JA-5_AF_Form_66.pdf

Air Force Form PDF 470 KB Posted

Attached to
Youth Center Roof Repair
Solicitation number
FA5004-16-B-C003
Issued by

About this file

JA-5 AF Form 66

View the file

Other versions and copies of AF Form 66

File Revision Posted Attached to
Attachment 2 AF Form 66.pdf Revision not stated REPAIR AC PAVING
AF form 66 Blank.pdf Revision not stated Demo Mini mute sites
Attach 9_AF Form 66 Submittal Register.pdf Revision not stated PKAA Dorm Water Damage Repair (Construction)
AF Form 66-EEPZ260842 Renovate Convert Comm to SAPR B730.xlsx Revision not stated B730 Renovate Convert Comm to SAPR
AF Form 66_EEPZ254664-B972 UOQ.xlsx Revision not stated B972 Renovate UOQ Community Commons
AF Form 66 B268.xlsx Revision not stated B268 Replace STUS Backup Generator
AF Form 66 B730.xlsx Revision not stated B730 - Renovate RM106 for Emergency Operations Center
AF Form 66.xlsx Revision not stated B836 Replace Electrical in Airfield Lighting Vault
AF Form 66 OSI Flooring.xlsx Revision not stated OSI B926 Flooring
EEPZ254660 Repair Control Tower HVAC B1806 - AF Form 66.xlsx Revision not stated B1806 Repair Control Tower HVAC
AF Form 66 Template.xlsx Revision not stated Replace AAS BAK-15 Controls, B2001, B2003
AF Form 66 EEPZ216808 Replace Security Forces Elevator B926.xlsx Revision not stated B926 Replace Security Forces Elevator
WT 17518487 AF Form 66.xlsx Revision not stated Repair Structural Fire Trainer B17903, 17904
AF Form 66.xlsx Revision not stated RENOVATE/CONVERT 50th 49th SQ OPS, B230
AF Form 66.xlsx Revision not stated T-6 Flightline Shacks
AF Form 66 Template.xlsx Revision not stated Replace Fire Alarms, Multi Facility
EEPZ248229 -- AF Form 66.xlsx Revision not stated Repair Kiddie Pool
Atch 2 AF Form 66.pdf Revision not stated Removal of Underground Storage Tank at Launch Facility E-10 (Laramie County, WY)
Attachment 4 - AF Form 66 Submittal Register.pdf Revision not stated Bldg 65 - Renovation of Telephone Office Area, FE Warren AFB, WY AMENDMENT 03
Attachment 7 - AF Form 66.xlsx Revision not stated Replace Chapel Windows B912
Show all 20

Who attaches AF Form 66

State Files
Iowa 1
Massachusetts 1

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT NO.

SCHEDULE OF MATERIAL SUBMITTALS

KEY: 1 SC -1 WEEK PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 2 CM -2 WEEKS PRIOR TO COMMISSIONING 4 15 -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR DIVISION 15 4 SC -4 WEEKS PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 4 CM -4 WEEKS PRIOR TO COMMISSIONING 4 M -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR SPEC SECTION

PR -4 WEEKS PRIOR TO CONSTRUCTION ACTIVITY

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

L I N E

N U M B E R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

C

E R

T

IF

IC

A

T

IO

N O

F C

O M

P L

IA

N

C E

S H

O P

D R

A W

IN

G

S

S A

M P

L E

S

C O

L O

R S

E L

E C

T

IO

N

M A

N U

F A

C T

R 'S

R E

C O

M M

E N

D A

T

IO

N S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

C A

T A

L O

G

D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

S E

R V

IC

E

S

IZ

E

U

S E

S C

H E

D U

L E

O T

H E

R

REQUIRED

SUB-

MISSION

DATE

DATE

RECEIVED

IN CON-

TRACTING

DATE TO

CIVIL

ENGINEER-

ING

RETURN

SUSPENSE

DATE

FOLLOW-UP

DATE

CONTRACTOR

NOTIFIED

CONTRAC-

TOR RE-

SUBMIT-

TAL

FINAL APPROVAL REMARKS

APPROV

ED

DIS-

APPROV

ED

STATEMENT OF WORK

(SOW)

1 Work Plan, SOW 3.1 5 4 wks prior to work

01010 DESCRIPTION OF

WORK AND COORDINATION

2 AF Form 103 01010 1.11 A

3 2 wks prior to work start

01000 SUMMARY OF WORK

3 Welding Permits 01000 - 9.1 (If applicable)

2 2 wks prior to work

01030 SAFETY,

ENVIRONMENTAL

PROTECTION,

REGULATIONS, AND CODES

4 Construction Operations and Safety Plan - 1.6 2 4 wks prior to work 5 Safety and Health Plan - 1.8

2 4 wks prior to work

6 Environmental Protection Plan (EPP) - 1.20 2 6 wks prior to work 7 Hazardous Materials Inventory -

1.21 2 2 wks prior to work

8 Hazardous Waste Accumulation Log - 1.22 2 As Applicable

NOI and asbestos abatement plan (if required) 1.26B 4

10 working days prior to work start

Submit only if applicable

Waste disposal/Borrow pit worksheet, 1.26C (if required) 2 w/in 3 days of material transfer Submit only if applicable

Asbestos waste manifests, 1.26D (if required) 2 w/in 3 days of material transfer Submit only if applicable

Abatement Drawings, 1.26F (if required) 2 with Closeout submittals Submit only if applicable

Final Asbestos report, 1.26G (if required) 3 with Closeout submittals Submit only if applicable

14 Schedule- 1.6 2 4 wks prior to work

FTQW 12-1040 Repair Roof of Youth Center Annex (B3303)

FA5004-16-B-C003

EIELSON AFB, AK

ATTACHMENT JA-5

AF FORM 66

SOLICITATION/CONTRACT NO.

SCHEDULE OF MATERIAL SUBMITTALS

KEY: 1 SC -1 WEEK PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 2 CM -2 WEEKS PRIOR TO COMMISSIONING 4 15 -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR DIVISION 15 4 SC -4 WEEKS PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 4 CM -4 WEEKS PRIOR TO COMMISSIONING 4 M -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR SPEC SECTION

PR -4 WEEKS PRIOR TO CONSTRUCTION ACTIVITY

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

L I N E

N U M B E R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

C

E R

T

IF

IC

A

T

IO

N O

F C

O M

P L

IA

N

C E

S H

O P

D R

A W

IN

G

S

S A

M P

L E

S

C O

L O

R S

E L

E C

T

IO

N

M A

N U

F A

C T

R 'S

R E

C O

M M

E N

D A

T

IO

N S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

C A

T A

L O

G

D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

S E

R V

IC

E

S

IZ

E

U

S E

S C

H E

D U

L E

O T

H E

R

REQUIRED

SUB-

MISSION

DATE

DATE

RECEIVED

IN CON-

TRACTING

DATE TO

CIVIL

ENGINEER-

ING

RETURN

SUSPENSE

DATE

FOLLOW-UP

DATE

CONTRACTOR

NOTIFIED

CONTRAC-

TOR RE-

SUBMIT-

TAL

FINAL APPROVAL REMARKS

APPROV

ED

DIS-

APPROV

ED

FTQW 12-1040 Repair Roof of Youth Center Annex (B3303)

06100 ROUGH CARPENTRY

15 Product Data - 3.1 2 2 wks prior to ordering materials

07530 SINGLE-PLY

MEMBRANE ROOFING

16 Product Data - 2.1 2 2 wks prior to ordering materials

17 Manufacturer's Warranty - 2.2 2 1 wk after complete

07650 - FLEXIBLE FLASHING

18 Product Data - 3.1 2 2 wks prior to ordering materials

19 Shop Drawings - 3.2 3 4 wks prior to work

075323 - ETHYLENE

PROPYLENE DIENE

MONOMER ROOFING

20 Shop Drawings - SD-02 3 4 wks prior to work

21 Product Data - SD-03 2 4 wks prior to work

22 Design Data - SD-05 2 4 wks prior to work

23 Certificates - SD-07 2 4 wks prior to work

24 Manufacturer's Instructions -

SD-08

2 4 wks prior to work

25 Closeout Submittals - SD-11 2 1 wk after complete

FA5004-16-B-C003

EIELSON AFB, AK

ATTACHMENT JA-5

AF FORM 66