Work Sequence Summary
This is a Work Sequence document for the Biosolids Project 011139.0465 prepared by Herbert, Rowland & Grubic, Inc. for Ephrata Borough Authority in Pennsylvania. The project encompasses coordination and installation of two owner-procured BioDryers, demolition and replacement of dewatered solids conveyor systems, select wall demolition and replacement, indoor utility replacements, site piping replacement and relocation, a dumpster loading canopy, and associated electrical improvements. The construction work is divided into separate general construction and electrical construction contracts (EBA26-2 and EBA26-3). Bidding documents are available through PennBid at https://pennbid.bonfirehub.com/, with bids due December 8, 2026, at 10:00 AM local time. A pre-bid open house is scheduled for November 18, 2026, from 8:00 AM to 10:00 AM to allow prospective bidders to view the facility.
The document outlines construction constraints and a detailed 21-step suggested work sequence that the Contractor must incorporate into their overall construction plan. Critical constraints include maintaining the plant's dewatering process throughout construction at 250 gallons per minute with 1.5% solids concentration for eight hours per day, Monday through Friday, with the Contractor responsible for providing bypass pumping and coordinating temporary dewatering facilities with the Engineer. The Contractor bears ultimate responsibility for sequencing and executing all work safely while meeting Substantial Completion and Final Completion milestones. The work sequence progresses from mobilization and erosion controls through equipment installation, conveyor modifications, and temporary dewatering coordination, culminating in electrical installation, equipment start-up and field testing, site improvements, final restoration, paving, and demobilization.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 12 16 – WORK SEQUENCE
Herbert, Rowland & Grubic, Inc. 01 12 16-1 011139.0465
SECTION 01 12 16 – WORK SEQUENCE
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Site Conditions.
2. Construction Constraints.
3. Suggested Construction Sequence.
B. Related Requirements:
1. Section 01 50 00 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.2 CONSTRUCTION CONSTRAINTS
A. The following is a list of constraints that the Contractor shall include in developing the overall plan of construction. This list is not intended to release the Contractor from the responsibility to coordinate the Work in any manner which will ensure Project completion within the Substantial Completion and Final Completion milestones.
1. The dewatering process of the plant shall be maintained at all times throughout construction, whether by maintaining a train of dewatering or hauling of solids.
See Section 01 74 19 for time constraints and responsibilities of the General Contractor. Contractor shall maintain the dewatering operation at 250 gpm at 1.5% solids for 8 hours per day Monday-Friday. Solids can be processed via the existing Centrifuges as identified elsewhere in the Contract Documents, or the Contractor shall, at his own expense, provide a temporary dewatering system.
2. General Contractor is responsible to provide bypass pumping as necessary to facilitate the Work. General Contractor shall also be responsible for planning to switch flows from existing dewatering facilities to temporary dewatering facilities.
3. General Contractor is responsible for coordinating temporary piping, bypass pumping and temporary dewatering facilities with the Engineer.
4. Delivery of Owner Procured equipment must be coordinated with those vendors as indicated in Section 01 64 00.SUGGESTED CONSTRUCTION SEQUENCE
A. The following areas are not necessarily listed in their required sequence of construction.
A suggested sequence within each area, where necessary, is included. This sequence is not intended to release the Contractor from the responsibility to coordinate all Work in a safe manner which will ensure the Substantial Completion and Final Completion milestones are met. The Contractor is ultimately responsible for the sequence and execution of the Work.
1. Mobilization.
2. Installation of erosion and sedimentation controls.
3. Temporary demolition of existing insulated metal wall panels to allow for delivery of BioDryers by-others. Coordinate with Owner’s rigging company as required for
01 12 16 – WORK SEQUENCE
Herbert, Rowland & Grubic, Inc. 01 12 16-2 011139.0465 work. Prep and install equipment pads and floor retrofits as required for installation of BioDryers.
4. Prep conduit and other utility connections for BioDryer installation.
5. Reassemble wall where BioDryers were brought in. During rigging, the wall is to be protected from the elements via plastic sheeting as required to keep wind and precipitation out.
6. Coordinate demolition timeline for pyrolysis unit and ancillary equipment with the Owner.
7. Install temporary piping for centrate pumping station. Replacement of centrate pumping station force main, plug valves, connections to existing pipes and structures.
8. Install stairs and platform onto biodryer catwalk.
9. Complete modifications of conveyors C-606 and C-607.
10. Erect proposed dumpster canopy, make bypass conveyor wall penetration, install bypass conveyor supports, install bypass conveyors C-605A and C-605B, test operation of bypass conveyor and prepare for solids.
11. Coordinate temporary dewatering plan with Owner for maintenance of solids during construction. See Section 01 74 19 for time constraint requirements.
12. Maintain solids through existing centrifuge #2 and conveyors C-602, C-604, and C-607. Transport solids through bypass conveyor for removal. Demolish one train of existing conveyors (C-601, C-603, and C-606), and install Contract Procured conveyors in that train. Retrofit and install conveyor supports.
13. Maintain solids through existing centrifuge #1 and through newly installed C-601, C-603 and C-606 into bypass conveyor. Demolish existing and install proposed conveyors C-602, C-604, and C-607.
14. Reconnect sprinkler system and proposed utility water wash lines into both trains of newly installed conveyors.
15. Demolish existing conveyors C-623 and C-625. Install proposed conveyor C-625.
The maximum downtime for this work is 14 calendar days.
16. Installation of remaining electrical components and controls.
17. Coordinate with Owner’s Integrator for all new equipment.
18. Start-up and field test all furnished equipment and electrical components, some field testing and start-up may take place during the process described above.
19. Completion of site improvements.
20. Final restoration and site paving.
21. Demobilization.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION - Not Used.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes: |
| 1. Site Conditions. |
| 2. Construction Constraints. |
| 3. Suggested Construction Sequence. |
| B. Related Requirements: |
| 1. Section 01 50 00 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities. |
| 1.2 CONSTRUCTION CONSTRAINTS |
| A. The following is a list of constraints that the Contractor shall include in developing the overall plan of construction. This list is not intended to release the Contractor from the responsibility to coordinate the Work in any manner which will ens... |
| 1. The dewatering process of the plant shall be maintained at all times throughout construction, whether by maintaining a train of dewatering or hauling of solids. See Section 01 74 19 for time constraints and responsibilities of the General Contracto... |
| 2. General Contractor is responsible to provide bypass pumping as necessary to facilitate the Work. General Contractor shall also be responsible for planning to switch flows from existing dewatering facilities to temporary dewatering facilities. |
| 3. General Contractor is responsible for coordinating temporary piping, bypass pumping and temporary dewatering facilities with the Engineer. |
| 4. Delivery of Owner Procured equipment must be coordinated with those vendors as indicated in Section 01 64 00. |
| 1.3 SUGGESTED CONSTRUCTION SEQUENCE |
| A. The following areas are not necessarily listed in their required sequence of construction. A suggested sequence within each area, where necessary, is included. This sequence is not intended to release the Contractor from the responsibility to coord... |
| 1. Mobilization. |
| 2. Installation of erosion and sedimentation controls. |
| 3. Temporary demolition of existing insulated metal wall panels to allow for delivery of BioDryers by-others. Coordinate with Owner’s rigging company as required for work. Prep and install equipment pads and floor retrofits as required for installatio... |
| 4. Prep conduit and other utility connections for BioDryer installation. |
| 5. Reassemble wall where BioDryers were brought in. During rigging, the wall is to be protected from the elements via plastic sheeting as required to keep wind and precipitation out. |
| 6. Coordinate demolition timeline for pyrolysis unit and ancillary equipment with the Owner. |
| 7. Install temporary piping for centrate pumping station. Replacement of centrate pumping station force main, plug valves, connections to existing pipes and structures. |
| 8. Install stairs and platform onto biodryer catwalk. |
| 9. Complete modifications of conveyors C-606 and C-607. |
| 10. Erect proposed dumpster canopy, make bypass conveyor wall penetration, install bypass conveyor supports, install bypass conveyors C-605A and C-605B, test operation of bypass conveyor and prepare for solids. |
| 11. Coordinate temporary dewatering plan with Owner for maintenance of solids during construction. See Section 01 74 19 for time constraint requirements. |
| 12. Maintain solids through existing centrifuge #2 and conveyors C-602, C-604, and C-607. Transport solids through bypass conveyor for removal. Demolish one train of existing conveyors (C-601, C-603, and C-606), and install Contract Procured conveyors... |
| 13. Maintain solids through existing centrifuge #1 and through newly installed C-601, C-603 and C-606 into bypass conveyor. Demolish existing and install proposed conveyors C-602, C-604, and C-607. |
| 14. Reconnect sprinkler system and proposed utility water wash lines into both trains of newly installed conveyors. |
| 15. Demolish existing conveyors C-623 and C-625. Install proposed conveyor C-625. The maximum downtime for this work is 14 calendar days. |
| 16. Installation of remaining electrical components and controls. |
| 17. Coordinate with Owner’s Integrator for all new equipment. |
| 18. Start-up and field test all furnished equipment and electrical components, some field testing and start-up may take place during the process described above. |
| 19. Completion of site improvements. |
| 20. Final restoration and site paving. |
| 21. Demobilization. |
| PART 2 - PRODUCTS - Not Used. |
| PART 3 - EXECUTION - Not Used. |