01 12 00 - Multiple Contract Summary.pdf
PDF 268 KB Posted
- Attached to
- Biosolids Project 011139.0465
- Solicitation number
- US.260443
- Issued by
- Lancaster County, Pennsylvania
About this file
This Multiple Contract Summary document outlines the scope of work, responsibilities, and coordination requirements for the Biosolids Project 011139.0465 in Ephrata Borough, Pennsylvania, which involves two separate contracts: General Construction (EBA26-2) and Electrical Construction (EBA26-3). The project includes coordination and interconnection of two owner-procured BioDryers, demolition and replacement of dewatered solids conveyor systems, selective wall demolition and replacement, indoor utility replacements, site piping replacement/relocation, a dumpster loading canopy, and associated electrical improvements. A pre-bid open house is scheduled for November 18, 2026, from 8:00 AM to 10:00 AM, with bids due December 8, 2026, at 10:00 AM through PennBid. Bidding documents are available at https://pennbid.bonfirehub.com/, and prospective bidders are urged to register as plan holders on this designated website for all official notifications and addenda.
The General Construction Contract encompasses building permits, site preparation, earthwork, utility connections, concrete work for the outdoor canopy, demolition and selective restoration, interior finishes, process and control equipment installation, plumbing, fire protection, and closeout documentation including record drawings and operation and maintenance manuals. The Electrical Contract covers all work per E-Series drawings and Division 26 specifications, including conduit, conductors, communication wiring, control systems, and electrical connections for owner-procured BioDryers and conveyor systems. The General Contractor bears responsibility for temporary heating, cooling, ventilation, electric power service for all construction entities, temporary enclosures, dewatering facilities, sediment and erosion control, and overall project coordination including scheduling, quality assurance, and equipment start-up and testing. Each contractor is responsible for its own excavation, blocking, backing panels, access panels, equipment pads, and waste disposal, while painting and patching are the General Contractor's responsibility.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 12 00 - MULTIPLE CONTRACT SUMMARY
Herbert, Rowland & Grubic, Inc. 01 12 00 - 1 011139.0465
SECTION 01 12 00 - MULTIPLE CONTRACT SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Summary of each contract.
2. Responsibilities for coordination.
3. Responsibilities for temporary facilities.
4. Responsibilities for controls.
B. Related Requirements:
1. Section 01 10 00 - Project Summary: Work covered by the Contract Documents, restrictions on use of Project site, phased construction, coordination with occupants, and work restrictions.
2. Section 01 31 13 - Project Coordination: general coordination requirements.
1.2 SCOPE OF WORK
A. Extent of Contract:
1. Unless otherwise indicated, the work described in this Section for each contract shall be complete systems and assemblies, including products, components, accessories, and installation required by the Contract Documents.
2. Trenches and other excavation for the work of each contract shall be the work of each contract for its own work.
3. Each contract includes blocking, backing panels, sleeves, and metal fabrication supports for its own work.
4. Furnishing of access panels for the work of each contract shall be the work of each contract for its own work. Installation of access panels shall be the work of each contract for its own work.
5. Equipment pads for the work of each contract shall be the work of each contract for its own work.
6. Roof-mounted equipment curbs for the work of each contract shall be the work of each contract for its own work.
7. Painting for the work of each contract shall be the work of the General Contractor.
8. Cutting and Patching: Patching for the Work of each Contract shall be the work of the General Contractor.
B. Work in the General Construction Contract includes, but is not limited to, the following:
1. The Borough of Ephrata Building Permit, if required.
2. Remaining work not identified as work under other contracts.
3. Development and maintenance of the construction schedule, including all other contract’s work.
4. Pre and post site photographic documentation.
5. Site preparation, including earthwork as required.
6. Site improvements, including landscaping and asphalt restoration.
Herbert, Rowland & Grubic, Inc. 01 12 00 - 2 011139.0465
7. Utility connections of Owner procured and placed BioDryer units, Biodryer Feed Conveyors, BioDryer Discharge Conveyors, BioDryer odor control dampers and ducts, and other associated appurtenances shown on drawings.
8. Concrete, building, and material work for outdoor canopy.
9. Maintaining solids through the system during construction.
10. Selective demolition.
11. Below-grade building construction, including excavation, backfill, and thermal and moisture protection.
12. Exterior closure demolition and reinstallation (following BioDryer setting by
Owner), including walls, parapets, doors, windows, and louvers. Procurement of materials as necessary to facilitate in-kind replacement. Replacement in-kind of existing facilities during wall demolition, also temporary service of utilities required on the wall.
13. Interior finishes as disturbed.
14. Miscellaneous items, including patching, concrete equipment bases and painting of other Contractor’s work.
15. Coordination of conveyor startup, and startup of all equipment furnished through the Contract.
16. Fire protection specialties.
17. Furnish and install Process and Control Equipment except as otherwise noted in the Contract Documents.
18. Mounting of control panels and local control systems of Owner Procured
Equipment, or of materials procured under the General Contract.
19. Site water and utility water supply distribution, including temporary work during construction.
20. Site plumbing and drains.
21. Contract closeout information to include record drawings, operation and maintenance manuals, final testing, inspection certificates, guarantees, and warranties as per Division 01.
22. All other work not explicitly included by others will be the responsibility of the General Contractor.
C. Work in the Electrical Contract includes, but is not limited to, the following:
1. All work as described in the E-Series drawings, Division 26 of the Specifications, and electrical/communication connection work associated with the Owner Procured Bio Dryers and conveyor systems.
2. Site photographic documentation.
3. Coordination with General Contractor.
4. Site communications and control conduit, wiring, and equipment.
5. Selective electrical demolition.
6. Installation of Owner procured electrical equipment.
7. Electrical connections to equipment furnished by the General Contractor and
Owner.
8. Installation of all conduit, conductors, communication wires, control boxes, wiring to instruments and all other work as shown on drawings.
9. Contract closeout information to include record drawings, operation and maintenance manuals, final testing, inspection certificates, guarantees, and warranties as per Division 01.
Herbert, Rowland & Grubic, Inc. 01 12 00 - 3 011139.0465
1.3 TEMPORARY FACILITY RESPONSIBILITIES
A. Temporary Facilities and Controls: In addition to specific responsibilities for temporary facilities and controls indicated in this Section and in Section 01 50 00 "Temporary Facilities and Controls," each contractor is responsible for the following:
1. Installation, operation, maintenance, and removal of each temporary facility necessary for its own normal construction activity, and costs and use charges associated with each facility, except as otherwise provided for in this Section.
2. Plug-in electric power cords and extension cords, supplementary plug-in task lighting, and special lighting necessary exclusively for its own activities.
3. Its own field office, complete with necessary furniture, utilities, and telephone service.
4. Its own storage and fabrication sheds.
5. Temporary enclosures for its own construction activities.
6. Staging and scaffolding for its own construction activities.
7. General hoisting facilities for its own construction activities.
8. Waste disposal facilities, including collection and legal disposal of its own hazardous, dangerous, unsanitary, or other harmful waste materials.
9. Progress cleaning of work areas affected by its operations on a daily basis.
10. Secure lockup of its own tools, materials, and equipment.
11. Construction aids and miscellaneous services and facilities necessary exclusively for its own construction activities.
B. Temporary Heating, Cooling, and Ventilation: The General Contractor is responsible for temporary heating, cooling, and ventilation, including utility-use charges, temporary meters, and temporary connections.
C. Use Charges: Comply with the following:
1. Electric Power Service: Include the cost for electric power service, whether metered or otherwise, for electricity used by all entities engaged in construction activities at Project site in the General Contract.
D. Temporary facilities and controls in the General Contract include, but are not limited to, the following:
1. Temporary facilities and controls that are not otherwise specifically assigned to the other contractors.
2. Temporary wastewater process dewatering equipment for sludge treatment and disposal (if required)
3. Sediment and erosion control.
4. Unpiped temporary toilet fixtures, wash facilities, and drinking water facilities, including disposable supplies.
5. Temporary enclosure for building exterior, except as indicated.
6. Dewatering facilities and drains.
7. Excavation support and protection, unless required solely for the Work of another contract.
8. General waste disposal facilities.
9. Temporary stairs.
10. Temporary fire-protection facilities.
11. Covered walkways.
Herbert, Rowland & Grubic, Inc. 01 12 00 - 4 011139.0465
12. Security enclosure and lockup.
13. Environmental protection.
14. Restoration of Owner's existing facilities used as temporary facilities.
15. Temporary alarms for process control systems.
E. Temporary facilities and controls in the Electrical Contract include, but are not limited to, the following:
1. As necessary to complete work and provide complete systems as identified in these specifications and as shown on the Contract Drawings.
1.4 COORDINATION ACTIVITIES
A. Coordination activities of General Contractor include, but are not limited to, the following:
1. Provide overall coordination of the Work.
2. Coordinate shared access to workspaces.
3. Coordinate product selections for compatibility.
4. Provide overall coordination of temporary facilities and controls.
5. Coordinate, schedule, and approve interruptions of permanent and temporary utilities, including those necessary to make connections for temporary services.
6. Coordinate construction and operations of the Work with work performed by each Contract.
7. Prepare coordination drawings in collaboration with each contractor to coordinate work by more than one contract.
8. Coordinate sequencing and scheduling of the Work. Include the following:
a. Provide photographic documentation.
b. Provide quality assurance and quality-control services specified in Section
01 40 00 "Quality Requirements."
c. Coordinate sequence of activities to accommodate tests and inspections, and coordinate schedule of tests and inspections.
d. Provide information necessary to adjust, move, or relocate existing utility structures affected by construction.
e. Locate existing permanent benchmarks, control points, and similar reference points, and establish permanent benchmarks on Project site.
f. Provide field surveys of in-progress construction and site work.
g. Provide progress cleaning of common areas and coordinate progress cleaning of areas or pieces of equipment where more than one contractor has worked.
h. Coordinate cutting and patching.
i. Coordinate protection of the Work.
j. Coordinate firestopping.
k. Coordinate completion of interrelated punch list items.
l. Coordinate preparation of Project record documents if information from more than one contractor is to be integrated with information from other contractors to form one combined record.
m. Print and submit record documents if installations by more than one contractor are indicated on the same Contract Drawing or shop drawing.
n. Collect record Specification Sections from contractors, collate Sections into numeric order, and submit complete set.
Herbert, Rowland & Grubic, Inc. 01 12 00 - 5 011139.0465
o. Coordinate preparation of operation and maintenance manuals if information from more than one contractor is to be integrated with information from other contractors to form one combined record.
p. Coordinate start-up and testing of equipment.
B. Initial Coordination Meeting: At earliest possible date, arrange and conduct a meeting with contractors for sequencing and coordinating the Work; negotiate reasonable adjustments to schedules.
C. Prepare a combined contractors' construction schedule for entire Project. Base schedule on preliminary construction schedule. Secure time commitments for performing critical construction activities from contractors. Show activities of each contract on a separate sheet. Prepare a simplified summary sheet indicating combined construction activities of contracts.
1. Submit schedules to Engineer for review and approval.
2. Provide quality assurance and quality-control services
3. Distribute copies of approved schedules to contractors.
4. Provide photographic documentation.
5. Provide quality-assurance and quality-control services specified in Section
01 40 00 "Quality Requirements."
6. Coordinate sequence of activities to accommodate tests and inspections, and coordinate schedule of tests and inspections.
7. Provide information necessary to adjust, move, or relocate existing utility structures affected by construction.
8. Coordinate work with Bioforcetech.
9. Locate existing permanent benchmarks, control points, and similar reference points, and establish permanent benchmarks on Project site.
10. Provide field surveys of in-progress construction and site work.
11. Provide progress cleaning of common areas and coordinate progress cleaning of areas or pieces of equipment where more than one contractor has worked.
12. Coordinate cutting and patching.
13. Coordinate protection of the Work.
14. Coordinate firestopping.
15. Coordinate completion of interrelated punch list items.
16. Coordinate preparation of Project record documents if information from more than one contractor is to be integrated with information from other contractors to form one combined record.
17. Print and submit record documents if installations by more than one contractor are indicated on the same Contract Drawing or shop drawing.
18. Collect record Specification Sections from contractors, collate Sections into numeric order, and submit complete set.
19. Coordinate preparation of operation and maintenance manuals if information from more than one contractor is to be integrated with information from other contractors to form one combined record.
20. Coordinate start-up and testing of equipment.
D. Electrical Contractors: Coordination activities include, but are not limited to, the following:
1. Schedule and sequence electrical activities.
Herbert, Rowland & Grubic, Inc. 01 12 00 - 6 011139.0465
2. Coordinate sharing access to workspaces.
3. Coordinate integration of work into limited spaces.
4. Coordinate protection of the work.
5. Coordinate cutting and patching for the work.
6. Prepare coordination drawings.
7. Coordinate tests and inspections for the work.
8. Coordinate temporary services and facilities.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION - Not Used.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes: |
| 1. Summary of each contract. |
| 2. Responsibilities for coordination. |
| 3. Responsibilities for temporary facilities. |
| 4. Responsibilities for controls. |
| B. Related Requirements: |
| 1. Section 01 10 00 - Project Summary: Work covered by the Contract Documents, restrictions on use of Project site, phased construction, coordination with occupants, and work restrictions. |
| 2. Section 01 31 13 - Project Coordination: general coordination requirements. |
| 1.2 SCOPE OF WORK |
| A. Extent of Contract: |
| 1. Unless otherwise indicated, the work described in this Section for each contract shall be complete systems and assemblies, including products, components, accessories, and installation required by the Contract Documents. |
| 2. Trenches and other excavation for the work of each contract shall be the work of each contract for its own work. |
| 3. Each contract includes blocking, backing panels, sleeves, and metal fabrication supports for its own work. |
| 4. Furnishing of access panels for the work of each contract shall be the work of each contract for its own work. Installation of access panels shall be the work of each contract for its own work. |
| 5. Equipment pads for the work of each contract shall be the work of each contract for its own work. |
| 6. Roof-mounted equipment curbs for the work of each contract shall be the work of each contract for its own work. |
| 7. Painting for the work of each contract shall be the work of the General Contractor. |
| 8. Cutting and Patching: Patching for the Work of each Contract shall be the work of the General Contractor. |
| B. Work in the General Construction Contract includes, but is not limited to, the following: |
| 1. The Borough of Ephrata Building Permit, if required. |
| 2. Remaining work not identified as work under other contracts. |
| 3. Development and maintenance of the construction schedule, including all other contract’s work. |
| 4. Pre and post site photographic documentation. |
| 5. Site preparation, including earthwork as required. |
| 6. Site improvements, including landscaping and asphalt restoration. |
| 7. Utility connections of Owner procured and placed BioDryer units, Biodryer Feed Conveyors, BioDryer Discharge Conveyors, BioDryer odor control dampers and ducts, and other associated appurtenances shown on drawings. |
| 8. Concrete, building, and material work for outdoor canopy. |
| 9. Maintaining solids through the system during construction. |
| 10. Selective demolition. |
| 11. Below-grade building construction, including excavation, backfill, and thermal and moisture protection. |
| 12. Exterior closure demolition and reinstallation (following BioDryer setting by Owner), including walls, parapets, doors, windows, and louvers. Procurement of materials as necessary to facilitate in-kind replacement. Replacement in-kind of existing ... |
| 13. Interior finishes as disturbed. |
| 14. Miscellaneous items, including patching, concrete equipment bases and painting of other Contractor’s work. |
| 15. Coordination of conveyor startup, and startup of all equipment furnished through the Contract. |
| 16. Fire protection specialties. |
| 17. Furnish and install Process and Control Equipment except as otherwise noted in the Contract Documents. |
| 18. Mounting of control panels and local control systems of Owner Procured Equipment, or of materials procured under the General Contract. |
| 19. Site water and utility water supply distribution, including temporary work during construction. |
| 20. Site plumbing and drains. |
| 21. Contract closeout information to include record drawings, operation and maintenance manuals, final testing, inspection certificates, guarantees, and warranties as per Division 01. |
| 22. All other work not explicitly included by others will be the responsibility of the General Contractor. |
| C. Work in the Electrical Contract includes, but is not limited to, the following: |
| 1. All work as described in the E-Series drawings, Division 26 of the Specifications, and electrical/communication connection work associated with the Owner Procured Bio Dryers and conveyor systems. |
| 2. Site photographic documentation. |
| 3. Coordination with General Contractor. |
| 4. Site communications and control conduit, wiring, and equipment. |
| 5. Selective electrical demolition. |
| 6. Installation of Owner procured electrical equipment. |
| 7. Electrical connections to equipment furnished by the General Contractor and Owner. |
| 8. Installation of all conduit, conductors, communication wires, control boxes, wiring to instruments and all other work as shown on drawings. |
| 9. Contract closeout information to include record drawings, operation and maintenance manuals, final testing, inspection certificates, guarantees, and warranties as per Division 01. |
| 1.3 TEMPORARY FACILITY RESPONSIBILITIES |
| A. Temporary Facilities and Controls: In addition to specific responsibilities for temporary facilities and controls indicated in this Section and in Section 01 50 00 "Temporary Facilities and Controls," each contractor is responsible for the following: |
| 1. Installation, operation, maintenance, and removal of each temporary facility necessary for its own normal construction activity, and costs and use charges associated with each facility, except as otherwise provided for in this Section. |
| 2. Plug-in electric power cords and extension cords, supplementary plug-in task lighting, and special lighting necessary exclusively for its own activities. |
| 3. Its own field office, complete with necessary furniture, utilities, and telephone service. |
| 4. Its own storage and fabrication sheds. |
| 5. Temporary enclosures for its own construction activities. |
| 6. Staging and scaffolding for its own construction activities. |
| 7. General hoisting facilities for its own construction activities. |
| 8. Waste disposal facilities, including collection and legal disposal of its own hazardous, dangerous, unsanitary, or other harmful waste materials. |
| 9. Progress cleaning of work areas affected by its operations on a daily basis. |
| 10. Secure lockup of its own tools, materials, and equipment. |
| 11. Construction aids and miscellaneous services and facilities necessary exclusively for its own construction activities. |
| B. Temporary Heating, Cooling, and Ventilation: The General Contractor is responsible for temporary heating, cooling, and ventilation, including utility-use charges, temporary meters, and temporary connections. |
| C. Use Charges: Comply with the following: |
| 1. Electric Power Service: Include the cost for electric power service, whether metered or otherwise, for electricity used by all entities engaged in construction activities at Project site in the General Contract. |
| D. Temporary facilities and controls in the General Contract include, but are not limited to, the following: |
| 1. Temporary facilities and controls that are not otherwise specifically assigned to the other contractors. |
| 2. Temporary wastewater process dewatering equipment for sludge treatment and disposal (if required) |
| 3. Sediment and erosion control. |
| 4. Unpiped temporary toilet fixtures, wash facilities, and drinking water facilities, including disposable supplies. |
| 5. Temporary enclosure for building exterior, except as indicated. |
| 6. Dewatering facilities and drains. |
| 7. Excavation support and protection, unless required solely for the Work of another contract. |
| 8. General waste disposal facilities. |
| 9. Temporary stairs. |
| 10. Temporary fire-protection facilities. |
| 11. Covered walkways. |
| 12. Security enclosure and lockup. |
| 13. Environmental protection. |
| 14. Restoration of Owner's existing facilities used as temporary facilities. |
| 15. Temporary alarms for process control systems. |
| E. Temporary facilities and controls in the Electrical Contract include, but are not limited to, the following: |
| 1. As necessary to complete work and provide complete systems as identified in these specifications and as shown on the Contract Drawings. |
| 1.4 COORDINATION ACTIVITIES |
| A. Coordination activities of General Contractor include, but are not limited to, the following: |
| 1. Provide overall coordination of the Work. |
| 2. Coordinate shared access to workspaces. |
| 3. Coordinate product selections for compatibility. |
| 4. Provide overall coordination of temporary facilities and controls. |
| 5. Coordinate, schedule, and approve interruptions of permanent and temporary utilities, including those necessary to make connections for temporary services. |
| 6. Coordinate construction and operations of the Work with work performed by each Contract. |
| 7. Prepare coordination drawings in collaboration with each contractor to coordinate work by more than one contract. |
| 8. Coordinate sequencing and scheduling of the Work. Include the following: |
| a. Provide photographic documentation. |
| b. Provide quality assurance and quality-control services specified in Section 01 40 00 "Quality Requirements." |
| c. Coordinate sequence of activities to accommodate tests and inspections, and coordinate schedule of tests and inspections. |
| d. Provide information necessary to adjust, move, or relocate existing utility structures affected by construction. |
| e. Locate existing permanent benchmarks, control points, and similar reference points, and establish permanent benchmarks on Project site. |
| f. Provide field surveys of in-progress construction and site work. |
| g. Provide progress cleaning of common areas and coordinate progress cleaning of areas or pieces of equipment where more than one contractor has worked. |
| h. Coordinate cutting and patching. |
| i. Coordinate protection of the Work. |
| j. Coordinate firestopping. |
| k. Coordinate completion of interrelated punch list items. |
| l. Coordinate preparation of Project record documents if information from more than one contractor is to be integrated with information from other contractors to form one combined record. |
| m. Print and submit record documents if installations by more than one contractor are indicated on the same Contract Drawing or shop drawing. |
| n. Collect record Specification Sections from contractors, collate Sections into numeric order, and submit complete set. |
| o. Coordinate preparation of operation and maintenance manuals if information from more than one contractor is to be integrated with information from other contractors to form one combined record. |
| p. Coordinate start-up and testing of equipment. |
| B. Initial Coordination Meeting: At earliest possible date, arrange and conduct a meeting with contractors for sequencing and coordinating the Work; negotiate reasonable adjustments to schedules. |
| C. Prepare a combined contractors' construction schedule for entire Project. Base schedule on preliminary construction schedule. Secure time commitments for performing critical construction activities from contractors. Show activities of each contr... |
| 1. Submit schedules to Engineer for review and approval. |
| 2. Provide quality assurance and quality-control services |
| 3. Distribute copies of approved schedules to contractors. |
| 4. Provide photographic documentation. |
| 5. Provide quality-assurance and quality-control services specified in Section 01 40 00 "Quality Requirements." |
| 6. Coordinate sequence of activities to accommodate tests and inspections, and coordinate schedule of tests and inspections. |
| 7. Provide information necessary to adjust, move, or relocate existing utility structures affected by construction. |
| 8. Coordinate work with Bioforcetech. |
| 9. Locate existing permanent benchmarks, control points, and similar reference points, and establish permanent benchmarks on Project site. |
| 10. Provide field surveys of in-progress construction and site work. |
| 11. Provide progress cleaning of common areas and coordinate progress cleaning of areas or pieces of equipment where more than one contractor has worked. |
| 12. Coordinate cutting and patching. |
| 13. Coordinate protection of the Work. |
| 14. Coordinate firestopping. |
| 15. Coordinate completion of interrelated punch list items. |
| 16. Coordinate preparation of Project record documents if information from more than one contractor is to be integrated with information from other contractors to form one combined record. |
| 17. Print and submit record documents if installations by more than one contractor are indicated on the same Contract Drawing or shop drawing. |
| 18. Collect record Specification Sections from contractors, collate Sections into numeric order, and submit complete set. |
| 19. Coordinate preparation of operation and maintenance manuals if information from more than one contractor is to be integrated with information from other contractors to form one combined record. |
| 20. Coordinate start-up and testing of equipment. |
| D. Electrical Contractors: Coordination activities include, but are not limited to, the following: |
| 1. Schedule and sequence electrical activities. |
| 2. Coordinate sharing access to workspaces. |
| 3. Coordinate integration of work into limited spaces. |
| 4. Coordinate protection of the work. |
| 5. Coordinate cutting and patching for the work. |
| 6. Prepare coordination drawings. |
| 7. Coordinate tests and inspections for the work. |
| 8. Coordinate temporary services and facilities. |
| PART 2 - PRODUCTS - Not Used. |
| PART 3 - EXECUTION - Not Used. |
File details come from the government source that posted it. Updated .