J-FY20 Monthly Summary Report-Jul 2020.pdf
PDF 2 MB Posted
- Attached to
- Aerial Targets III FY23 Federal contract opportunity
- Solicitation number
- FA489021CPKCA
About this file
This pre-solicitation notice seeks industry feedback for aircraft and target drone maintenance, range instrumentation system operations and maintenance, and support services at Tyndall Air Force Base, Florida and Holloman Air Force Base, New Mexico. Periodic deployments to the Utah Test and Training Range and other continental United States locations may be required. The Air Combat Command Acquisition and Management Integration Center will issue this solicitation for the Aerial Targets III contract providing maintenance, operations, and support services for aerial targets and range systems. Services include full-scale and sub-scale aerial target maintenance and operations, range instrumentation system operations and maintenance, and associated support functions.
View the file
Other files for this federal contract opportunity
Show all 50
Aerial Targets III FY23 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AERIAL TARGETS MONTHLY SUMMARY JULY 2020
Unclassified Page 1 of 42 Distribution: A
Aerial Targets Monthly Contract Summary Report – CDRL A001
Contract Number FA4890-15-C-0018
1 – 31 July 2020
Prepared for:
Acquisition Management and Integration Center
Langley AFB, Virginia
Prepared by:
PAE Aviation and Technical Services, LLC
1001 Florida Avenue
Tyndall AFB, Florida
David Olson
Program Manager
Aerial Targets Program
UNCLASSIFIED
Distribution Limitation: A
Unclassified Page 2 of 42
TABLE OF CONTENTS
Tab 1A – FULL-SCALE AERIAL TARGETS – TYNDALL AFB, FL
Tab 1B – FULL-SCALE AERIAL TARGETS – HOLLOMAN AFB, NM
Tab 2 – SUBSCALE AERIAL TARGETS – TYNDALL AFB, FL
Tab 3 – RANGE INSTRUMENTATION SYSTEM (RIS) O&M
Tab 4 – MAINTENANCE DATA SYSTEM ANALYSIS (MDSA) METRICS
Tab 5 – TECHNICAL REPORT STATUS
Tab 6 – QUALITY CONTROL (QC) SUMMARY REPORT
Tab 7 – RIS MAINTENANCE ANALYSIS REQUESTS
Tab 8 – FACILITIES OPEN WORK REQUESTS
Tab 9 – CONTRACTOR PROGRAM MANAGEMENT CONCERNS
Unclassified Page 3 of 42
TAB 1A – FULL-SCALE AERIAL TARGETS – TYNDALL AFB, FL
1. SORTIES SCHEDULED:
Note: Off-station sorties reported in this summary are credited to the location that possessed the aircraft, regardless of who launched or recovered the aircraft.
2. MISSIONS FLOWN:
QF-16 NULLO:
Mission Symbol Mission Project Supported # Missions FYTD
O5ZZ AIM-9X AIM-9X 5
All O5ZZ 5
Sub Total 5 19
QF-16 MANNED:
Mission Symbol Mission Project Supported # Missions
All O3ZZ 0 3
O5ZZ AIM-9X AIM-9X 4
O5ZZ Combat Sentry Combat Sentry 7
O5ZZ JATM JATM 2
All O5ZZ 13 155
O6ZZ AIM-9X AIM-9X 2
O6ZZ Combat Sentry Combat Sentry 4
O6ZZ CT O&M 39
O6ZZ Cross Country O&M 4
All O6ZZ 49 446
O8ZZ CT O&M 1
O8ZZ SAFE O&M 4
All O8ZZ 5 10
Sub Total 67 614
Grand Total 72 633
QF-16 JUL 20 FYTD
Scheduled 92 841
Canceled 18 105
Successful Flown 72 629
Ground Aborts 5 57
Air Aborts 0 4
Total Flown 72 633
Unclassified Page 4 of 42
3. TOTAL HOURS FLOWN:
Mission Symbol Hours FYTD
O5ZZ 3.6 12.8
Sub Total 3.6 12.8
Hours FYTD
O3ZZ 0.0 4.7
O5ZZ 23.3 249.7
O6ZZ 56.6 567.4
O8ZZ 6.1 12.8
Sub Total 86.0 834.6
Grand Total 89.6 847.4
4. MISSIONS CANCELED:
Date
MDS
AF#
Msn
Sym
Mission
Reason
7 Jul QF-16C 48 O6ZZ CT Weather
10 Jul QF-16C 51 O5ZZ JATM Project
13 Jul QF-16C 62 O8ZZ SAFE ATC
14 Jul QF-16A 42 O5ZZ AIM-9X ATC
14 Jul QF-16C 48 O5ZZ CT Weather
14 Jul QF-16C 29 O5ZZ CT Weather
14 Jul QF-16C 47 O5ZZ CT Weather
15 Jul QF-16C 48 O5ZZ DACT Weather
15 Jul QF-16C 22 O5ZZ DACT Weather
16 Jul QF-16C 48 O5ZZ Combat Sentry Weather
16 Jul QF-16C 52 O5ZZ Chase Weather
16 Jul QF-16C 31 O5ZZ AIM-9X Weather
21 Jul QF-16C 51 O5ZZ CT Ops
27 Jul QF-16C 62 O6ZZ FCS Weather
27 Jul QF-16C 53 O6ZZ CT Weather
29 Jul QF-16C 49 O6ZZ CT Ops
31 Jul QF-16A 40 O5ZZ AIM-9X Project
31 Jul QF-16C 47 O5ZZ Chase Project
5. ABORTS – GROUND AND AIR:
Date Type
Abort
MDS AF
Msn
Sym
Mission Reason
2 Jul GAB QF-16C 56 O6ZZ SAFE CADC
Unclassified Page 5 of 42 Distribution: A
14 Jul GAB QF-16C 48 O5ZZ CT FLCS (Spare Avail Not Used)
14 Jul GAB QF-16C 29 O5ZZ CT FTIT Gauge
20 Jul GAB QF-16C 68 O8ZZ SAFE Engine Fault
27 Jul GAB QF-16C 50 O6ZZ Chase Centerline Fuel Tank Read Zero
6. MAINTENANCE AND LOGISTICS PROBLEMS:
a. Maintenance:
(1) QF-16:
(a) AF056 Awaiting SAFE
(b) AF068 Awaiting SAFE
(c) AF059 Acceptance INW
(d) AF065 Acceptance INW
(e) AF069 Acceptance INW
(f) AF066 Acceptance INW
(2) AGE/Support Vehicles:
(a) QF-16 AGE and Support/Test Equipment
1. Procurement of AGE equipment, support/test equipment is continuing.
(b) Stock listed and commercially procured AGE maintenance equipment and tool purchasing in work.
b. Logistics:
(1) Long lead-time (MICAP) on F-16A components is negatively affecting the ability to generate aircraft.
(2) Post Hurricane Michael supply needs are being met via Tyndall AFB and Eglin AFB.
Delays in processing/receiving parts are continual.
(3) IMDS Cloud Migration
(a) Major slowdown in normal processing with near total stoppages for several days.
(b) Resulting in extreme difficulty to properly document/track inspections, time changes, including safety-of-flight issues, parts tracking and debriefing procedures.
(c) Designed and implemented numerous locally designed tracking tools to track data and other issues until IMDS is fully restored.
Unclassified Page 6 of 42
7. WASHES:
a. Washes Accomplished in July 2020:
WEEK ENDING AF#
30 Day: 3 July Data not available due to IMDS Cloud issues
10 July Data not available due to IMDS Cloud issues
17 July Data not available due to IMDS Cloud issues
24 July Data not available due to IMDS Cloud issues
31 July Data not available due to IMDS Cloud issues
a. Washes Not Accomplished & Reasons:
Data not available due to IMDS Cloud issues
c. Wash Schedule for August 2020:
WEEK ENDING AF#
30 Day: 7 August 060, 035, 030
14 August 049, 047, 068, 062, 022, 027, 040
21 August 048, 026, 024, 031, 050, 021, 029
28 August 052, 056, 054, 065, 051
31 August 053
8. REPEAT/RECURRING DISCREPANCIES:
Date MDS AF# R/R Discrepancy Corrective Action
None
9. RECOMMENDATIONS: Negative this report period.
10. SPECIAL PROJECTS/SPECIAL INTEREST: Negative this report period.
Unclassified Page 7 of 42
TAB 1B – FULL-SCALE AERIAL TARGETS – HOLLOMAN AFB, NM
Note: Off-station sorties reported in this monthly summary are credited to the location that possessed the aircraft, regardless of who launched or recovered the aircraft.
All O5ZZ NULLO F-35 HOT 1 1
Sub Total
All O3ZZ HILL AFB Full Paint 2 10
All O4ZZ 0
O5ZZ F-35 Dress F-.35 2
O5ZZ F-35 Chase F-35 1
O5ZZ Patriot Army 6
All O5ZZ 9 58
O6ZZ C/T Training 12
O6ZZ Red Air Training 2
All O6ZZ 14 171
All O8ZZ 1
Grand Total 26 241
05ZZ 0.9 0.9
NULLO sub Total
Hours FYTD
O3ZZ 3.4 17.4
O4ZZ 0.0 0.0
QF-16 JUL 20 FYTD
Scheduled 30 264
Canceled 4 22
Successful Flown 26 241
Ground Aborts 0 17
Air Aborts 0 1
Total Flown 26 242
Unclassified Page 8 of 42 Distribution: A
O5ZZ 14.4 94.7
O6ZZ 19.5 253.9
O8ZZ 0.0 1.3
Sub Total 38.2 368.2
Grand Total 38.2 368.2
Date MDS AF# Msn
Mission Reason
8 Jul QF-16C 055 O5ZZ F-35 Chase Project
8 Jul QF-16C 008 O5ZZ F-35 Hot Project
15 Jul QF-16C 055 O5ZZ C/T Ops
15 Jul QF-16C 044 O5ZZ C/T Ops
Date Type
Abort
MDS AF# Msn
Sym
Negative this report
a. Maintenance: We were without AF028 the entire month due to replacement engine needed. It has been ordered and repairs are in work on the replacement engine at the CRF.
b. Logistics: New Items: Negative this report period.
7. WASHES:
Washes Accomplished: QF012
Washes Not Accomplished & Reasons:
QF028 – F-1 Cavity Fuel Leak
Date MDS AF# R/R Discrepancy Corrective Action
Negative this report
9. RECOMMENDATIONS: Negative this report period.
10. SPECIAL PROJECTS/SPECIAL INTEREST: Negative this report period.
Unclassified Page 9 of 42
TAB 2 – SUBSCALE AERIAL TARGETS – TYNDALL AFB, FL
Note: Off-station sorties reported in this monthly summary are credited to the location that possessed the aircraft, regardless of who launched or recovered the aircraft.
BQM-167A
Symbol
Mission Project Supported #
Missions
FYTD
O5ZZ F-15 OFP/ CTF F-15 OFP/ CTF 0 2
O5ZZ AFSAT APS AFSAT APS 1 1
O5ZZ APS TEST APS Test 0 1
O5ZZ F16 Cruise Missile Defense
Test
F16 Cruise Missile Defense
Test
0 1
O5ZZ AMRAAM SIP AMRAAM SIP 1 5
O5ZZ AIM 9X AIM 9X 0 5
O5ZZ AMR PHS4 AMR PHS4 0 1
O5ZZ WSEP WSEP 9 47
Total 11 63
BQM-167A
O5ZZ 7.8 49.5
Total 7.8 49.5
Date
MDS
Tail #
Msn Sym
Reason
2 Jul BQM167A O5ZZ AFSAT APS Project
14 Jul BQM167A O5ZZ WSEP Project
15 Jul BQM167A O5ZZ WSEP Project
15 Jul BQM167A O5ZZ WSEP Project
BQM-167A JUL 20 FYTD
Scheduled 21 112
Canceled 10 48
Successful Flown 9 61
Ground Aborts 0 3
Air Aborts 1 1
Total Flown 11 63
Unclassified Page 10 of 42 Distribution: A
16 Jul BQM167A O5ZZ WSEP Project
16 Jul BQM167A O5ZZ WSEP Project
17 Jul BQM167A O5ZZ WSEP Project
22 Jul BQM167A O5ZZ WSEP Project
23 Jul BQM167A O5ZZ WSEP Project
30 Jul BQM167A O5ZZ AMRAAM SIP Project
Date Type Abort MDS Tail# Msn
16 Jul BQM167A 17-0604 O5ZZ WSEP Uncommanded engine shutdown
a. Hurricane damage to building 256’s roof continues to impact Mx activity and available storage space due to the amount of water intrusion into the hangar. Maintenance time is lost to cleaning it up after any rain. Temporary Mx facilities have been erected, but are awaiting a floor covering change-out before they can be moved into.
b. Minor adjustments to the established Forward Supply point continue, but there are presently no new or major impacts to target generation.
c. The three temporary facilities for SSAT Mx and the two for the chute shop have been identified as “Not safe for Mx personnel during a 5 MILE LIGHTNING LIGHT” and will require evacuation during this entire period. PAE has engaged the 53 WEG leadership for possible alternatives that would negate the need to leave the facilities. Additionally, we have asked for a location to be identified for Mx to go to during this time.
d. We have been notified that all 5 tents (chute shop x 2 and SSAT Mx x 3) will have to be moved. Locations for them are still in discussion.
7. CORROSION CONTROL INSPECTION:
a. Launch Pad Corrosion Control Maintenance: Routine corrosion control is being accomplished on all applicable support equipment.
b. Launch Rail Gantry systems 1, 2, 5, & 6 are showing signs of severe corrosion (they were installed in 1975). Presently, they are all serviceable. However, their replacements should be programmed / considered in the near future. NOTE: Gantries on rails 3 & 4 are newer and will not require replacement any time soon.
Unclassified Page 11 of 42
Date MDS Tail# R/R Discrepancy Corrective Action
None
9. RECOMMENDATIONS: None
10. SPECIAL PROJECTS: None
Unclassified Page 12 of 42 Distribution: A
TAB 3 – RANGE INSTRUMENTATION SYSTEM (RIS) O&M
1. Tellabs Switch and Data/Comm. Operational Availability:
Tellabs Switch: 100% Available
Data/Comm. Circuits: 100% Available
2. Mission Availability:
GRDCS: 100% Available
RCS: 100% Available
Access Net: 100% Available
Mission Video: 100% Available
TPS-75 Radar: Scheduled Available Non-Charge Not Available
Missions 38 35.05 0 2.95
Hours 94.75 87.25 0 7.50
Overall Availability: 92.08% Available ((Available + Non-Charge)/Scheduled)
0%
20%
40%
60%
80%
100%
Tellabs Switch Data/Comm
July 100% 100%
12 month avg 100% 100%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
100%
GRDCS RCS AccessNet TPS-75 Mission Video
July 100% 100% 100% 92.1% 100.0%
12 month avg 100% 100% 100% 99.3% 100%
Unclassified Page 13 of 42 Distribution: A
3. Summary of Mission Maintenance Actions:
a. 17 July 2020:
Troubleshot DLS S/N 098 (from E-9 048) to faulty R/T Unit resulting in unit decommission; Reference RIS 201560101.
Configured DLS S/N 123 for aircraft installation and performed bench check and site calibration at RWS; unit delivered to E-9 crew for installation in tail number 048.
b. 22 July 2020: Performed bench checks on DLSr S/N 019 and found no data throughput resulting in RMA request for repair at MSI.
c. 24 July 2020: Performed self-calibration on 915 DTS S/N 002.
4. RIS Scheduled Maintenance Summary:
a. GRDCS:
1) Due within 45 Days:
Monthly Console Checks, by 31 August 2020
2) Due within 90 Days:
Data Link Subsystem Annual Checks:
SITE DATE DUE S/N Test Type
SUBE 02 Sep 2020 025 Annual
SUBW 02 Sep 2020 032 6 Month
DEPOT 07 Sep 2020 054 6 Month
D3 15 Sep 2020 016 6 Month
PCB 15 Sep 2020 027 6 Month
RWER 17 Sep 2020 031 6 Month
Depot 17 Sep 2020 033 6 Month
SHELL 22 Sep 2020 035 6 Month
CARRABELLE 22 Sep 2020 036 6 Month
1801 ISC1 16 Oct 2020 078 Annual
Unclassified Page 14 of 42
b. TPS-75 Radar: Accomplished this month and due within 45 Days.
JOB Completed or due from3/30/2020 until 5/29/2020 JST REOCCUR Next Due EQUIP #
/0
/2
/0
/2
/0
/2
/0
/2
/0
/2
/0
/2
/0
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/3
/2
/3
/2
/0
/2
/0
/2
/0
/2
/0
/2
/0
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/3
/2 0 0 = Job Forecast
/ = Partially C/W
1 = C/W
ANTENNA TIEDOWN STRAPS AND JACKPAD INSPECTION 24 DAILY RE035 1 0 0 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 35E4-178-1 TABLE 2-1
DAILY PERFORMANCE INSPECTION 24 DAILY RE035 1 0 0 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 31P3-2TPS75-6WC-1
UPX 37 DAILY SYSTEM CHECKS - SER # A0109 266 DAILY REA09 0 0 0 0 0 0 2UPX37-1 TBL 4-1
UPX 37 DAILY SYSTEM CHECKS - SER # C0126 266 DAILY REA26 1 0 0 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2UPX37-1 TBL 4-1
3N1 DAILY PERFORMANCE CHECK 301 DAILY C60A3 1 0 0 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 35E4-177-1 TABLE 2-1
2N1 DAILY PERFORMANCE CHECK 326 DAILY C84B2 1 0 0 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 35E4-178-1 TABLE 2-1
DISPLAY CONSOLE TURN ON/OFF 1301 DAILY RE035 1 0 0 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 31P1-2UYQ27-26WC-1
UPA 59 DAILY PREVENTATIVE MAINTENANCE 1308 DAILY RE035 1 0 0 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 31P1-2UPA59-1-1 & 2
WEATHER/ECM PERFORMANCE ROUTINE 2 7 DAY 8/3/20 RE035 1 1 1 1 0 0 0 31P3-2TPS75-6WC-1
RADAR/SIF SYSTEM TEST PERFORMANCE 50 7 DAY 8/3/20 RE035 1 1 1 1 0 0 0 31P3-2TPS75-6WC-1
I-F RECEIVER PERFORMANCE ROUTINE 51 7 DAY 8/3/20 RE035 1 1 1 1 0 0 0 31P3-2TPS75-6WC-1
HEIGHT PERFORMANCE ROUTINE 73 7 DAY 8/3/20 RE035 1 1 1 1 0 0 0 31P3-2TPS75-6WC-1
CLUTTER MAPPING PERFORMANCE ROUTINE 74 7 DAY 8/3/20 RE035 1 1 1 1 0 0 0 31P3-2TPS75-6WC-1
COMMUNICATIONS PERFORMANCE ROUTINE 273 7 DAY 8/3/20 RE035 1 1 1 1 0 0 0 31P3-2TPS75-6WC-1
POWER SUPPLY TEST PERFORMANCE ROUTINE 273 7 DAY 8/3/20 RE035 1 1 1 1 0 0 0 31P3-2TPS75-6WC-1
DISPLAY CONSOLE WEEKLY INSPECTION 1303 7 DAY 8/7/20 RE035 1 1 1 0 0 0 31P1-2UYQ27-26WC-1
ANTENNA/RECEIVER INTERFACE TEST PERFORMANCE ROUTINE 550 14 DAY 8/5/20 RE035 1 0 0 31P3-2TPS75-6WC-1
SYSTEM ORIENTATION PERFORMANCE CHECK 993 14 DAY 8/3/20 RE035 1 1 0 0 31P3-2TPS75-6WC-1
AFRADES HEIGHT EVALUATION 999 14 DAY 8/5/20 RE035 1 1 0 0 31P3-2TPS75-6WC-1
AFRADES BEACON PERFORMANCE 1038 14 DAY 8/5/20 RE035 1 1 0 0 31P3-2TPS75-6WC-1
AFRADES CLUTTER ANALYSIS 1041 14 DAY 8/5/20 RE035 1 1 0 0 31P3-2TPS75-6WC-1
AUTO SEQUENCER TEST 1207 14 DAY 8/7/20 RE035 1 1 0 0 31P3-2TPS75-6WC-1
HEAT EXCHANGER SERVICING 1270 14 DAY 8/3/20 RE035 1 1 0 35E4-177-1 TABLE 2-1
SHELTER CLEANING AND INSPECTION SERVICING 1271 14 DAY 8/14/20 RE035 1 1 1 0 35E4-177-1 TABLE 2-1
COMPRESSOR DEHYDRATOR ON/OFF RATIOS 304 28 DAY 8/14/20 RE035 1 0 31P3-2TPS75-6WC-1
FREQ GENERATOR COHO REF OUTPUT CHECK 1241 28 DAY 8/14/20 RE035 1 0 31P3-2TPS75-6WC-1
FREQ GENERATOR IF TEST TARGET AMPLITUDE CHECK 1245 28 DAY 8/14/20 RE035 1 0 31P3-2TPS75-6WC-1
ANTENNA PEDESTAL AND LEVELING JACK INSPECTION 1250 28 DAY 7/28/20 RE035 1 0 31P3-2TPS75-6WC-1
RF AND SLIP RING TEST 1253 28 DAY 8/3/20 RE035 1 0 0 31P3-2TPS75-6WC-1
MDS/FAR TEST 1254 28 DAY 8/3/20 RE035 1 0 0 31P3-2TPS75-6WC-1
AFRADES TILT SENSOR PERFORMANCE 1255 28 DAY 8/3/20 RE035 1 0 0 31P3-2TPS75-6WC-1
ANTENNA ASSEMBLY CLEANING AND INSPECTION SERVICING 1272 28 DAY 8/25/20 RE035 1 0 31P3-2TPS75-6WC-1
SHELTER CORROSION CONTROL INSPECTION AND SERVICING 1273 28 DAY 8/7/20 RE035 1 0 31P3-2TPS75-6WC-1
ANTENNA CORROSION CONTROL INSPECTION AND SERVICING 1274 28 DAY 8/25/20 RE035 1 0 31P3-2TPS75-6WC-1
ANTENNA POWER SUPPLY ENCLOSURE AIR FILTER CLEANING 1274 28 DAY 8/25/20 RE035 1 0 31P3-2TPS75-6WC-1
COMPRESSOR- DEHYDRATOR ASSEMBLY RELIEF VALVE SERVICING 1276 28 DAY 8/13/20 RE035 1 0 31P3-2TPS75-6WC-1
ANTENNA BULL GEAR LUBRICATION 1279 28 DAY 8/24/20 RE035 1 0 31P3-2TPS75-6WC-1
ANTENNA DRIVE MOTOR GEARBOX OIL LEVEL CHECK 1280 28 DAY 8/3/20 RE035 1 0 0 31P3-2TPS75-6WC-1
TUSK ASSEMBLY, JACKSCREW, AND ANTENNA YOKE LUBRICATION 1281 28 DAY 8/24/20 RE035 1 0 31P3-2TPS75-6WC-1
DISPLAY CONSOLE INSPECTION AND CLEANING 1304 28 DAY 8/7/20 RE035 1 0 31P3-2TPS75-6WC-1
3N1 MONTHLY PERFORMANCE CHECK 323 MONTHLY 8/6/20 C60A3 1 0 35E4-177-1 TABLE 2-1
Unclassified Page 15 of 42
2N1 MONTHLY PERFORMANCE CHECK 329 MONTHLY 8/6/20 C84B2 1 0 35E4-178-1 TABLE 2-1
UPX 37 QUARTERLY INSPECTION - SER # A0109 283 84 DAY 9/21/20 REA09 2UPX37-1 TBL 4-1
UPX 37 QUARTERLY INSPECTION - SER # C0126 283 84 DAY 9/21/20 REA26 2UPX37-1 TBL 4-1
TRANSMITTER OIL BREAKDOWN TEST & FILAMENT INTERRUPT CHECK PROCEDURE 1256 84 DAY 9/24/20 RE035 1 31P3-2TPS75-6WC-1
STORAGE TWYSTRON PUMP DOWN 1257 84 DAY 9/8/20 RE035 31P3-2TPS75-6WC-1
MODIFIED BEARING LUBRICATION 1282 84 DAY 8/24/20 RE035 0 31P3-2TPS75-6WC-1
ANTENNA LEG ASSEMBLY INSPECTION 1283 84 DAY 9/14/20 RE035 31P3-2TPS75-6WC-1
PROCESSOR RACK INSPECTION AND CLEANING 1285 84 DAY 9/17/20 RE035 31P3-2TPS75-6WC-1
MODULAR INTERFACE GROUP INSPECTION AND CLEANING 1289 84 DAY 9/9/20 RE035 31P3-2TPS75-6WC-1
UPX 37 SEMIANNUAL INSPECTION - SER # A0109 294 168 DAY 12/14/20 REA09 2UPX37-1 TBL 4-1
UPX 37 SEMIANNUAL INSPECTION - SER # C0126 294 168 DAY 12/14/20 REA26 2UPX37-1 TBL 4-1
TRANSMITTER LIQUID COOLANT SERVICING 1290 168 DAY 9/8/20 RE035 31P3-2TPS75-6WC-1
PPI CIRCUIT CARD INSPECTION AND CLEANING 1291 168 DAY 1/14/21 RE035 1 31P3-2TPS75-6WC-1
CONTROL MONITOR INSPECTION AND CLEANING 1292 168 DAY 1/1/21 RE035 1 31P3-2TPS75-6WC-1
ANTENNA AND SHELTER JACKS LUBRICATION 1293 168 DAY 12/16/20 RE035 1 31P3-2TPS75-6WC-1
UPA 59 PREVENTATIVE MAINTENANCE 1309 168 DAY 6/23/20 RE035 31P1-2UPA59-1-1 & 2
ANTENNA DRIVE MOTOR GEARBOX SERVICE 1294 336 DAY 7/29/20 RE035 0 31P3-2TPS75-6WC-1
PROCESSOR RACK AND CIRCUIT CARD INSPECTION AND CLEANING 1295 336 DAY 7/1/21 RE035 1 31P3-2TPS75-6WC-1
INTERROGATOR CIRCUIT CARD INSPECTION AND CLEANING 1297 336 DAY 6/29/21 RE035 1 31P3-2TPS75-6WC-1
DESICCANT CARTRIDGE REPLACEMENT 1298 336 DAY 1/14/21 RE035 31P3-2TPS75-6WC-1
CONTROL MONITOR INSPECTION, CLEANING, AND LUBE 1299 336 DAY 6/21/21 RE035 1 31P3-2TPS75-6WC-1
HIGH VOLTAGE INSULATED GLOVES TEST SET #1 367 365 DAY 5/8/21 RE035 AFI 91-203, 812.8
HIGH VOLTAGE INSULATED GLOVES TEST SET #2 396 365 DAY 5/3/21 RE035 AFI 91-203, 812.8
ANNUAL HISTORICAL RECORDS REVIEW 1320 365 DAY 2/6/21 RE035 00-20-1 PARA 10.7.4
ANNUAL FACILITY GROUNDS INSPECTION 1322 365 DAY 12/14/20 RE035
MIL-HDBK-419A PARA 2.3.1,
31-10-24 Appx B
TX HOIST 1323 365 DAY 12/9/20 RE035 31P3-2TPS75-6 Chpt 2 Sec 1
ANT & SHELTER LIFT HARDWARE INSPECTION BY NDI/ TX HOIST 68 365 DAY 12/30/00 RE035 31P3-2TPS75-6 Chpt 2 Sec 1
ANTENNA TIEDOWN STRAPS INSPECT AND REPLACE ALL 1324 720 DAY 1/28/21 RE035 31P3-2TPS75-6
INSPECT AND REPLACE ALL HYDRAULIC HOSES 1325 60 MONTH 06/06/23 RE035 31P3-2TPS75-6
5. Maintenance and Logistics Problems:
With the dissolution of the sole repair vendor for the proprietary DLS Receiver/Transmitter units, the current cache of four spare units are all that are available. Some DLSr units have been delivered, and are being used on a limited basis. The remaining DLSr delivery date is a moving target, with an anticipated delivery of August 2020.
a. Top Five Report:
b. Long Lead Report:
6. Gulf Range Tower Conditions:
a. Tower for Site RWN:
Hurricane Michael brought down tower containing this antenna.
Temporary tower installed and working well.
Contracts were awarded September 2019 for replacement of this tower.
Temporary tower moved in order for permanent replacement tower to be erected in the original location. Survey was completed, and temporary tower is running at new location.
b. Tower for Site RWW:
Hurricane Michael brought down tower containing this antenna.
Temporary tower installed and working well.
Contracts were awarded September 2019 month for replacement of this tower.
Temporary tower moved in order for permanent replacement tower to be erected in the original location. Survey was completed, and temporary tower is running at new location.
c. Tower for Site APPL:
Hurricane Michael brought down tower containing this antenna.
d. All other towers fully functional.
Top 5 Parts Ordered
NSN Part Number Nomenclature End Item Remarks
5935-00-013-9857 SMD604346-2 BACKSHELL RADAR Est Due 27 Nov 21
6840-01-309-3890 32901 INSECT REPELLENT RADAR Rec'd 28 Jul 20
5970-00-955-9976 MIL-I-46852 TAPE SHOPUSE Rec'd 20 Jul 20
6850-00-851-8725 10043943-90 DESICCANT RADAR Rec'd 28 Jul 20
6850-00-290-0042 MIL-D-3716 DESICCANT RADAR Rec'd 20 Jul 20
Top 5 Parts With Longest Lead Time
Date Ordered NSN Part Number Nomenclature QTY End Item Remarks
19-Jun-18 8010-00-490-7650 MIL-L-81352 LACQUER 1 RADAR Est Due11 Feb 21
15-Jan-19 7920-00-823-9773 AA1432 TOWEL UTILITY 4 SHOPUSE Est Due 19 Oct 20
16-Oct-19 6625-01-571-1592 N9912A-104/230 SIGNAL ANALYZER 1 EQUIPMENT Est Due 18 Feb 21
10-Dec-19 6625-01-344-9277 SMR27 SIGNAL GENERATOR 2 EQUIPMENT Est Due 31 Dec 20
16-Jul-20 5935-00-013-9857 SMD604346-2 BACKSHELL 10 RADAR Est Due 27 Nov 21
Unclassified Page 17 of 42 Distribution: A
7. Wendover Status:
a. Building 625 Control Site:
PAE continues to work infrastructure requirements per TSS requests for both a consolidated Wendover only operation and the requirements for a split configuration that would have control at Wendover and drone launches at Dugway. The 388th's contractor
JT3 will provide the WEG an estimate for their support to finish their infrastructure upgrade for the host communications system.
PAE provided locations and quantities for NIPR and SIPR drops within building 625 to aid JT3 with their estimates. Cable and jacks for phones and NIPR computers are installed between the communications room and each location within the building, so only the range infrastructure remains to be completed. The TSS is working procurement of the computers and phone instruments.
Based on the consolidated versus split operations plan, the tower needed at building 625 will be new or come from the current Wig Mountain site. The tower at 625 will support antennas for GRDCS, radios and GPS timing. The fastest and most versatile path is to purchase and install a new tower onto the newly built tower base already in place at
Wendover; a new tower would provide increased height (better coverage) at a cost of
~$20K. For either solution, additional RF cable, mounting clamps, etc. must be purchased for the move; a list of those parts was provided to the TSS, ~$6.6K.
GRDCS “New Tech” hardware and software were installed in the Wendover control site; however, the software must be updated to the newest revision in order to become operational.
On 29 April 2019, UTTR 388th personnel reported a water pipe had burst inside the wall of the mechanical room in control site building 625. The water affected several rooms including the console room and server/communications rooms. Per a report from a SPO representative from Hill, none of the WEG owned equipment was damaged and the only required repair for the operations areas is new floor coverings. The break room received more significant damage, primarily to cabinetry and carpet.
b. Launch Pad:
Compressors and power supplies must be purchased for the rails. The 82nd RAs were working this in 2018; there was a contracting hiccup, so funding short stopped the purchase.
Gantries and hoists must be purchased for the launch pad as well as a contract let to install them. PAE completed a design; the narrative for the SOW for the construction must be written before the task can go out for bids.
PAE is developing parts lists for the installation of the rails, power supplies, compressors, grounding, communications, connections for generator, etc.
Fiber equipment must be purchased and installed to provide connectivity from building
625 to the LAMS, and in turn from the LAMS to the launch pad. Much of the hardware from Dugway will be reused when maintenance activities and launch operations move from Dugway; however, several additional items will be needed due to the longer fiber cable runs.
Work continues with environmental approval contractor for the launch and maintenance areas.
Unclassified Page 18 of 42
c. LAMS Maintenance Shelter:
PAE is working a requirements document to install electrical, grounding, lightning protection, etc.
PAE is developing parts lists for the installation of a compressor, stands to mount items like fire extinguishers, eyewash, AED, etc.
PAE is working a requirements document for a secure storage area within the LAMS.
The LAMS itself was erected; however, it requires repair due to wind damage. The
WEG is working the repair effort.
d. Wendover GRDCS Sites:
The TSS is working lease efforts for the I-80 GRDCS site. This is the single most critical RF point needed to use the Wendover control whether launching from Dugway or Wendover. Site H97 is going through the environmental process. It would also be very helpful for Dugway operations with Wendover control, but it really becomes critical when launch operations move to Wendover. PAE is designing an inclusive site platform for H97.
8. GRDCS and RCS Operating Hours:
9. GRDCS and RCS Accounts Status:
10. GRDCS Accounts:
The GRDCS computers are accessed by user groups rather than by individual accounts. The users are trained for, and only granted access to, the level required to perform their assigned tasks. The three user groups and their level of access are depicted in the following chart.
Mission Support Maintenance Programming & Engineering
Administration
GRDCS 116.58 22.22 5.34 5.00
RCS 308.00 40.00 62.00 34.00
H o u rs
GRDCS (Operations) CDT (Maintenance) ROOT (Administration)
Hours 141.02 3.12 5.00
GRDCS User Accounts
Unclassified Page 19 of 42 Distribution: A
a. RCS Accounts:
The RCS computers are accessed by user groups rather than by individual accounts. The users are trained for and only granted access to the level required to perform their assigned tasks. The five user groups and their level of access are depicted in the following chart.
10. Engineering and Systems Programming Tasks:
a. Short Title: Testing and evaluation of the maximum GRDCS participant capability.
Summary: Due to the additional GRDCS hardware/software implementation of SIR 451
“Integration of NDI-AIU C-Band Beacon data into GRDCS and RCS
External Track Data” with development version 55, test flights are being supported to verify the maximum GRDCS participant capability.
Date Initiated: 24 April 2009
Completion Date (Estimated): TBD, depending on availability of mission(s).
Current Status: 85% complete.
Problems anticipated or encountered: None.
b. Short Title: Test TM connectivity with Bldg. 223 in order to evaluate the external
NDI-AIU C-Band Beacon data with Safety.
Summary: Due to the additional GRDCS hardware/software implementation of SIR 451
“Integration of NDI-AIU C-Band Beacon data into GRDCS and RCS
External Track Data” with development version 55, a connectivity test with
TM Bldg 223 is still pending to evaluate the data into GRDCS and RCS.
Date Initiated: 13 July 2009
Completion Date (Estimated): TBD, depending on TM shop and testing results.
Current Status: 0% complete.
Problems anticipated or encountered:
First test on 13 July 2009 was not successful. Bldg. 223 personnel could not start the program. More work on their side is required.
83rd 82nd ROOT USAF_Administr ator
Wetstone MSCT
Hours 28.00 30.00 22.00 44.00 352.00 352.00
RCS User Accounts
Unclassified Page 20 of 42 Distribution: A
c. Short Title: User software (increment-13, based on v60.4) installation for the QF-16 DR2
Hardware Changes (SIR 843).
Summary: In process of supporting ground and test flights for the QF-16 DR2 Hardware
Changes with Autopilot v1.7 software.
Date Initiated: 29 June 2018
Completion Date: July 2020
Current Status: Flight testing is complete at Hollowman. SIR 843 scheduled to be included in v62 software upgrade.
Problems anticipated or encountered: None at this time.
d. Short Title: Software installation of GRDCS Software V62.0 (29Mar19).
Summary: In process of supporting DT testing for v62.0 for the software upgrade.
Date Initiated: 29 March 2019
Completion Date (Estimated): TBD
Current Status: Demo Phase; Start date 28 Feb 2019 with video (SIR844) and .sml file
(SIR878). Continued on 29 May 19, with SIR 739, 822, 874, 849, 877, and 674.
Supported DT phase at Eglin 21-22 January 2020, 18-19 & 26 February 2020.
Problems anticipated or encountered: None at this time.
11. Special Projects:
a. In process of enhancing locally developed ‘safe flight script’ to handle QF-16 telemetry during the different phases of the safe flight profile (10% complete).
b. Supporting Wendover system evaluation as a first look of the new hardware (console and computer) and software to include local RF environment. (Ongoing effort at this time, no
ETA available yet).
12. ATIS Mission Support (Over-the-Horizon Airborne Relays using platform aircraft):
a. None during this reporting period.
Unclassified Page 21 of 42 Distribution: A
TAB 4 – MAINTENANCE DATA SYSTEM ANALYSIS (MDSA)
METRICS
1. MDSA Metrics:
a. Abort Rate: SDS Criteria FSAT/SSAT < 12%
FSAT = 5.2% (0 AAB + 5 GAB with 97 sorties flown and 0 chargeable GAB lines)
((0 / 97) + (5 / (97 + 0))) x100) (2 non-chargeable GAB lines on SAFE flights)
CADC
FLCS
FTIT gauge
Engine fault
Centerline fuel tank read zero
SSAT = 0.0% (0 AAB + 0 GAB with 11 sorties flown and 0 GAB lines)
((0 / 11) + (0 / (11 + 0))) x100) (1 non-chargeable AAB for engine failure)
b. Repeat/Recur Rate: SDS Criteria FSAT/SSAT < 7%
FSAT = 0.0% (0 Repeat + 0 Recur with 15 PRDs) ((0 / 15) x 100)
SSAT = 0.0% (0 Repeat & 0 Recur with 1 PRDs) ((0 / 1) x 100)
c. Cannibalization Rate: 5.6% (6 Canns with 108 Sorties Flown) ((6 / 108) x 100)
d. Data Integrity Error Rate: SDS Criteria - 98% of correctable errors corrected
100.0% (12 Errors with 4 Uncorrectable and 8 Corrected) (8 / (12 - 4)) (2,036 DDRs checked)
e. Break Rate = 5.6% (6 Code 3s with 108 Sorties Flown) ((6 / 108) x 100)
f. Primary Aerospace Vehicle Authorized (PAA) vs. Possessed (PP) Rate:
FSAT = 100.0% (36 assigned with 36 possessed, 50 baseline and 0 CLIN 4/6 inventory at EOM) ((36 / 36) x 100)
SSAT = 100.0% (44 PAA with 44 possessed and 0 CLIN4/6 inventory at EOM) ((44 /
44) x 100)
g. FSAT Mission Success Rate: SDS Criteria - 95%, Critical Standard – 98%
100.0% (121 Sorties attempted with 97 successful and 24 non-chargeable non-successful) ((97 / (121 - 24)) x 100)
h. SSAT Mission Success Rate: SDS Criteria - 95%, Critical Standard – 98%
100.0% (21 Sorties attempted with 11 successful and 10 non-chargeable non-successful) ((11 / (21 - 10)) x 100)
Unclassified Page 22 of 42
2. Maintenance and Flying Schedule Effectiveness (MSE and FSE)
a. MSE = 68.8% (522 points scheduled with 359 complied with) ((359 / 522) x 100)
b. FSE = 53.0% (108 sorties flown, with 32 sorties cancelled, 6 sortie added and 63 total
FSE deviations) (((134 - 63) / 134) x 100)) (Of the 63 chargeable deviations, 1 was attributed to maintenance.)
The main driver was 32 Cancels.
Add Lines = 6 (2 Project, 4 Ops)
Add Tails = 1 (1 Mx)
Cancels = 32 (15 Project, 11 Wx, 4 Ops, 2 ATC)
Early T/O = 8 (5 Ops, 1 Project, 2 Airspace)
Late T/O = 16 (1 Ops, 7 Project, 5 Wx, 3 Airspace)
GAB Lines = 0
3. Narratives:
Ground & Air Aborts
a. FSAT – During July, there were 5 ground aborts at Tyndall and no aborts at Holloman.
(1) There were hardly any abort trends this month. There were no aircraft with multiple aborts, there were no systems with multiples, and only one aircraft had recorded a previous abort similar to this month’s abort.
(a) That aircraft was AF029, which aborted for FTIT Gauge and had an FTIT abort in March 2018. This brings it up to 9 aborts as a QF-16, the 21st highest in the program.
(b) One of the other 4 aborting aircraft had 3 unrelated previous aborts, 2 had 1 previous abort and AF068 had none.
(2) The numerical breakouts for July were:
(a) The 5 aborts involved 5 QF-16Cs at Tyndall.
(b) All 5 aborts occurred on O&M flights, all manned.
(c) The weekly abort distribution was 2 on Mondays, 2 on a Tuesday and 1 on a
Thursday. Four aborts occurred on scheduled morning sorties and 1 on an afternoon sortie.
(d) Four sorties were lost to aborts. Two were on SAFE flights; on the other 2, a spare was available but not used because the lines were weather-cancelled.
Unclassified Page 23 of 42 Distribution: A
b. SSAT – Aircraft 17-0604 experienced an air abort for Engine Fail, ruled not chargeable to the contractor by AMIC.
Date Base AF # Reason Corrective Action
FSAT
2 Jul TAFB 56 CADC R2 CADC
14 Jul TAFB 48 FLCS R2 FLCC
14 Jul TAFB 29 FTIT gauge In work
20 Jul TAFB 68 Engine fault In work
27 Jul TAFB 50 Centerline fuel tank read 0 R2 tank
SSAT
16 July TAFB 604 Engine fail In work
TAB 5 – TECHNICAL REPORT STATUS
Negative this report period.
Unclassified Page 24 of 42 Distribution: A
TAB 6 – QUALITY CONTROL (QC) SUMMARY REPORT
1. Full-Scale - Tyndall:
a. Seventeen Quality Verification Inspections, nineteen SI, eight Personnel Evaluations, and 1
Audit were accomplished. Forty-five inspections passed. There were zero failures this period.
One minor consisting of Training Record Documentation.
b. Problem Area: None
c. PQDR/AIDRs: Seven this report period.
DR control # Date CAT Serial # Acft Noun
FA4881-20-0039 7/15/2020 PQDR QF026 Liquid Oxygen Converter
FA4881-20-0041 7/22/2020 PQDR 0108/QF056 Universal Replacement Autopilot (URAP)
d. AFTO Form 22’s: None this report period.
e. TODO: Fifty-three technical order changes and revisions were received this period.
f. Impoundments: None this report period.
g. FOD/DOP/Lost item: One this report period
2. Full-Scale - Holloman:
a. Five Quality Verification Inspections, nine Special Inspections, three audits, and five
Personnel Evaluation were accomplished. Twenty-two inspection/audits passed.
b. Problem Areas: None this report.
c. PQDRs: One this report period.
1) FA4810-19-0001 Canopy Sill Nut Channel (NULLO) PQDR
Parent FA4810-19-0005 Canopy Sill Nut Channel (NULLO) PQDR Child (Subordinate to FA4810-19-0001)
d. AFTO Form 22’s: None this report period.
e. TODO: Reviewed 66 Technical Order changes/revisions.
f. Impoundments: One this report period.
g. FOD/DOP/Lost item: None this report period.
Unclassified Page 25 of 42
3. Subscale:
a. Sixteen Quality Verification Inspections, four special inspections, and four personal evaluations. Twenty-four inspections passed. Zero fails this report period. There were two minors consisting of Forms Doc and CTK management
b. Problem Areas: None this report period.
c. PQDRs: None this report period.
d. AFTO Form 22s: None this report period.
e. TODO: Seven technical order change and revision received this period.
g. DOP/Lost Item: None this report period.
4. GRDCS - Tyndall:
a. Four personal evaluation and one special inspections were accomplished this period. Five inspections passed. Zero discrepancies this period.
b. AFTO Form 22s: None this report period.
c. PQDRs: None this report period.
d. TODO: Two technical orders change and revision this period.
e. Problem Areas: None this report period.
5. ESH - Tyndall:
a. Seven inspections this period. Seven passed. Zero discrepancies this period.
6. ESH - Holloman:
a. One was accomplished this month. Zero Failed.
Unclassified Page 26 of 42 Distribution: A
7. Publications and Forms: No contractual impacts this period. See CDRL A009, Master
Document List.
0.7
0.8
0.9
TYN HMN SSAT RIS ESH
QA Inspection Pass Rate May - July 2020
May
June
July
Unclassified Page 27 of 42 Distribution: A
TAB 7 – RIS MAINTENANCE ANALYSIS REQUESTS
1. ELECTRO-MAGNETIC INTERFERENCE (EMI):
No EMI reported this period.
2. RIS MAINTENANCE ACTIONS:
1.
RIS NUMBER: DISCREPANCY: ACTION TAKEN: MISSION IMPACT:
183020001 CARRY OVER:
All poles holding Antenna systems at B1801 down due to Hurricane Michael.
N/A No mission impact noted.
MAINT. AREA:
RIS
START DATE:
20181029
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
DISCR. HOURS: EQUIPMENT MAKE: EQUIPMENT MODEL: EQUIPMENT S/N:
N/A N/A N/A N/A
Unclassified Page 28 of 42
RIS NUMBER: DISCREPANCY: ACTION TAKEN: MISSION IMPACT:
183020002 CARRY OVER:
Runway West tower down due to Hurricane Michael.
Temporarily installed mobile DLS trailer at site.
No mission impact noted.
MAINT. AREA:
RIS
START DATE:
20181029
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
183020003 CARRY OVER:
Runway North tower down due to Hurricane
Michael.
Temporarily installed mobile DLS trailer at site.
No mission impact noted.
MAINT. AREA:
RIS
START DATE:
20181029
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
Unclassified Page 29 of 42 Distribution: A
RIS NUMBER: DISCREPANCY: ACTION TAKEN: MISSION IMPACT:
183020007 CARRY OVER:
ACDS Missile and Drone, Primary and Backup antenna systems down due to Hurricane Michael.
(See RIS# 183020001)
Temporarily installed ACDS
Missile Primary and Backup antennas on Tower 1802.
Temporarily installed Drone
Primary and backup antennas on Tower B1830.
No mission impact noted.
MAINT. AREA:
RIS
START DATE:
20181029
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
183020011 CARRY OVER:
Runway west video is down due to Hurricane
Michael. (See RIS#
183020002)
N/A No mission impact noted.
MAINT. AREA:
RIS
START DATE:
20181029
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
Unclassified Page 30 of 42
190980001 CARRY OVER:
RCS MULTI (RBZ94)
took a lightning strike.
Job opened with COMM
Focal Point (283-4896).
Put GRDCS Multi in RCS
Multi’s slot.
None
MAINT. AREA:
COMM
START DATE:
20190408
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
DISCR. HOURS: BRAND: EQUIPMENT MODEL: EQUIPMENT S/N:
192120101 CARRY OVER:
GSM Transceiver
Communication Error during attempted Self-
Calibration.
IAW w/ T.O., checked all connections. Rebooted system, symptom persisted.
Reported to SPO, awaiting direction. SPO picked up unit for delivery to MSI for repair. Received repaired unit from MSI 29 July
2020. Unit pending calibration and full operational check.
None
MAINT. AREA:
DLS
START DATE:
20190731
STOP DATE:
N/A
REPAIRED BY:
D. Holmes
MAN HOURS:
N/A
COST:
N/A
N/A MSI 915 DTS 003
Unclassified Page 31 of 42
200220001 No receive on
WETSTONE GATR-A
radio (288.5).
Opened a remedy ticket.
The radio has been flagged obsolete. There are no parts available.
No mission impact noted.
MAINT. AREA:
COMM
START DATE:
20200122
STOP DATE:
20200731
REPAIRED BY:
J.TINSLEY
MAN HOURS:
0.5
COST:
N/A
4583.5 N/A N/A N/A
200220101 CARRY OVER:
60% data quality reported on DLSr at
SUBW
Performed DLSr FAT, Oscillator Calibration, and
Pulses Present tests, all tests passed except for
“PA Enable.” RMA requested from MSI.
None
MAINT. AREA:
DLS
START DATE:
20200122
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
N/A MSI DLSr 051
Unclassified Page 32 of 42
200240101 CARRY OVER:
No output reported from DLSr at RWER
No pulses present, oscillator will not calibrate, no output.
RMA requested from
MSI.
None
MAINT. AREA:
DLS
START DATE:
20200124
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
N/A MSI DLSr 030
201150001 CARRY OVER:
TriCaster will not boot.
Awaiting RMA from
NewTek.
No mission impact noted.
MAINT. AREA:
VIDEO
START DATE:
20200424
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
Unclassified Page 33 of 42
201190001 CARRY OVER:
1801 Building UPS has
Temperature alarm and cycles on and off.
Awaiting for GE tech rep to arrive for system troubleshooting.
Tech replaced parts. No fix.
No mission impact noted.
MAINT. AREA:
1801 UPS
START DATE:
20200428
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
201560101 DLS failed in flight, E-9
Tail 048.
Removed and replaced power supply resulting in good bench checks, unit failed in ground testing.
Troubleshot to faulty RT
Unit, no spares available.
Unit decommissioned. Job
Closed.
None
MAINT. AREA:
DLS
START DATE:
20200124
STOP DATE:
20200717
REPAIRED BY:
D. Holmes
MAN HOURS:
8.0
COST:
N/A
552 IBM DLS 098
Unclassified Page 34 of 42
201760001 TDF 19 interface board not recognized by computer.
Removed and replaced
RAID controller.
Operational checks good.
No mission impact noted.
MAINT. AREA:
ACS
START DATE:
20200623
STOP DATE:
20200701
REPAIRED BY:
D.CONTRERAS
MAN HOURS:
1.5
COST:
N/A
187.5 N/A N/A N/A
201880001 D3 UHF-2 has extremely weak receive audio.
The radio has been flagged obsolete. There are no parts available.
No mission impact noted.
MAINT. AREA:
COMM
START DATE:
20200706
STOP DATE:
20200731
REPAIRED BY:
N/A
MAN HOURS:
0.5
COST:
N/A
594.5 N/A N/A N/A
Unclassified Page 35 of 42 Distribution: A
RIS NUMBER: DISCREPANCY: ACTION TAKEN: MISSION IMPACT:
201880002 Roadguard radio interface box will not power on.
Removed and replaced radio interface box with parts on hand.
Operational checks good.
No mission impact noted.
MAINT. AREA:
COMM
START DATE:
20200706
STOP DATE:
20200706
REPAIRED BY:
J.TIN/E.ROS
MAN HOURS:
1.0
COST:
N/A
0.5 N/A N/A N/A
201990001 BC3 TDF 10 lost second monitor output.
Removed and replaced video card with parts on hand.
Operational checks good.
No mission impact noted.
MAINT. AREA:
ACS
START DATE:
20200717
STOP DATE:
20200717
REPAIRED BY:
K.GIAWASHI
MAN HOURS:
2.0
COST:
N/A
2.0 N/A N/A N/A
Unclassified Page 36 of 42
202020001 ACDS Missile Left has fault in Exciter or HPA.
Removed and replaced converter at wind site.
Operational checks good.
No mission impact noted.
MAINT. AREA:
AATTCS
START DATE:
20200720
STOP DATE:
20200720
REPAIRED BY:
A.BIG/B.WIE
MAN HOURS:
4.0
COST:
$180.00
4.0 B&B 26750 N/A
202020002 DLSr at Runway West site failed to respond.
Removed and replaced
DLSr with part on hand.
Operational checks good.
No mission impact noted.
MAINT. AREA:
DLS
START DATE:
20200720
STOP DATE:
20200720
REPAIRED BY:
D.HOL/B.WIE
MAN HOURS:
3.0
COST:
N/A
3.5 N/A N/A N/A
Unclassified Page 37 of 42 Distribution: A
RIS NUMBER: DISCREPANCY: ACTION TAKEN: MISSION IMPACT:
202040001 Received repaired
ACDS HPA from depot.
Reinstalled repaired unit.
Operational checks good.
No mission impact noted.
MAINT. AREA:
UHF DESTRUCT
START DATE:
20200722
STOP DATE:
20200722
REPAIRED BY:
A.BIG/K.GIA
MAN HOURS:
2.0
COST:
N/A
1.0 N/A N/A N/A
202040101 OPEN: No data throughput for DLSR
Test on bench with 915
DTS IAW T.O. All tests failed. RMA requested and received from MSI.
None
MAINT. AREA:
DLS
START DATE:
20200722
STOP DATE:
REPAIRED BY:
MAN HOURS:
COST:
MSI DLSR 019
Unclassified Page 38 of 42
202120001 There are multiple switch covers broken on
AATTCS consoles 1 and
3.
Removed and replaced switch covers.
Operational checks good.
No mission impact noted.
MAINT. AREA:
AATTCS
START DATE:
20200730
STOP DATE:
20200730
REPAIRED BY:
B.WIEBKE
MAN HOURS:
2.0
COST:
N/A
2.0 N/A N/A N/A
Unclassified Page 39 of 42
TAB 8 – FACILITIES OPEN WORK REQUESTS
TOP FIVE WORK REQUESTS
TOP 5
JOB NO.
BLDG WORK DESCRIPTION STATUS DATE
SUBMITTED
38912
1801 Repair raised floor in room 114. Note:
Submitted by the 81st Range Control Squadron.
CES/CEO
REVIEW
25 Jan 18
39890 239 Repair 239 above-ground storage tank CES/CENPD
REVIEW
13 Nov 19
8513 LP Gate Repair CES
REVIEW
31 Jul 19
38125
45 Pave access road/checkpoint. CES/CENPD
REVIEW
1 Apr 15
59188
Extend existing permanent static ground system inside buildings.
CES/CENM
7 Aug 13
Full Scale Facilities – Building Manager – S. Davis
JOB
NO.
BLDG WORK DESCRIPTION STATUS DATE SUBMITTED
38125 45 Pave access road/checkpoint.
CES/CENPD
REVIEW
1 Apr 15
59222 45 Roadway Improvement
CES/CENP
REVIEW
21 Nov 13
E2953 9310
Plumb emergency eyewash drain to the building exterior. Install shower pans under emergency showers in
Bays 1 and 3 and plumb to drain outside.
CES/FM
PLUMBER
AWT
SCHEDULE
11 Aug 17
38672 9310 Install 26 electrical outlets.
CES/CENP
REVIEW
24 Jan 17
G-0425 9310 Install ice maker
CES/CENPD
IN WORK
26 Jul 19
6275 98 Install two 220 outlets on west wall of main maintenance room.
CES/ALOP
SUBMITTED
21 Jul 20
G6173 9306 Hook air compressor to 220 power. CES/ALOP
SUBMITTED
15 Jul 20
G6084 9306 Secure shop equipment to floor.
CES/ALOP
SUBMITTED
9 Jul 20
Unclassified Page 40 of 42
Range Instrumentation Systems Facilities – Building Manager - R. Williams
JOB NO. BLDG WORK DESCRIPTION STATUS DATE
SUBMITTED
38912 1801 Repair raised floor in room 114. Note:
Submitted by the 81st Range Control Squadron.
CES/CEO
REVIEW
25 Jan 18
39126 9401 Paint facility. Paint samples collected by CE for Lead
Based Paint testing.
CES/ALOP
SUBMITTED
16 Aug 18
39211 9350 Replace galvanized communication tower due to
Hurricane Michael damage
CES/ALOP
SUBMITTED
13 Dec 18
39210 9349 Replace galvanized communication tower due to
Hurricane Michael damage
CES/ALOP
SUNMITTED
13 Dec 18
39209 1810 Replace galvanized communication tower due to
Hurricane Michael damage
CES/ALOP
SUBMITTED
13 Dec 18
39297 9317 R&R 20’ Tower Ladder. Reinstall LPS
(Ladder Portion Complete)
CES/ALOP
SUBMITTED
(In Progress)
10 Jan 19
39389 9401 R&R Perimeter Security Fence CES/ALOP
SUBMITTED
31 Jan 19
40127 9352 Replace 148’ communications tower. CES/ALOP
SUBMITTED
7 Jul 20
Unclassified Page 41 of 42
Sub Scale Launch Pad – Building Manager - B. Prince
JOB
NO.
BLDG WORK DESCRIPTION STATUS DATE
SUBMITTED
34672 8500 Area Paint buildings and floors. CES/CEPD
REVIEW
24 Jan 06
37441 8519 Install pavement southwest of building.
Project No. XLWU142051D
CES/CENPD
CONTRACT
15 Jun 12
59188 8519
Extend existing permanent static ground system inside buildings.
CES/CENM
REVIEW
7 Aug 13
C7092 8519 Install emergency eyewash/shower stations in the north and south bays.
CES/PLUMER
IN PROGRESS
24 Nov 15
F2434 8525
Rail #4
Repair rail #4 hoist electrical power conduit. CES/ALOP
SUBMITTED
30 Aug 18
8513 LP Gate Repair CES/CEPD
Review
30 Jul 19
G0555 8519 Overhead Light fixture repair CES
Submitted
30 Jul 19
Sub Scale Maintenance Facilities – Building Manager - D. Jacobs
JOB NO. BLDG WORK DESCRIPTION STATUS DATE
SUBMITTED
39890 239 Repair 239 above ground storage tank CES/CENPD
13 Nov 19
TAB 9 – CONTRACTOR PROGRAM MANAGEMENT CONCERNS
The lack of aircraft deliveries from Boeing is impacting our overall aircraft fleet numbers as well as our ability to manage aircraft hours. Once Boeing has worked through production issues, we expect the number of aircraft deliveries will increase past the 2 deliveries/month as called out in the PWS.
This will impact PAE’s ability to meet Safe Flight time requirements and create a backlog of aircraft awaiting Safe Flights.
Unclassified Page 42 of 42
All the cleanup of failed data documentation and maintenance processes in aircraft generation from
AMARG and/or Boeing continues to fall on PAE for correction prior to SAFE flight.
Failure to receive delivery aircraft is impacting available manned flyers (Tyndall & Holloman).
Correspondingly, NULLO fleet health/quantity is becoming an issue. Expect continued movement of aircraft to and from Holloman and early De-Man of flyers to keep Tyndall’s NULLO fleet minimally populated.
Severe damage to most of our facilities is causing many workarounds and much turmoil. PAE is managing the situation the best we can. Construction of temporary facilities is almost complete and for the most part the facilities are adequate with a few workarounds.
A major concern is safely moving into temporary facilities while still complying with all AF regulations governing the safe handling and storage of explosive items. Also, we are being told all 5 of the temporary facilities (chute shop & SSAT Mx tents) will have to move. There is a major concern of meeting mission support while moving all 5 tents.