JA-2_Statement_of_Work.pdf

PDF 543 KB Posted

Attached to
Youth Center Roof Repair
Solicitation number
FA5004-16-B-C003
Issued by

About this file

JA-2 Statement of Work

View the file

Other files

File Type Posted
Questions_ _Answers_19_May_2016.pdf PDF
FA5004-16-B-C003-0002.pdf PDF
JA-6_Site_Map _As_Built_Drawings _ _Pictures.pdf PDF
Sign_In_Sheet_5_May_16.pdf PDF
JA-4_Wage_Determination.pdf PDF
FA5004-16-B-C003-0001.pdf PDF
JA-3_Specifications.pdf PDF
FA5004-16-B-C003.pdf PDF
JA-6_Site_Map _As_Built_Drawings _ _Pictures.pdf PDF
JA-7_Asbestos_Report.pdf PDF
JA-1_Other_Contract_Requirements.pdf PDF
JA-5_AF_Form_66.pdf PDF
JA-8_-_AF_Forms.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

PROJECT FTQW 12-1040

REPAIR ROOF OF YOUTH CENTER ANNEX B3303

1.0 SCOPE: Furnish all plant, labor, supplies, parts, transportation, tools, equipment, and facilities necessary to perform work required to complete project FTQW 12-1040 in strict accordance with this Statement of Work. All work shall be warranted as indicated in the

Performance Work Specification, Section 01000 and project specifications.

2.0 DESCRIPTION OF WORK: Repair the entire roof of Bldg 3303 by replacement. The roof system shall be installed in accordance with manufacturers' specifications, as stated in

Specifications Section 072353, SD-08.

2.1 Remove the existing 3,196 SF IRMA roof system, including insulation. Remove all flashing.

2.3 Remove the existing 4,430 SF BUR roof system, including insulation. Remove all flashing.

2.4 Install 7,626 SF EPDM system insulated to R38 in accordance with manufacturer's specifications and in the specifications, section 07530.

2.5 Install tapered insulation for IRMA/BUR roof system to provide proper drainage into newly installed drains accordingly to specifications, section 07530 7.1.1.

2.6 Install 3,196 SF 5/8” gypsheeting thermal barrier in accordance with manufacturer’s specifications

2.7 Install designed roof edges, curbs, roof divider and expansion joint as shown in

Attachment 2.

2.7 Install new 656 SF flashing and expansion joints. Flashings shall be chosen and installed to withstand wind gusts at speeds of up to 24 knots and in accordance to

Specifications, Section 07650. Roof flashing color must match roof material.

2.8 Install manufactured flashing for 15 vents though roof (VTRs) in accordance to

Specifications, Section 07720.

2.9 Install 315 SF metal flashings and expansion joints in accordance with manufacturing specifications and Specifications, Section 07650.

2.10 Install 7,626 SF FFP 8mil polyethylene vapor barrier in accordance to

FA5004-16-B-C003

EIELSON AFB, AK

ATTACHMENT JA-2

manufacturer’s specifications and to Specifications, Section 07650 8.8.

2.11 Install 5 new roof drains with 2-4” drain extensions and install flashing for drains in accordance to manufacturer’s specifications and Specifications, Section 07650 14.14.

2.12 Install roof warranty signs on exterior of building near roof access points.

2.12.1 Post a 12" x 12" x 1/8" brown sign with white lettering at any and all access points to the roof. These signs will be posted at or near eye level on the nearest vertical surfaces to the access points to the roof and will read as follows:

a. THIS ROOF IS UNDER WARRANTY UNTIL EXPIRATION DATE:

[expiration date of warranty] DO NOT PENETRATE THIS ROOF

WITHOUT NOTIFYING 354 CES Roofing Engineer, 377-3157

3.0 SUBMITTALS: Documents shall be submitted according to the attached AF Form 66.

3.1 Work Plans (WPs) - Prior to commencement of work, the Contractor shall submit a

Work Plan (WP) delineating methodology, material, manpower, etc. necessary to perform the work. The Work Plan shall also include a schedule. This plan shall cover each major definable feature of the work to be performed (Contractor’s work as well as

Subcontractor’s work).

4.0 GOVERNMENT FURNISHED MATERIALS: None.

5.0 ATTACHMENTS:

5.1 AF Form 66, Schedule of Material Submittals

5.2 Appendix 1, Proposal Roof Plan B3303

22 March 2016