JA-5_AF_Form_66.pdf
Air Force Form PDF 470 KB Posted
- Attached to
- Youth Center Roof Repair
- Solicitation number
- FA5004-16-B-C003
About this file
JA-5 AF Form 66
View the file
Other versions and copies of AF Form 66
Show all 20
Who attaches AF Form 66
| State | Files |
|---|---|
| Iowa | 1 |
| Massachusetts | 1 |
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION/CONTRACT NO.
SCHEDULE OF MATERIAL SUBMITTALS
KEY: 1 SC -1 WEEK PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 2 CM -2 WEEKS PRIOR TO COMMISSIONING 4 15 -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR DIVISION 15 4 SC -4 WEEKS PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 4 CM -4 WEEKS PRIOR TO COMMISSIONING 4 M -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR SPEC SECTION
PR -4 WEEKS PRIOR TO CONSTRUCTION ACTIVITY
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL
C
E R
T
IF
IC
A
T
IO
N O
F C
O M
P L
IA
N
C E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
R 'S
R E
C O
M M
E N
D A
T
IO
N S
M A
N U
F A
C T
U R
E R
'S W
A R
R A
N T
Y
C A
T A
L O
G
D
A T
A
O P
E R
A T
IN
G
I N
S T
R U
C T
IO
N
S
S E
R V
IC
E
S
IZ
E
U
S E
S C
H E
D U
L E
O T
H E
R
REQUIRED
SUB-
MISSION
DATE
DATE
RECEIVED
IN CON-
TRACTING
DATE TO
CIVIL
ENGINEER-
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP
DATE
CONTRACTOR
NOTIFIED
CONTRAC-
TOR RE-
SUBMIT-
TAL
FINAL APPROVAL REMARKS
APPROV
ED
DIS-
APPROV
ED
STATEMENT OF WORK
(SOW)
1 Work Plan, SOW 3.1 5 4 wks prior to work
01010 DESCRIPTION OF
WORK AND COORDINATION
2 AF Form 103 01010 1.11 A
3 2 wks prior to work start
01000 SUMMARY OF WORK
3 Welding Permits 01000 - 9.1 (If applicable)
2 2 wks prior to work
01030 SAFETY,
ENVIRONMENTAL
PROTECTION,
REGULATIONS, AND CODES
4 Construction Operations and Safety Plan - 1.6 2 4 wks prior to work 5 Safety and Health Plan - 1.8
2 4 wks prior to work
6 Environmental Protection Plan (EPP) - 1.20 2 6 wks prior to work 7 Hazardous Materials Inventory -
1.21 2 2 wks prior to work
8 Hazardous Waste Accumulation Log - 1.22 2 As Applicable
NOI and asbestos abatement plan (if required) 1.26B 4
10 working days prior to work start
Submit only if applicable
Waste disposal/Borrow pit worksheet, 1.26C (if required) 2 w/in 3 days of material transfer Submit only if applicable
Asbestos waste manifests, 1.26D (if required) 2 w/in 3 days of material transfer Submit only if applicable
Abatement Drawings, 1.26F (if required) 2 with Closeout submittals Submit only if applicable
Final Asbestos report, 1.26G (if required) 3 with Closeout submittals Submit only if applicable
14 Schedule- 1.6 2 4 wks prior to work
FTQW 12-1040 Repair Roof of Youth Center Annex (B3303)
FA5004-16-B-C003
EIELSON AFB, AK
ATTACHMENT JA-5
AF FORM 66
SOLICITATION/CONTRACT NO.
SCHEDULE OF MATERIAL SUBMITTALS
KEY: 1 SC -1 WEEK PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 2 CM -2 WEEKS PRIOR TO COMMISSIONING 4 15 -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR DIVISION 15 4 SC -4 WEEKS PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 4 CM -4 WEEKS PRIOR TO COMMISSIONING 4 M -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR SPEC SECTION
PR -4 WEEKS PRIOR TO CONSTRUCTION ACTIVITY
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL
C
E R
T
IF
IC
A
T
IO
N O
F C
O M
P L
IA
N
C E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
R 'S
R E
C O
M M
E N
D A
T
IO
N S
M A
N U
F A
C T
U R
E R
'S W
A R
R A
N T
Y
C A
T A
L O
G
D
A T
A
O P
E R
A T
IN
G
I N
S T
R U
C T
IO
N
S
S E
R V
IC
E
S
IZ
E
U
S E
S C
H E
D U
L E
O T
H E
R
REQUIRED
SUB-
MISSION
DATE
DATE
RECEIVED
IN CON-
TRACTING
DATE TO
CIVIL
ENGINEER-
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP
DATE
CONTRACTOR
NOTIFIED
CONTRAC-
TOR RE-
SUBMIT-
TAL
FINAL APPROVAL REMARKS
APPROV
ED
DIS-
APPROV
ED
FTQW 12-1040 Repair Roof of Youth Center Annex (B3303)
06100 ROUGH CARPENTRY
15 Product Data - 3.1 2 2 wks prior to ordering materials
07530 SINGLE-PLY
MEMBRANE ROOFING
16 Product Data - 2.1 2 2 wks prior to ordering materials
17 Manufacturer's Warranty - 2.2 2 1 wk after complete
07650 - FLEXIBLE FLASHING
18 Product Data - 3.1 2 2 wks prior to ordering materials
19 Shop Drawings - 3.2 3 4 wks prior to work
075323 - ETHYLENE
PROPYLENE DIENE
MONOMER ROOFING
20 Shop Drawings - SD-02 3 4 wks prior to work
21 Product Data - SD-03 2 4 wks prior to work
22 Design Data - SD-05 2 4 wks prior to work
23 Certificates - SD-07 2 4 wks prior to work
24 Manufacturer's Instructions -
SD-08
2 4 wks prior to work
25 Closeout Submittals - SD-11 2 1 wk after complete
FA5004-16-B-C003
EIELSON AFB, AK
ATTACHMENT JA-5
AF FORM 66
File details come from the government source that posted it. Updated .