Contract Modification Procedures
This document is a contract modification procedures specification prepared by Herbert, Rowland & Grubic, Inc. for the Biosolids Project 011139.0465 managed by Ephrata Borough Authority in Pennsylvania. The specification establishes the formal processes and requirements for implementing changes to the construction contract, including procedures for Requests for Interpretation (RFI), minor changes, proposal requests, change orders, and work change directives. The document requires contractors to submit the name of an authorized individual responsible for receiving change documents and to carefully review all contract documents before proceeding with fabrication and installation work. Any identified errors, inconsistencies, omissions, or discrepancies must be promptly reported to the Engineer. The project includes coordination and interconnection of two new biodryers, demolition and replacement of dewatered solids conveyor systems, wall demolition and replacement, indoor utility replacements, site piping replacement/relocation, a dumpster loading canopy, and electrical improvements. Bids are due December 8, 2026 at 10:00 AM, with a pre-bid open house scheduled for November 18, 2026 from 8:00 AM to 10:00 AM. Separate contracts are requested for General Construction (Contract No. EBA26-2) and Electrical Construction (Contract No. EBA26-3).
Contractors must submit detailed proposals within five days of receiving a Proposal Request and include quantities of products required or eliminated, unit costs, applicable taxes, delivery charges, equipment rental information, labor and equipment costs directly attributable to changes, and an updated construction schedule reflecting the change's effects. Change Orders require approval by the Owner and Engineer and can be executed on a stipulated price basis or unit price basis. Contractors must promptly revise the Schedule of Values, Applications for Payment, and Progress Schedules to reflect authorized changes and adjust the contract price and time accordingly. The specification permits the Engineer to issue Work Change Directives signed by the Owner, instructing the contractor to proceed with work on a time and material basis, with detailed records required for subsequent evaluation and cost substantiation. The document references related sections including RFI forms, Work Change Directive forms, and Change Order forms, as well as substitution procedures outlined in Section 01 25 00.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 26 00 – CONTRACT MODIFICATION PROCEDURES
Herbert, Rowland & Grubic, Inc. 01 26 00 - 1 011139.0465
SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes
1. Change procedures.
B. Related Sections
1. Document 00 60 00 - Project Forms.
2. Document 00 63 13 - RFI Form.
3. Document 00 63 49 - Work Change Directive Form.
4. Document 00 63 63 - Change Order Form.
5. Section 01 26 13 - Requests for Interpretation.
1.2 CHANGE PROCEDURES
A. Submittals: Submit name of individual who is authorized to receive change documents and is responsible for informing others in Contractor's employ or Subcontractors of changes to the Work.
B. Carefully study and compare Contract Documents before proceeding with fabrication and installation of Work. Promptly advise Engineer of any error, inconsistency, omission, or apparent discrepancy.
C. Requests for Interpretation (RFI) and Clarifications: Allot time in construction scheduling for liaison with Engineer; establish procedures for handling queries and clarifications.
1. Refer to Section 01 26 13 - Requests for Interpretation.
2. Engineer may respond with a direct answer on the Request for Interpretation form or Field Order.
1.3 MINOR CHANGES IN THE WORK
A. Engineer will advise of minor changes in the Work not involving adjustment to Contract Price or Contract Time by issuing supplemental instructions on Field Order.
1.4 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Engineer may issue Proposal Request including a detailed description of proposed change with supplementary or revised Drawings and Specifications.
1. Proposal Requests issued by Engineer are not instructions either to stop work in progress or to execute the proposed change.
2. Contractor will prepare and submit estimate within 5 days.
a. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.
Herbert, Rowland & Grubic, Inc. 01 26 00 - 2 011139.0465
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and equipment directly attributable to the change.
d. Include an updated Construction Schedule that indicates the effect of the change.
B. Contractor may propose changes by submitting a Change Proposal to Engineer, describing proposed change and its full effect on the Work. Include a statement describing reason for the change and the effect on Contract Price and Contract Time with full documentation and a statement describing effect on the Work by separate or other Contractors.
1. Notice: Comply with General Conditions where latent or changed conditions require modifications to the Contract.
2. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and equipment directly attributable to the change.
5. Include an updated Construction Schedule that indicates the effect of the change.
C. Document requested substitutions according to Section 01 25 00 - Substitution Procedures.
1.5 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Proposal Request, Engineer will issue a Change Order for execution by Owner and Contractor.
1. Change Order Forms: Document 00 63 63 - Change Order Form.
B. Stipulated Price Change Order: Based on Proposal Request and Contractor's price quotation or Contractor's request for Change Order as approved by Engineer.
C. Unit Price Change Order: For Contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of that which are not predetermined, execute Work under Work Directive Change.
D. Correlation of Contractor Submittals:
1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as separate line item and adjust Contract Price.
2. Promptly revise Progress Schedules to reflect change in Contract Time, adjust times for other items of Work affected by the change, and resubmit.
3. Promptly enter changes in Record Documents.
1.6 WORK CHANGE DIRECTIVE
A. Engineer may issue directive, on Work Change Directive signed by Owner, instructing Contractor to proceed with change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work and designate method of determining any change in Contract Price or Contract Time. Promptly execute change.
Herbert, Rowland & Grubic, Inc. 01 26 00 - 3 011139.0465
B. Maintain detailed records of Work done on time and material basis. Provide full information required for evaluation of proposed changes and to substantiate costs for changes in the Work.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION - Not Used.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes |
| 1. Change procedures. |
| B. Related Sections |
| 1. Document 00 60 00 - Project Forms. |
| 2. Document 00 63 13 - RFI Form. |
| 3. Document 00 63 49 - Work Change Directive Form. |
| 4. Document 00 63 63 - Change Order Form. |
| 5. Section 01 26 13 - Requests for Interpretation. |
| 1.2 CHANGE PROCEDURES |
| A. Submittals: Submit name of individual who is authorized to receive change documents and is responsible for informing others in Contractor's employ or Subcontractors of changes to the Work. |
| B. Carefully study and compare Contract Documents before proceeding with fabrication and installation of Work. Promptly advise Engineer of any error, inconsistency, omission, or apparent discrepancy. |
| C. Requests for Interpretation (RFI) and Clarifications: Allot time in construction scheduling for liaison with Engineer; establish procedures for handling queries and clarifications. |
| 1. Refer to Section 01 26 13 - Requests for Interpretation. |
| 2. Engineer may respond with a direct answer on the Request for Interpretation form or Field Order. |
| 1.3 MINOR CHANGES IN THE WORK |
| A. Engineer will advise of minor changes in the Work not involving adjustment to Contract Price or Contract Time by issuing supplemental instructions on Field Order. |
| 1.4 PROPOSAL REQUESTS |
| A. Owner-Initiated Proposal Requests: Engineer may issue Proposal Request including a detailed description of proposed change with supplementary or revised Drawings and Specifications. |
| 1. Proposal Requests issued by Engineer are not instructions either to stop work in progress or to execute the proposed change. |
| 2. Contractor will prepare and submit estimate within 5 days. |
| a. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. |
| b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. |
| c. Include costs of labor and equipment directly attributable to the change. |
| d. Include an updated Construction Schedule that indicates the effect of the change. |
| B. Contractor may propose changes by submitting a Change Proposal to Engineer, describing proposed change and its full effect on the Work. Include a statement describing reason for the change and the effect on Contract Price and Contract Time with ful... |
| 1. Notice: Comply with General Conditions where latent or changed conditions require modifications to the Contract. |
| 2. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. |
| 3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. |
| 4. Include costs of labor and equipment directly attributable to the change. |
| 5. Include an updated Construction Schedule that indicates the effect of the change. |
C. Document requested substitutions according to Section 01 25 00 - Substitution Procedures.
| 1.5 CHANGE ORDER PROCEDURES |
| A. On Owner's approval of a Proposal Request, Engineer will issue a Change Order for execution by Owner and Contractor. |
| 1. Change Order Forms: Document 00 63 63 - Change Order Form. |
| B. Stipulated Price Change Order: Based on Proposal Request and Contractor's price quotation or Contractor's request for Change Order as approved by Engineer. |
| C. Unit Price Change Order: For Contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of that which are not predetermined, execute Work under Work Directive Change. |
| D. Correlation of Contractor Submittals: |
| 1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as separate line item and adjust Contract Price. |
| 2. Promptly revise Progress Schedules to reflect change in Contract Time, adjust times for other items of Work affected by the change, and resubmit. |
| 3. Promptly enter changes in Record Documents. |
| 1.6 WORK CHANGE DIRECTIVE |
| A. Engineer may issue directive, on Work Change Directive signed by Owner, instructing Contractor to proceed with change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work and designate method of determ... |
| B. Maintain detailed records of Work done on time and material basis. Provide full information required for evaluation of proposed changes and to substantiate costs for changes in the Work. |
| PART 2 - PRODUCTS - Not Used. |
| PART 3 - EXECUTION - Not Used. |