00 65 16 - Certificate of Substantial Completion.pdf

PDF 250 KB Posted

Attached to
Biosolids Project 011139.0465
Solicitation number
US.260443
Issued by
Lancaster County, Pennsylvania

About this file

This is a Certificate of Substantial Completion prepared by Herbert, Rowland & Grubic, Inc., an engineer, for the Ephrata Borough Authority's Biosolids Improvements Project. The certificate, based on the modified EJCDC C-625 form, documents that authorized representatives of the Owner, Contractor, and Engineer have inspected the Work and found it to be substantially complete. The document covers two separate construction contracts: Contract No. EBA26-2 for General Construction and Contract No. EBA26-3 for Electrical Construction. The project involves coordination and interconnection of two new owner-procured Biodryers, demolition and replacement of dewatered solids conveyor systems, selective wall demolition and replacement, indoor utility replacements, site piping replacement and relocation, a dumpster loading canopy, and associated electrical improvements. The Date of Substantial Completion establishes the commencement of the contractual correction period and applicable warranties as required by the Contract Documents. A punch list of items to be completed or corrected is attached to this Certificate, though it may not be all-inclusive and does not alter the Contractor's responsibility to complete all Work in accordance with the Contract Documents.

The Certificate specifies that amendments to both Owner and Contractor responsibilities regarding security, operation, safety, maintenance, heat, utilities, insurance, and warranties are noted as "None," indicating no modifications to the standard contractual obligations. The Certificate explicitly states that it does not constitute acceptance of Work not in accordance with the Contract Documents, nor does it release the Contractor's obligation to complete all Work as specified. The document requires execution by the Engineer through authorized signature, with spaces provided for the signatory's name and title. No pricing terms, set-asides, or funding information is contained within this Certificate of Substantial Completion document.

View the file

Other files

File Type Posted
26 08 00 - Electrical Field Acceptance Tests.pdf PDF
00 63 25 - Substitution Request Form (During Construction).pdf PDF
40 05 36 - Fiberglass-Reinforced Plastic Process Pipe.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 60 00 - Project Forms.pdf PDF
26 29 23 - VFDs .pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
26 05 19 - Conductors.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
05 53 00 - Metal Gratings (VPR).pdf PDF
02 41 19.13 - Selective Building Demolition (VPR).pdf PDF
01 29 00 - Payment Procedures.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
01 64 00 - Owner Furnished Products.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 25 00 - Erosion And Sedimentation Controls.pdf PDF
40 05 65.23 - Swing Check Valves.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
05 50 00 - Metal Fabrications (VPR).pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
26 09 16 - Auxiliary Controls & Relays.pdf PDF
01 10 00 - Project Summary.pdf PDF
05 52 00 - Metal Railings (VPR).pdf PDF
26 24 19 - MCC.pdf PDF
26 05 53 - Electrical System Identification.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 60 00 - Grouting (VPR).pdf PDF
01 61 00 - Product Requirements.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 31 00a Ephrata Boro Record Drawings.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
26 27 16 - Control Panels & Enclosures.pdf PDF
26 05 26 - Grounding.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 01 01 - LA Cover.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
32 92 19 - Seeding.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
05 31 23 - Steel Roof Decking (VPR).pdf PDF
00 52 00b - Agmnt btw Own and Cntr for Const Con Stip Price - Electrical Construction.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Modified EJCDC® C-625, Certificate of Substantial Completion. Prepared and published 2018 by the Engineers Joint Contract Documents Committee.

Herbert, Rowland & Grubic, Inc. 00 65 16 - 1 011139.0465

CERTIFICATE OF SUBSTANTIAL COMPLETION

Owner: Ephrata Borough Authority Owner's Contract No.:

Contractor: Contractor’s Project No.:

Engineer: Herbert, Rowland and Grubic, Inc. Engineer's Project No.: 011139.0465

Project: Biosolids Improvements Project Contract No. EBA26-2 – General Construction Contract No. EBA26-3 – Electrical Construction

Contract Name:

This ☐ Preliminary ☐ Final Certificate of Substantial Completion applies to:

All Work The following specified portions of the Work:

Date of Substantial Completion:

The Work to which this Certificate applies has been inspected by authorized representatives of Owner, Contractor, and Engineer, and found to be substantially complete. The Date of Substantial Completion of the Work or portion thereof designated above is hereby established, subject to the provisions of the Contract pertaining to Substantial Completion.

The date of Substantial Completion in the final Certificate of Substantial Completion marks the commencement of the contractual correction period and applicable warranties required by the Contract.

A punch list of items to be completed or corrected is attached to this Certificate. This list may not be all-inclusive, and the failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents.

Amendments of contractual responsibilities recorded in this Certificate should be the product of mutual agreement of Owner and Contractor; see Paragraph 15.03.D of the General Conditions.

The responsibilities between Owner and Contractor for security, operation, safety, maintenance, heat, utilities, insurance, and warranties upon Owner's use or occupancy of the Work must be as provided in the Contract, except as amended as follows:

Amendments to Owner's responsibilities: None As follows

Amendments to Contractor's responsibilities: None As follows:

The following documents are attached to and made a part of this Certificate:

This Certificate does not constitute an acceptance of Work not in accordance with the Contract Documents, nor is it a release of Contractor's obligation to complete the Work in accordance with the Contract.

EXECUTED BY ENGINEER:

By:

(Authorized signature)

Name:

Title:

File details come from the government source that posted it. Updated .