louvers). |
| 1.9 TEMPORARY VENTILATION |
| A. Ventilate enclosed areas to achieve curing of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases. |
| 1.10 TEMPORARY UTILITY WATER SERVICE |
| A. General Contractor shall be responsible for maintaining utility water pressure inside the building at all times during construction. Coordinate short term (less than 8 hours) isolations with Owner for proposed work on utility waterlines. |
| 1.11 TEMPORARY SANITARY FACILITIES |
| A. Each Contractor shall provide and maintain required facilities and enclosures. Existing facility use is not permitted. Provide facilities at time of Project mobilization. |
| 1.12 PARKING |
| A. Use of existing on-Site streets and driveways used for construction traffic is permitted. Tracked vehicles are not allowed on paved areas. |
| B. Use of designated areas of existing parking facilities used by construction personnel is permitted. Coordinate location of parking with Owner such as not to impede operation. |
| C. Do not allow heavy vehicles or construction equipment in parking areas. |
| D. Maintenance: |
| 1. Maintain traffic and parking areas in sound condition free of excavated material, construction equipment, products, mud, snow, ice, and the like. |
| 2. Maintain existing paved areas used for construction; promptly repair breaks, potholes, low areas, standing water, and other deficiencies, to maintain paving and drainage in original condition. |
| E. Removal, Repair: |
| 1. Repair existing facilities damaged by use, to original condition. |
F. Mud from Site vehicles: Provide means of removing mud from vehicle wheels before entering streets.
| 1.13 PROGRESS CLEANING AND WASTE REMOVAL |
| A. Maintain areas free of waste materials, debris, and rubbish. Maintain Site in clean and orderly condition. |
| B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, before enclosing spaces. |
| C. Broom and vacuum clean interior areas before starting surface finishing, and continue cleaning to eliminate dust. |
| D. Collect and remove waste materials, debris, and rubbish from Site periodically and dispose of off-Site. |
| E. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids. |
| 1.14 FIRE-PREVENTION FACILITIES |
| A. Prohibit smoking within buildings under construction and demolition. Designate area on Site where smoking is permitted. Provide approved ashtrays in designated smoking areas. |
| B. Establish fire watch for cutting, welding, and other hazardous operations capable of starting fires. Maintain fire watch before, during, and after hazardous operations until threat of fire does not exist. |
| C. The NEC classification of the space must be taken into account at all times during construction. |
| D. Contractor is to reestablish sprinkler lines requiring relocation within one (1) day of proposed conveyor installation. Sprinkler lines shall be established prior to operation of conveyor system. |
| 1.15 BARRIERS |
| A. Provide barriers to prevent unauthorized entry to construction areas to allow for Owner's use of Site, and to protect existing facilities and adjacent properties from damage from construction operations and demolition. |
| B. Tree and Plant Protection: Preserve and protect existing trees and plants designated to remain. |
| 1.16 SECURITY |
| A. Security Program: |
| 1. Protect Work on existing premises and Owner's operations from theft, vandalism, and unauthorized entry. |
| 2. Initiate program in coordination with Owner's existing security system at Project mobilization. |
| 3. Maintain program throughout construction period. |
| B. Entry Control: |
| 1. Restrict entrance of persons and vehicles to Project Site and existing facilities. |
| 2. Allow entrance only to authorized persons with proper identification. |
| 3. Maintain log of workers and visitors and make available to Owner on request. |
| 4. Owner will control entrance of persons and vehicles related to Owner's operations. |
| 1.17 WATER CONTROL |
| A. Grade Site to drain. Maintain excavations free of water. Provide, operate, and maintain necessary pumping equipment. |
| B. Protect Site from puddles or running water. |
| 1.18 DUST CONTROL |
| A. Execute Work by methods that minimize raising dust from construction operations. |
| B. Provide positive means to prevent airborne dust from dispersing into atmosphere and into Owner-occupied areas. |
| 1.19 EROSION AND SEDIMENT CONTROL |
| A. Plan and execute construction by methods to control surface drainage from cuts and fills from borrow and waste disposal areas. Prevent erosion and sedimentation. |
| B. Minimize surface area of bare soil exposed at one time. |
| C. Provide temporary measures including berms, dikes, drains, and other devices to prevent water flow. |
| D. Construct fill and waste areas by selective placement to avoid erosive surface silts and clays. |
| E. Periodically inspect earthwork to detect evidence of erosion and sedimentation. Promptly apply corrective measures. |
| F. Comply with sediment and erosion control plan indicated on Drawings. |
| 1.20 NOISE CONTROL |
| A. Contractor is required to comply with Borough Noise Ordinance. |
| 1.21 PEST AND RODENT CONTROL |
| A. Provide methods, means, and facilities to prevent pests and insects from damaging the Work. |
| 1.22 POLLUTION CONTROL |
| A. Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances and pollutants produced by construction operations. |
| B. Comply with pollution and environmental control requirements of PADEP. |
| 1.23 TEMPORARY DIGESTED SLUDGE DEWATERING FACILITIES AND CONTROLS |
| A. General |
| 1. The intention of solids processing during construction is described in Section 01 74 19. |
| B. Operational Requirements |
| 1. Contractor shall maintain solids through the facility, at the highest percent solids possible, at all times. Contractor must maintain at minimum a solids throughput of 250 gpm at 1.5% solids 5 days per week (8 hour days) with a minimum solids outpu... |
| C. Environmental Protection |
| 1. Provide secondary containment, spill prevention measures, and containment of process liquids associated with temporary sludge dewatering operations. |
| 2. Collect and return centrate, wash water, and other process drainage flows to locations approved by Owner. |
| 3. Conduct temporary dewatering operations in a manner that minimizes odors, aerosol generation, noise, and potential environmental impacts to plant personnel, neighboring properties, and receiving waters. |
| D. Submittals |
| 1. Submit a Temporary Sludge Dewatering Plan for review prior to installation of temporary facilities, according to the requirements of Section 01 74 19. |
| 2. Include: |
| a. Process description. |
| b. How the process will be coordinated with the Owner. |
| c. Provide a detailed day-to-day schedule of how centrifuge room conveyors will be installed while maintaining flow. |
| 3. Do not place temporary dewatering facilities into service until the Temporary Digested Sludge Dewatering Plan has been reviewed by Engineer and accepted by Owner. |
| 4. Demonstrate reliable operation of any temporary system prior to taking existing systems out of service. |
| 1.24 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS |
| A. Remove temporary utilities, equipment, facilities, and materials before Final Application for Payment inspection. |
| B. Remove underground installations to minimum depth of 2 feet. |
| C. Clean and repair damage caused by installation or use of temporary Work. |
| D. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition. |
| PART 2 - PRODUCTS - Not Used. |
| PART 3 - EXECUTION - Not Used. |
File details come from the government source that posted it. Updated .