01 32 26 - Construction Progress Reporting.pdf

PDF 223 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This is a Construction Progress Reporting specification document prepared for the Biosolids Project 011139.0465 by Ephrata Borough Authority in Pennsylvania. The document outlines the contractor's requirements to submit comprehensive documentation throughout the construction process, including daily construction reports (submitted monthly if requested by the Owner/Engineer), material location reports (submitted monthly if requested), field condition reports (submitted immediately upon discovery of differing site conditions), and special coordination memoranda. Daily construction reports must record 19 categories of information encompassing subcontractor and personnel lists, equipment inventory, material deliveries, weather conditions, accidents, meetings, work stoppages, change orders, work change directives, equipment tests, and completion milestones. Material location reports must provide cumulative listings of delivered and stored materials with delivery schedules for fabricated items stored off-site. Field condition reports require detailed descriptions of any discrepancies between actual field conditions and the Contract Documents, accompanied by recommendations for contract modifications. The reporting requirements emphasize coordination between the prime contractor, subcontractors, and separate contractors through the distribution of coordination memoranda to all parties involved.

The specification document does not contain pricing information, set-asides, funding amounts, or other financial terms. This document functions as a technical specification section establishing documentation and reporting protocols required during project execution. No contract award date, term length, or renewal options are specified in this particular section. The document is part of the broader bidding package for the Biosolids Project, which includes separate contracts for General Construction (EBA26-2) and Electrical Construction (EBA26-3), with bids due December 8, 2026, at 10:00 AM through PennBid.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 32 26 - CONSTRUCTION PROGRESS REPORTING

Herbert, Rowland & Grubic, Inc. 01 32 26 - 1 011139.0465

SECTION 01 32 26 - CONSTRUCTION PROGRESS REPORTING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes

1. Daily construction reports.

2. Material location reports.

3. Field condition reports.

4. Special reports.

B. Related Sections

1. Section 01 10 00 – Summary.

2. Section 01 40 00 – Quality Control.

1.2 SUBMITTALS

A. Daily Construction Reports: Submit at monthly intervals, if requested by Owner/Engineer.

B. Material Location Reports: Submit at monthly intervals, if requested by Owner/Engineer.

C. Field Condition Reports: Submit at time of discovery of differing conditions.

D. Special Reports: Submit at time of occurrence.

1.3 COORDINATION

A. Coordinate preparation and processing of reports with performance of construction activities and with reporting of separate contractors.

1.4 REPORTS

A. Daily Construction Reports: For the purposes of documentation prepare a daily construction report recording the following information concerning events at Project site:

1. List of subcontractors at Project site.

2. List of separate contractors at Project site.

3. Personnel at Project site by classification.

4. Equipment at Project site.

5. Material deliveries.

6. High and low temperatures and general weather conditions.

7. Accidents.

8. Meetings and significant decisions.

9. Stoppages, delays, shortages, and losses.

10. Meter readings and similar recordings.

11. Emergency procedures.

12. Orders and requests of authorities having jurisdiction.

13. Change Orders received and implemented.

01 32 26 - CONSTRUCTION PROGRESS REPORTING

Herbert, Rowland & Grubic, Inc. 01 32 26 - 2 011139.0465

14. Work Change Directives received and implemented.

15. Clarifications requested, received, and implemented.

16. Services connected and disconnected.

17. Equipment or system tests and startups.

18. Partial Completions and occupancies.

19. Substantial Completions authorized.

B. Material Location Reports: At monthly intervals, prepare and submit a comprehensive list of materials delivered to and stored at Project site. List shall be cumulative, showing materials previously reported plus items recently delivered. Include with list a statement of progress on and delivery dates for materials or items of equipment fabricated or stored away from Project site.

C. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.

1.5 SPECIAL REPORTS

A. Prepare Coordination Memoranda for distribution to each Contractor involved outlining special procedures required for coordination. Include such items as required notices, reports, and attendance at meetings. Provide copy to the Engineer.

B. Prepare similar memoranda for the Owner and separate contractors where coordination of their work is required. All such memoranda must be directed through the Engineer.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION – Not Used

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes
1. Daily construction reports.
2. Material location reports.
3. Field condition reports.
4. Special reports.
B. Related Sections
1. Section 01 10 00 – Summary.
2. Section 01 40 00 – Quality Control.
1.2 SUBMITTALS
A. Daily Construction Reports: Submit at monthly intervals, if requested by Owner/Engineer.
B. Material Location Reports: Submit at monthly intervals, if requested by Owner/Engineer.
C. Field Condition Reports: Submit at time of discovery of differing conditions.
D. Special Reports: Submit at time of occurrence.
1.3 COORDINATION
A. Coordinate preparation and processing of reports with performance of construction activities and with reporting of separate contractors.
1.4 REPORTS
A. Daily Construction Reports: For the purposes of documentation prepare a daily construction report recording the following information concerning events at Project site:
1. List of subcontractors at Project site.
2. List of separate contractors at Project site.
3. Personnel at Project site by classification.
4. Equipment at Project site.
5. Material deliveries.
6. High and low temperatures and general weather conditions.
7. Accidents.
8. Meetings and significant decisions.
9. Stoppages, delays, shortages, and losses.
10. Meter readings and similar recordings.
11. Emergency procedures.
12. Orders and requests of authorities having jurisdiction.
13. Change Orders received and implemented.
14. Work Change Directives received and implemented.
15. Clarifications requested, received, and implemented.
16. Services connected and disconnected.
17. Equipment or system tests and startups.
18. Partial Completions and occupancies.
19. Substantial Completions authorized.
B. Material Location Reports: At monthly intervals, prepare and submit a comprehensive list of materials delivered to and stored at Project site. List shall be cumulative, showing materials previously reported plus items recently delivered. Include...
C. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation. Include a detailed description of the differin...
1.5 SPECIAL REPORTS
A. Prepare Coordination Memoranda for distribution to each Contractor involved outlining special procedures required for coordination. Include such items as required notices, reports, and attendance at meetings. Provide copy to the Engineer.
B. Prepare similar memoranda for the Owner and separate contractors where coordination of their work is required. All such memoranda must be directed through the Engineer.
PART 2 - PRODUCTS - Not Used
PART 3 - EXECUTION – Not Used