Work Sequence Summary

This is a Work Sequence document for the Biosolids Project 011139.0465 prepared by Herbert, Rowland & Grubic, Inc. for Ephrata Borough Authority in Pennsylvania. The project encompasses coordination and installation of two owner-procured BioDryers, demolition and replacement of dewatered solids conveyor systems, select wall demolition and replacement, indoor utility replacements, site piping replacement and relocation, a dumpster loading canopy, and associated electrical improvements. The construction work is divided into separate general construction and electrical construction contracts (EBA26-2 and EBA26-3). Bidding documents are available through PennBid at https://pennbid.bonfirehub.com/, with bids due December 8, 2026, at 10:00 AM local time. A pre-bid open house is scheduled for November 18, 2026, from 8:00 AM to 10:00 AM to allow prospective bidders to view the facility.

The document outlines construction constraints and a detailed 21-step suggested work sequence that the Contractor must incorporate into their overall construction plan. Critical constraints include maintaining the plant's dewatering process throughout construction at 250 gallons per minute with 1.5% solids concentration for eight hours per day, Monday through Friday, with the Contractor responsible for providing bypass pumping and coordinating temporary dewatering facilities with the Engineer. The Contractor bears ultimate responsibility for sequencing and executing all work safely while meeting Substantial Completion and Final Completion milestones. The work sequence progresses from mobilization and erosion controls through equipment installation, conveyor modifications, and temporary dewatering coordination, culminating in electrical installation, equipment start-up and field testing, site improvements, final restoration, paving, and demobilization.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 12 16 – WORK SEQUENCE

Herbert, Rowland & Grubic, Inc. 01 12 16-1 011139.0465

SECTION 01 12 16 – WORK SEQUENCE

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Site Conditions.

2. Construction Constraints.

3. Suggested Construction Sequence.

B. Related Requirements:

1. Section 01 50 00 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.2 CONSTRUCTION CONSTRAINTS

A. The following is a list of constraints that the Contractor shall include in developing the overall plan of construction. This list is not intended to release the Contractor from the responsibility to coordinate the Work in any manner which will ensure Project completion within the Substantial Completion and Final Completion milestones.

1. The dewatering process of the plant shall be maintained at all times throughout construction, whether by maintaining a train of dewatering or hauling of solids.

See Section 01 74 19 for time constraints and responsibilities of the General Contractor. Contractor shall maintain the dewatering operation at 250 gpm at 1.5% solids for 8 hours per day Monday-Friday. Solids can be processed via the existing Centrifuges as identified elsewhere in the Contract Documents, or the Contractor shall, at his own expense, provide a temporary dewatering system.

2. General Contractor is responsible to provide bypass pumping as necessary to facilitate the Work. General Contractor shall also be responsible for planning to switch flows from existing dewatering facilities to temporary dewatering facilities.

3. General Contractor is responsible for coordinating temporary piping, bypass pumping and temporary dewatering facilities with the Engineer.

4. Delivery of Owner Procured equipment must be coordinated with those vendors as indicated in Section 01 64 00.SUGGESTED CONSTRUCTION SEQUENCE

A. The following areas are not necessarily listed in their required sequence of construction.

A suggested sequence within each area, where necessary, is included. This sequence is not intended to release the Contractor from the responsibility to coordinate all Work in a safe manner which will ensure the Substantial Completion and Final Completion milestones are met. The Contractor is ultimately responsible for the sequence and execution of the Work.

1. Mobilization.

2. Installation of erosion and sedimentation controls.

3. Temporary demolition of existing insulated metal wall panels to allow for delivery of BioDryers by-others. Coordinate with Owner’s rigging company as required for

01 12 16 – WORK SEQUENCE

Herbert, Rowland & Grubic, Inc. 01 12 16-2 011139.0465 work. Prep and install equipment pads and floor retrofits as required for installation of BioDryers.

4. Prep conduit and other utility connections for BioDryer installation.

5. Reassemble wall where BioDryers were brought in. During rigging, the wall is to be protected from the elements via plastic sheeting as required to keep wind and precipitation out.

6. Coordinate demolition timeline for pyrolysis unit and ancillary equipment with the Owner.

7. Install temporary piping for centrate pumping station. Replacement of centrate pumping station force main, plug valves, connections to existing pipes and structures.

8. Install stairs and platform onto biodryer catwalk.

9. Complete modifications of conveyors C-606 and C-607.

10. Erect proposed dumpster canopy, make bypass conveyor wall penetration, install bypass conveyor supports, install bypass conveyors C-605A and C-605B, test operation of bypass conveyor and prepare for solids.

11. Coordinate temporary dewatering plan with Owner for maintenance of solids during construction. See Section 01 74 19 for time constraint requirements.

12. Maintain solids through existing centrifuge #2 and conveyors C-602, C-604, and C-607. Transport solids through bypass conveyor for removal. Demolish one train of existing conveyors (C-601, C-603, and C-606), and install Contract Procured conveyors in that train. Retrofit and install conveyor supports.

13. Maintain solids through existing centrifuge #1 and through newly installed C-601, C-603 and C-606 into bypass conveyor. Demolish existing and install proposed conveyors C-602, C-604, and C-607.

14. Reconnect sprinkler system and proposed utility water wash lines into both trains of newly installed conveyors.

15. Demolish existing conveyors C-623 and C-625. Install proposed conveyor C-625.

The maximum downtime for this work is 14 calendar days.

16. Installation of remaining electrical components and controls.

17. Coordinate with Owner’s Integrator for all new equipment.

18. Start-up and field test all furnished equipment and electrical components, some field testing and start-up may take place during the process described above.

19. Completion of site improvements.

20. Final restoration and site paving.

21. Demobilization.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Site Conditions.
2. Construction Constraints.
3. Suggested Construction Sequence.
B. Related Requirements:
1. Section 01 50 00 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.2 CONSTRUCTION CONSTRAINTS
A. The following is a list of constraints that the Contractor shall include in developing the overall plan of construction. This list is not intended to release the Contractor from the responsibility to coordinate the Work in any manner which will ens...
1. The dewatering process of the plant shall be maintained at all times throughout construction, whether by maintaining a train of dewatering or hauling of solids. See Section 01 74 19 for time constraints and responsibilities of the General Contracto...
2. General Contractor is responsible to provide bypass pumping as necessary to facilitate the Work. General Contractor shall also be responsible for planning to switch flows from existing dewatering facilities to temporary dewatering facilities.
3. General Contractor is responsible for coordinating temporary piping, bypass pumping and temporary dewatering facilities with the Engineer.
4. Delivery of Owner Procured equipment must be coordinated with those vendors as indicated in Section 01 64 00.
1.3 SUGGESTED CONSTRUCTION SEQUENCE
A. The following areas are not necessarily listed in their required sequence of construction. A suggested sequence within each area, where necessary, is included. This sequence is not intended to release the Contractor from the responsibility to coord...
1. Mobilization.
2. Installation of erosion and sedimentation controls.
3. Temporary demolition of existing insulated metal wall panels to allow for delivery of BioDryers by-others. Coordinate with Owner’s rigging company as required for work. Prep and install equipment pads and floor retrofits as required for installatio...
4. Prep conduit and other utility connections for BioDryer installation.
5. Reassemble wall where BioDryers were brought in. During rigging, the wall is to be protected from the elements via plastic sheeting as required to keep wind and precipitation out.
6. Coordinate demolition timeline for pyrolysis unit and ancillary equipment with the Owner.
7. Install temporary piping for centrate pumping station. Replacement of centrate pumping station force main, plug valves, connections to existing pipes and structures.
8. Install stairs and platform onto biodryer catwalk.
9. Complete modifications of conveyors C-606 and C-607.
10. Erect proposed dumpster canopy, make bypass conveyor wall penetration, install bypass conveyor supports, install bypass conveyors C-605A and C-605B, test operation of bypass conveyor and prepare for solids.
11. Coordinate temporary dewatering plan with Owner for maintenance of solids during construction. See Section 01 74 19 for time constraint requirements.
12. Maintain solids through existing centrifuge #2 and conveyors C-602, C-604, and C-607. Transport solids through bypass conveyor for removal. Demolish one train of existing conveyors (C-601, C-603, and C-606), and install Contract Procured conveyors...
13. Maintain solids through existing centrifuge #1 and through newly installed C-601, C-603 and C-606 into bypass conveyor. Demolish existing and install proposed conveyors C-602, C-604, and C-607.
14. Reconnect sprinkler system and proposed utility water wash lines into both trains of newly installed conveyors.
15. Demolish existing conveyors C-623 and C-625. Install proposed conveyor C-625. The maximum downtime for this work is 14 calendar days.
16. Installation of remaining electrical components and controls.
17. Coordinate with Owner’s Integrator for all new equipment.
18. Start-up and field test all furnished equipment and electrical components, some field testing and start-up may take place during the process described above.
19. Completion of site improvements.
20. Final restoration and site paving.
21. Demobilization.