This monthly summary report outlines maintenance and operations for aerial targets and range instrumentation systems. Key details include manned and unmanned sorties flown from Tyndall and Holloman Air Force bases with periodic deployments to Utah Test and Training Range, as well as maintenance actions, quality inspections, recurring issues, facilities work requests, and program concerns. The report provides performance metrics and issues updates for full-scale and subscale aerial targets, the Range Instrumentation System including radar and communications equipment, and support facilities.
View the file
Other files for this federal contract opportunity
Show all 50
Aerial Targets III FY23 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AERIAL TARGETS MONTHLY SUMMARY FEBRUARY 2020
Unclassified Page 1 of 40 Distribution: A
Aerial Targets Monthly Contract Summary Report – CDRL A001
Contract Number FA4890-15-C-0018
1 – 29 February 2020
Prepared for:
Acquisition Management and Integration Center
Langley AFB, Virginia
Prepared by:
PAE Aviation and Technical Services, LLC
1311 Florida Avenue
Tyndall AFB, Florida
David Olson
Program Manager
Aerial Targets Program
UNCLASSIFIED
Distribution Limitation: A
Unclassified Page 2 of 40
TABLE OF CONTENTS
Tab 1A – FULL-SCALE AERIAL TARGETS – TYNDALL AFB, FL
Tab 1B – FULL-SCALE AERIAL TARGETS – HOLLOMAN AFB, NM
Tab 2 – SUBSCALE AERIAL TARGETS – TYNDALL AFB, FL
Tab 3 – RANGE INSTRUMENTATION SYSTEM (RIS) O&M
Tab 4 – MAINTENANCE DATA SYSTEM ANALYSIS (MDSA) METRICS
Tab 5 – TECHNICAL REPORT STATUS
Tab 6 – QUALITY CONTROL (QC) SUMMARY REPORT
Tab 7 – RIS MAINTENANCE ANALYSIS REQUESTS
Tab 8 – FACILITIES OPEN WORK REQUESTS
Tab 9 – CONTRACTOR PROGRAM MANAGEMENT CONCERNS
Unclassified Page 3 of 40
TAB 1A – FULL-SCALE AERIAL TARGETS – TYNDALL AFB, FL
1. SORTIES SCHEDULED:
Note: Off-station sorties reported in this summary are credited to the location that possessed the aircraft, regardless of who launched or recovered the aircraft.
2. MISSIONS FLOWN:
QF-16 NULLO:
Mission Symbol Mission Project Supported # Missions FYTD
O5ZZ AMRAAM SIP AMRAAM 2
All O5ZZ 2
Sub Total 2 10
QF-16 MANNED:
Mission Symbol Mission Project Supported # Missions
All O3ZZ 0 2
O5ZZ AMRAAM SIP AMRAAM 1
O5ZZ DC-2 Chase O&M 1
O5ZZ EW/E3 Pod Test EW/E3 Pod 1
O5ZZ SAFE O&M 1
All O5ZZ 4 70
O6ZZ Chase WSEP WSEP 1
O6ZZ Chase DC-2 O&M 1
O6ZZ Checkride O&M 3
O6ZZ CT O&M 29
O6ZZ DACT O&M 2
O6ZZ DC-2 O&M 1
O6ZZ FCS O&M 6
O6ZZ SEFE O&M 3
O6ZZ SP-x O&M 3
All O6ZZ 49 246
O8ZZ CT O&M 1
All O8ZZ 1 3
Sub Total 54 308
Grand Total 56 318
QF-16 FEB 20 FYTD
Scheduled 82 378
Canceled 26 55
Successful Flown 56 316
Ground Aborts 5 30
Air Aborts 0 2
Total Flown 56 318
Unclassified Page 4 of 40
3. TOTAL HOURS FLOWN:
Mission Symbol Hours FYTD
O5ZZ 1.5 6.7
Sub Total 1.5 6.7
Hours FYTD
O3ZZ 0.0 3.2
O5ZZ 5.7 88.4
O6ZZ 63.4 312.3
O8ZZ 1.0 3.9
Sub Total 70.1 407.8
Grand Total 71.6 414.5
4. MISSIONS CANCELED:
Date
MDS
AF#
Msn
Sym
Mission
Reason
6 Feb QF-16C 26 O6ZZ X/C Weather
6 Feb QF-16C 22 O6ZZ X/C Weather
6 Feb QF-16C 48 O6ZZ X/C Weather
6 Feb QF-16C 30 O6ZZ Chase Weather
12 Feb QF-16C 52 O6ZZ CT Weather
12 Feb QF-16C 53 O6ZZ CT Weather
12 Feb QF-16C 31 O6ZZ CT Weather
12 Feb QF-16C 52 O6ZZ I/M Check Weather
12 Feb QF-16C 53 O6ZZ SEFE Weather
13 Feb QF-16C 52 O6ZZ SP-5 Weather
13 Feb QF-16C 53 O6ZZ SEFE Weather
13 Feb QF-16C 31 O6ZZ CT Weather
13 Feb QF-16C 31 O6ZZ CT Weather
13 Feb QF-16C 22 O6ZZ CT Weather
18 Feb QF-16C 26 O6ZZ Checkride Weather
18 Feb QF-16C 31 O6ZZ SEFE Weather
18 Feb QF-16C 30 O6ZZ CT Weather
20 Feb QF-16C 48 O6ZZ DACT Weather
20 Feb QF-16C 50 O6ZZ DACT Weather
20 Feb QF-16C 52 O6ZZ DACT Weather
25 Feb QF-16C 31 O6ZZ CT Ops
27 Feb QF-16C 33 O5ZZ AMRAAM SIP Project
27 Feb QF-16A 35 O5ZZ AMRAAM SIP Project
Unclassified Page 5 of 40 Distribution: A
28 Feb QF-16C 30 O5ZZ Chase Project
28 Feb QF-16C 33 O5ZZ AMRAAM SIP Project
28 Feb QF-16A 35 O5ZZ AMRAAM SIP Project
5. ABORTS – GROUND AND AIR:
Date Type
Abort
MDS AF
Msn
Sym
Mission Reason
10 Feb GAB QF-16C 26 O6ZZ Chase Hydraulics
10 Feb GAB QF-16C 48 O5ZZ EW/E3 Pod Test EPU
21 Feb GAB QF-16C 52 O6ZZ CT Engine
24 Feb GAB QF-16C 22 O6ZZ FCS FTIT
27 Feb GAB QF-16C 30 O6ZZ SP-5 Battery
6. MAINTENANCE AND LOGISTICS PROBLEMS:
a. Maintenance:
(1) QF-16:
(a) AF055 Awaiting SAFE
(b) AF057 Acceptance In Work
(2) AGE/Support Vehicles:
(a) QF-16 AGE and Support/Test Equipment
1. Procurement of AGE equipment, support/test equipment is continuing.
(b) Stock listed and commercially procured AGE maintenance equipment and tools purchasing in work.
b. Logistics:
(1) Long lead-time (MICAP) on F-16A components is negatively impacting the ability to generate aircraft.
(2) Post Hurricane Michael supply needs are being met via Tyndall AFB and Eglin AFB.
Delays in processing/receiving parts are continual.
(3) Received/populating two new CONEX storage containers with tools/equipment due to hurricane damage to previous storage buildings.
Unclassified Page 6 of 40
7. WASHES:
a. Washes Accomplished in February 2020:
WEEK ENDING AF#
30 Day: 7 February 042, 031, 048, 038, 024
14 February 052, 040, 030, 032, 050
21 February 053, 026, 033
28 February 035, 022, 023
b. Washes Not Accomplished & Reasons:
AF021 – Maintenance priority
AF027 – Maintenance priority
AF051 – In fuel barn – Fuel flow indicator
c. Wash Schedule for March 2020:
WEEK ENDING AF#
30 Day: 6 March 027, 021, 042, 038, 031, 048, 052, 057
13 March 051, 024, 040, 030
20 March 032, 050, 055, 053
27 March 026, 035, 023, 022
8. REPEAT/RECURRING DISCREPANCIES:
Date MDS AF
R/R Discrepancy Corrective Action
27 Feb QF-16C 31 Fuel flow indicator reads below normal values Fuel flow transmitter on order
9. RECOMMENDATIONS: Negative this report period.
10. SPECIAL PROJECTS/SPECIAL INTEREST: Negative this report period.
Unclassified Page 7 of 40
TAB 1B – FULL-SCALE AERIAL TARGETS – HOLLOMAN AFB, NM
Note: Off-station sorties reported in this monthly summary are credited to the location that possessed the aircraft, regardless of who launched or recovered the aircraft.
Mission Symbol Mission Project Supported # Missions FYTD
All O5ZZ
Sub Total 0
QF-16 MANNED:
Mission Symbol Mission Project Supported # Missions FYTD
All O3ZZ Acft Delivery Paint RTB/Input 2 7
All O4ZZ 0
O5ZZ
All O5ZZ 31
O6ZZ C/T Training 19
O6ZZ WITS Training 2
All O6ZZ 21 97
All O8ZZ 1
Grand Total 23 136
05ZZ 0.0 0.0
NULLO sub Total
Hours FYTD
O3ZZ 3.5 12.2
O4ZZ 0.0 0.0
O5ZZ 0.0 49.7
O6ZZ 31.4 144.7
QF-16 FEB 20 FYTD
Scheduled 29 147
Canceled 6 11
Successful Flown 23 136
Ground Aborts 0 9
Air Aborts 0 0
Total Flown 23 136
Unclassified Page 8 of 40 Distribution: A
O8ZZ 0.0 1.3
Sub Total 34.9 207.9
Grand Total 34.9 207.9
Date MDS AF# Msn
Sym
Mission Reason
5 Feb QF-16C 045 O6ZZ CT Weather
5 Feb QF-16C 046 O6ZZ CT Weather
10 Feb QF-16C 047 O6ZZ CT Weather
10 Feb QF-16C 049 O6ZZ CT Weather
11 Feb QF-16C 049 O6ZZ CT Weather
11 Feb QF-16C 047 O6ZZ CT Weather
Abort
MDS AF# Msn
Sym
Mission Reason
Negative this report period
a. Maintenance: We were without AF029 the entire month due to replacement engine needed. It’s been ordered and shipment is in work. Additionally, AF028 was also NMC for the last half of the month due to a replacement engine on order for an expired Time Change item. Finally, we delivered AF049 to Hill AFB for full paint and accepted AF047 that had just completed full paint.
b. Logistics: New Items: Negative this report period.
7. WASHES:
Washes Accomplished: AF046
Washes Not Accomplished & Reasons: AF014 - NULLO conversion in-work
AF029 - Awaiting Engine and panels
AF028 – F-1 Cavity Fuel Leak
Date MDS AF# R/R Discrepancy Corrective Action
Negative this report period
9. RECOMMENDATIONS: Negative this report period.
Unclassified Page 9 of 40
10. SPECIAL PROJECTS/SPECIAL INTEREST: Negative this report period.
TAB 2 – SUBSCALE AERIAL TARGETS – TYNDALL AFB, FL
Note: Off-station sorties reported in this summary are credited to the location that possessed the aircraft, regardless of who launched or recovered the aircraft.
BQM-167A
Mission Symbol Mission Project Supported #
Missions
FYTD
O5ZZ F-15 OFP/ CTF F-15 OFP/ CTF 0 2
O5ZZ APS TEST APS TEST 1 1
O5ZZ F16 Cruise Missile
Defense Test
F16 Cruise Missile
Defense Test
0 1
O5ZZ AMRAAM SIP AMRAAM SIP 1 2
O5ZZ AIM 9X AIM 9X 0 5
O5ZZ AMR PHS4 AMR PHS4 0 1
O5ZZ WSEP WSEP 3 13
Total 4 25
BQM-167A FEB 20 FYTD
Scheduled 6 40
Canceled 2 14
Successful Flown 4 25
Ground Aborts 0 3
Air Aborts 0 0
Total Flown 4 25
Unclassified Page 10 of 40
BQM-167A
O5ZZ 3.0 20.9
Total 3.0 20.9
Date
MDS
Tail #
Msn Sym
Mission
Reason
None
Abort
MDS Tail# Msn
Sym
Mission Reason
a. Hurricane damage to building 256’s roof continues to impact Mx activity and available storage space due to the amount of water intrusion into the hangar. Maintenance time is lost to cleaning it up after any rain. Temporary Mx facilities have been erected but are awaiting a floor covering change-out before they can be moved into.
b. Minor adjustments to the established Forward Supply point continue, but presently no new or major impacts to target generation.
c. The three temporary facilities for SSAT Mx and the two for the chute shop have been identified as “Not safe for Mx personnel during a 5 MILE LIGHTNING LIGHT” and will require evacuation during this entire period. PAE has engaged the 53 WEG leadership for possible alternatives that would negate the need to leave the facilities. Additionally, we have asked for a location to be identified for Mx to go to during this time.
7. CORROSION CONTROL INSPECTION:
a. Launch Pad Corrosion Control Maintenance: Routine corrosion control is being accomplished on all applicable support equipment.
b. Launch Rail Gantry systems 1, 2, 5, & 6 are showing signs of severe corrosion (they were installed in 1975). Presently, they all are serviceable. However, their replacements should be programmed / considered in the near future. NOTE: Gantries on rails 3 & 4 are newer and will not require replacement any time soon.
Unclassified Page 11 of 40
Date MDS Tail# R/R Discrepancy Corrective Action
9. RECOMMENDATIONS: None
10. SPECIAL PROJECTS: None
Unclassified Page 12 of 40 Distribution: A
TAB 3 – RANGE INSTRUMENTATION SYSTEM (RIS) O&M
1. Tellabs Switch and Data/Comm. Operational Availability:
Tellabs Switch: 100% Available
Data/Comm. Circuits: 100% Available
2. Mission Availability:
GRDCS: 100% Available
RCS: 100% Available
Access Net: 100% Available
Mission Video: 100% Available
TPS-75 Radar: Scheduled Available Non-Charge Not Available
Missions 17 15 2 0
Hours 40.00 35.00 5.00 0
Overall Availability: 100% Available ((Available + Non-Charge)/Scheduled)
0%
20%
40%
60%
80%
100%
Tellabs Switch Data/Comm
February 100% 100%
12 month avg 100% 100%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
100%
GRDCS RCS AccessNet TPS-75 Mission Video
February 100% 100% 100% 100.0% 100.0%
12 month avg 100% 100% 100% 100.0% 100%
Unclassified Page 13 of 40
3. Summary of Mission Maintenance Actions:
a. 4 February 2020: Began full bench check on DLS S/N 113 in preparation for potential use as an MUII unit; DLS failed RT unit test, DLS decommissioned.
b. 5 February 2020: Installed aircraft-style heat sink and cap-pak on DLS S/N 036 (from
WSMR) for testing and usage in MUII, performed full bench check, and field calibration at
RWS.
c. 7 - 11 February 2020: Troubleshot DLS S/N 092 after receiving notification of data failure during its usage in an MUII; unit found to have a faulty RT unit, DLS decommissioned.
d. 25 February 2020: Completed annual inspection on DLS S/N 089.
4. RIS Scheduled Maintenance Summary:
a. GRDCS:
1) Due within 45 Days:
Monthly Console Checks, by 31 March 2020
2) Due within 90 Days:
Data Link Subsystem Annual Checks:
SITE, Type DATE DUE S/N Test Type
E9 (048) 01 Mar 2020 098 Annual
PCB 18 Mar 2020 027 Annual
RWEr 18 Mar 2020 030 Annual
ISc B GCS 22 18 Mar 2020 114 Annual
*D3 30 Mar 2020 016 Annual
D1C 30 Mar 2020 024 9 Month
SUBE 30 Mar 2020 025 6 Month
DEPOT 30 Mar 2020 033 Annual
SRB 30 Mar 2020 034 Annual
SHELL 30 Mar 2020 035 Annual
CARRABELLE 30 Mar 2020 036 Annual
*SUBW 30 Mar 2020 051 9 Month
*Currently at MSI for repair
Unclassified Page 14 of 40
b. TPS-75 Radar: Accomplished this month and due within 45 Days.
JOB Completed or due from11/1/19 until 12/4/19 JST REOCCUR Next Due EQUIP #
/0
/2
/0
/2
/0
/2
/0
/2
/0
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/0
/2
/0
/2
/0
/2
/0
/2
/0
/2
/0
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/1
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/2
/3
/2
/3
/2
ANTENNA TIEDOWN STRAPS AND JACKPAD INSPECTION 24 DAILY RE035 1 1 1 1 1 1 1 1 1 0 0 1 1 1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 35E4-178-1 TABLE 2-1
DAILY PERFORMANCE INSPECTION 24 DAILY RE035 1 1 1 1 1 1 1 1 1 0 0 1 1 1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 31P3-2TPS75-6WC-1
UPX 37 DAILY SYSTEM CHECKS - SER # A0109 266 DAILY REA09 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2UPX37-1 TBL 4-1
UPX 37 DAILY SYSTEM CHECKS - SER # C0126 266 DAILY REA26 2UPX37-1 TBL 4-1
3N1 DAILY PERFORMANCE CHECK 301 DAILY C60A3 1 1 1 1 1 1 1 1 1 0 0 1 1 1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 35E4-177-1 TABLE 2-1
2N1 DAILY PERFORMANCE CHECK 326 DAILY C84B2 1 1 1 1 1 1 1 1 1 0 0 1 1 1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 35E4-178-1 TABLE 2-1
DISPLAY CONSOLE TURN ON/OFF 1301 DAILY RE035 1 1 1 1 1 1 1 1 1 0 0 1 1 1 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 31P1-2UYQ27-26WC-1
UPA 59 DAILY PREVENTATIVE MAINTENANCE 1308 DAILY RE035 1 1 1 1 1 1 1 1 1 0 0 1 1 0 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 31P1-2UPA59-1-1 & 2
WEATHER/ECM PERFORMANCE ROUTINE 2 7 DAY 3/2/20 RE035 1 1 1 1 0 0 0 0 31P3-2TPS75-6WC-1
RADAR/SIF SYSTEM TEST PERFORMANCE 50 7 DAY 3/2/20 RE035 1 1 1 1 0 0 0 0 0 31P3-2TPS75-6WC-1
I-F RECEIVER PERFORMANCE ROUTINE 51 7 DAY 2/25/20 RE035 1 1 1 0 0 0 0 0 31P3-2TPS75-6WC-1
HEIGHT PERFORMANCE ROUTINE 73 7 DAY 3/2/20 RE035 1 1 1 1 0 0 0 0 31P3-2TPS75-6WC-1
CLUTTER MAPPING PERFORMANCE ROUTINE 74 7 DAY 3/2/20 RE035 1 1 1 1 0 0 0 0 31P3-2TPS75-6WC-1
COMMUNICATIONS PERFORMANCE ROUTINE 273 7 DAY 3/2/20 RE035 1 1 1 1 0 0 0 0 0 31P3-2TPS75-6WC-1
POWER SUPPLY TEST PERFORMANCE ROUTINE 273 7 DAY 3/2/20 RE035 1 1 1 1 0 0 0 0 0 31P3-2TPS75-6WC-1
DISPLAY CONSOLE WEEKLY INSPECTION 1303 7 DAY 3/2/20 RE035 1 1 1 0 0 0 0 31P1-2UYQ27-26WC-1
ANTENNA/RECEIVER INTERFACE TEST PERFORMANCE ROUTINE 550 14 DAY 2/24/20 RE035 1 1 31P3-2TPS75-6WC-1
SYSTEM ORIENTATION PERFORMANCE CHECK 993 14 DAY 3/3/20 RE035 1 1 0 0 31P3-2TPS75-6WC-1
AFRADES HEIGHT EVALUATION 999 14 DAY 3/4/20 RE035 1 1 0 0 0 31P3-2TPS75-6WC-1
AFRADES BEACON PERFORMANCE 1038 14 DAY 3/4/20 RE035 1 1 0 0 0 31P3-2TPS75-6WC-1
AFRADES CLUTTER ANALYSIS 1041 14 DAY 3/4/20 RE035 1 1 0 0 0 31P3-2TPS75-6WC-1
AUTO SEQUENCER TEST 1207 14 DAY 3/3/20 RE035 1 1 0 0 0 31P3-2TPS75-6WC-1
HEAT EXCHANGER SERVICING 1270 14 DAY 3/9/20 RE035 1 1 35E4-177-1 TABLE 2-1
SHELTER CLEANING AND INSPECTION SERVICING 1271 14 DAY 2/27/20 RE035 1 0 35E4-177-1 TABLE 2-1
COMPRESSOR DEHYDRATOR ON/OFF RATIOS 304 28 DAY 2/26/20 RE035 1 31P3-2TPS75-6WC-1
FREQ GENERATOR COHO REF OUTPUT CHECK 1241 28 DAY 3/23/20 RE035 1 31P3-2TPS75-6WC-1
FREQ GENERATOR IF TEST TARGET AMPLITUDE CHECK 1245 28 DAY 3/23/20 RE035 1 31P3-2TPS75-6WC-1
ANTENNA PEDESTAL AND LEVELING JACK INSPECTION 1250 28 DAY 3/11/20 RE035 1 31P3-2TPS75-6WC-1
RF AND SLIP RING TEST 1253 28 DAY 3/17/20 RE035 1 31P3-2TPS75-6WC-1
MDS/FAR TEST 1254 28 DAY 3/17/20 RE035 1 31P3-2TPS75-6WC-1
AFRADES TILT SENSOR PERFORMANCE 1255 28 DAY 3/17/20 RE035 1 31P3-2TPS75-6WC-1
ANTENNA ASSEMBLY CLEANING AND INSPECTION SERVICING 1272 28 DAY 2/21/20 RE035 0 31P3-2TPS75-6WC-1
SHELTER CORROSION CONTROL INSPECTION AND SERVICING 1273 28 DAY 3/6/20 RE035 1 31P3-2TPS75-6WC-1
ANTENNA CORROSION CONTROL INSPECTION AND SERVICING 1274 28 DAY 3/23/20 RE035 1 31P3-2TPS75-6WC-1
ANTENNA POWER SUPPLY ENCLOSURE AIR FILTER CLEANING 1274 28 DAY 3/23/20 RE035 1 31P3-2TPS75-6WC-1
COMPRESSOR- DEHYDRATOR ASSEMBLY RELIEF VALVE SERVICING 1276 28 DAY 3/9/20 RE035 1 31P3-2TPS75-6WC-1
0 = Job Forecast
/ = Partially C/W
1 = C/W
Unclassified Page 15 of 40
ANTENNA BULL GEAR LUBRICATION 1279 28 DAY 2/21/20 RE035 0 31P3-2TPS75-6WC-1
ANTENNA DRIVE MOTOR GEARBOX OIL LEVEL CHECK 1280 28 DAY 3/17/20 RE035 1 31P3-2TPS75-6WC-1
TUSK ASSEMBLY, JACKSCREW, AND ANTENNA YOKE LUBRICATION 1281 28 DAY 2/21/20 RE035 0 31P3-2TPS75-6WC-1
DISPLAY CONSOLE INSPECTION AND CLEANING 1304 28 DAY 3/18/20 RE035 1 31P3-2TPS75-6WC-1
3N1 MONTHLY PERFORMANCE CHECK 323 MONTHLY 3/9/20 C60A3 1 35E4-177-1 TABLE 2-1
2N1 MONTHLY PERFORMANCE CHECK 329 MONTHLY 3/9/20 C84B2 1 35E4-178-1 TABLE 2-1
UPX 37 QUARTERLY INSPECTION - SER # A0109 283 84 DAY 4/3/20 REA09 2UPX37-1 TBL 4-1
UPX 37 QUARTERLY INSPECTION - SER # C0126 283 84 DAY 3/26/20 REA26 0 2UPX37-1 TBL 4-1
TRANSMITTER OIL BREAKDOWN TEST & FILAMENT INTERRUPT CHECK PROCEDURE 1256 84 DAY 3/27/20 RE035 0 31P3-2TPS75-6WC-1
STORAGE TWYSTRON PUMP DOWN 1257 84 DAY 3/23/20 RE035 0 31P3-2TPS75-6WC-1
MODIFIED BEARING LUBRICATION 1282 84 DAY 2/26/20 RE035 0 31P3-2TPS75-6WC-1
ANTENNA LEG ASSEMBLY INSPECTION 1283 84 DAY 3/27/20 RE035 0 31P3-2TPS75-6WC-1
PROCESSOR RACK INSPECTION AND CLEANING 1285 84 DAY 3/31/20 RE035 0 31P3-2TPS75-6WC-1
MODULAR INTERFACE GROUP INSPECTION AND CLEANING 1289 84 DAY 3/27/20 RE035 0 31P3-2TPS75-6WC-1
UPX 37 SEMIANNUAL INSPECTION - SER # A0109 294 168 DAY 6/26/20 REA09 2UPX37-1 TBL 4-1
UPX 37 SEMIANNUAL INSPECTION - SER # C0126 294 168 DAY 6/18/20 REA26 2UPX37-1 TBL 4-1
TRANSMITTER LIQUID COOLANT SERVICING 1290 168 DAY 1/29/20 RE035 31P3-2TPS75-6WC-1
PPI CIRCUIT CARD INSPECTION AND CLEANING 1291 168 DAY 7/27/20 RE035 1 31P3-2TPS75-6WC-1
CONTROL MONITOR INSPECTION AND CLEANING 1292 168 DAY 7/15/20 RE035 31P3-2TPS75-6WC-1
ANTENNA AND SHELTER JACKS LUBRICATION 1293 168 DAY 7/1/20 RE035 31P3-2TPS75-6WC-1
UPA 59 PREVENTATIVE MAINTENANCE 1309 168 DAY 6/23/20 RE035 31P1-2UPA59-1-1 & 2
ANTENNA DRIVE MOTOR GEARBOX SERVICE 1294 336 DAY 7/29/20 RE035 31P3-2TPS75-6WC-1
PROCESSOR RACK AND CIRCUIT CARD INSPECTION AND CLEANING 1295 336 DAY 7/29/20 RE035 31P3-2TPS75-6WC-1
INTERROGATOR CIRCUIT CARD INSPECTION AND CLEANING 1297 336 DAY 7/29/20 RE035 31P3-2TPS75-6WC-1
DESICCANT CARTRIDGE REPLACEMENT 1298 336 DAY 1/14/21 RE035 31P3-2TPS75-6WC-1
CONTROL MONITOR INSPECTION, CLEANING, AND LUBE 1299 336 DAY 7/13/20 RE035 31P3-2TPS75-6WC-1
HIGH VOLTAGE INSULATED GLOVES TEST SET #1 367 365 DAY 5/7/20 RE035 AFI 91-203, 812.8
HIGH VOLTAGE INSULATED GLOVES TEST SET #2 396 365 DAY 4/23/20 RE035 AFI 91-203, 812.8
ANNUAL HISTORICAL RECORDS REVIEW 1320 365 DAY 2/6/21 RE035 1 00-20-1 PARA 10.7.4
ANNUAL FACILITY GROUNDS INSPECTION 1322 365 DAY 12/14/20 RE035
TX HOIST 1323 365 DAY 12/9/20 RE035 31P3-2TPS75-6 Chpt 2 Sec 1
ANT & SHELTER LIFT HARDWARE INSPECTION BY NDI/ TX HOIST 68 365 DAY 12/30/00 RE035 31P3-2TPS75-6 Chpt 2 Sec 1
ANTENNA TIEDOWN STRAPS INSPECT AND REPLACE ALL 1324 720 DAY 1/28/21 RE035 31P3-2TPS75-6
INSPECT AND REPLACE ALL HYDRAULIC HOSES 1325 60 MONTH 06/06/23 RE035 31P3-2TPS75-6
MIL-HDBK-419A PARA 2.3.1, 31-
10-24 Appx B
5. Maintenance and Logistics Problems:
With the dissolution of the sole repair vendor for the proprietary DLS Receiver/Transmitter units, the current cache of four spare units are all that are available. Some DLSr units have been delivered, and are being used on a limited basis. The remaining DLSr delivery date is a moving target, with an anticipated delivery of March 2020.
a. Top Five Report:
b. Long Lead Report:
6. Gulf Range Tower Conditions:
a. Tower for Site RWN:
Hurricane Michael brought down tower containing this antenna.
Temporary tower installed and working well.
Contracts were awarded September 2019 for replacement of this tower.
b. Tower for Site RWW:
Hurricane Michael brought down tower containing this antenna.
Temporary tower installed and working well.
Contracts were awarded September 2019 month for replacement of this tower
c. Tower for Site APPL:
Hurricane Michael brought down tower containing this antenna.
d. All other towers fully functional.
7. Wendover Status:
a. Building 625 Control Site:
PAE continues to work infrastructure requirements per TSS requests for both a consolidated Wendover only operation and the requirements for a split configuration that would have control at Wendover and drone launches at Dugway. The 388th's contractor
JT3 will provide the WEG an estimate for their support to finish their infrastructure upgrade for the host communications system.
Top 5 Parts Ordered
NSN Part Number Nomenclature End Item Remarks
5340-01-434-2366 M5501/31-1028 CAP, PROTECTIVE SHOPUSE Rec'd 18 Feb 20
5935-00-768-3417 999581-3 CONNECTOR PLUG RADAR Rec'd 21 Feb 20
6135-00-826-4798 E92 BATTERY, NONRECHARGEABLE SHOPUSE Rec'd 29 Jan 20
5970-00-419-4291 MIL-I-24391 TAPE, INSULATION SHOPUSE Rec'd 10 Feb 20
6810-00-356-4936 D1193 5.0 GAL DISTILLED, DEIONIZED WATER RADAR Rec'd 21 Feb 20
Top 5 Parts With Longest Lead Time
Date Ordered NSN Part Number Nomenclature QTY End Item Remarks
19-Jun-18 8010-00-490-7650 MIL-L-81352 LACQUER 1 RADAR Est Due 07 Jul 20
15-Jan-19 7920-00-823-9773 AA1432 TOWEL UTILITY 4 SHOPUSE Est Due 8 May 20
16-Oct-19 6625-01-571-1592 N9912A-104/230 SIGNAL ANALYZER 1 EQUIPMENT Est Due 18 Feb 21
10-Dec-19 6625-01-344-9277 SMR27 SIGNAL GENERATOR 2 EQUIPMENT Est Due 15 Mar 20
26-Feb-20 6130-01-441-1566 SMART750 POWER SUPPLY 1 SHOPUSE Est Due 5 Mar 20
Unclassified Page 17 of 40 Distribution: A
PAE provided locations and quantities for NIPR and SIPR drops within building 625 to aid JT3 with their estimates. Cable and jacks for phones and NIPR computers are installed between the communications room and each location within the building so only the range infrastructure remains to be completed. The TSS is working procurement of the computers and phone instruments.
Based on the consolidated versus split operations plan, the tower needed at building 625 will be new or come from the current Wig Mountain site. The tower at 625 will support antennas for GRDCS, radios and GPS timing. The fastest and most versatile path is to purchase and install a new tower onto the newly built tower base already in place at
Wendover; a new tower would provide increased height (better coverage) at a cost of
~$20K. For either solution, additional RF cable, mounting clamps, etc. must be purchased for the move; a list of those parts was provided to the TSS, ~$6.6K.
GRDCS “New Tech” hardware and software were installed in the Wendover control site; however, the software must be updated to the newest revision in order to become operational.
On 29 April 2019, UTTR 388th personnel reported a water pipe had burst inside the wall of the mechanical room in control site building 625. The water affected several rooms including the console room and server/communications rooms. Per a report from a SPO representative from Hill, none of the WEG owned equipment was damaged and the only required repair for the operations areas is new floor coverings. The break room received more significant damage, primarily to cabinetry and carpet.
b. Launch Pad:
Compressors and power supplies must be purchased for the rails. The 82nd RAs were working this in 2018; there was a contracting hiccup, so funding short stopped the purchase.
Gantries and hoists must be purchased for the launch pad as well as a contract let to install them. PAE completed a design; the narrative for the SOW for the construction must be written before the task can go out for bids.
PAE is developing parts lists for the installation of the rails, power supplies, compressors, grounding, communications, connections for generator, etc.
Fiber equipment must be purchased and installed to provide connectivity from building
625 to the LAMS, and in turn from the LAMS to the launch pad. Much of the hardware from Dugway will be reused when maintenance activities and launch operations move from Dugway; however, several additional items will be needed due to the longer fiber cable runs.
Work continues with environmental approval contractor for the launch and maintenance areas.
c. LAMS Maintenance Shelter:
PAE is working a requirements document to install electrical, grounding, lightning protection, etc.
PAE is developing parts lists for the installation of a compressor, stands to mount items like fire extinguishers, eyewash, AED, etc.
PAE is working a requirements document for a secure storage area within the LAMS.
The LAMS itself was erected; however, it requires repair due to wind damage. The
WEG is working the repair effort.
Unclassified Page 18 of 40 Distribution: A
d. Wendover GRDCS Sites:
The TSS is working lease efforts for the I-80 GRDCS site. This is the single most critical RF point needed to use the Wendover control whether launching from Dugway or Wendover. Site H97 is going through the environmental process. It would also be very helpful for Dugway operations with Wendover control, but it really becomes critical when launch operations move to Wendover. PAE is designing an inclusive site platform for H97.
8. GRDCS and RCS Operating Hours:
9. GRDCS and RCS Accounts Status:
a. GRDCS Accounts:
The GRDCS computers are accessed by user groups rather than by individual accounts. The users are trained for, and only granted access to, the level required to perform their assigned tasks. The three user groups and their level of access are depicted in the following chart.
Mission Support Maintenance Programming &
Engineering
Administration
GRDCS 94.18 31.65 0.00 4.90
RCS 266.00 26.00 44.00 27.00
H o u rs
GRDCS (Operations) CDT (Maintenance) ROOT (Administration)
Hours 119.04 6.79 4.90
GRDCS User Accounts
Unclassified Page 19 of 40 Distribution: A
b. RCS Accounts:
The RCS computers are accessed by user groups rather than by individual accounts. The users are trained for and only granted access to the level required to perform their assigned tasks. The five user groups and their level of access are depicted in the following chart.
10. Engineering and Systems Programming Tasks:
a. Short Title: Testing and evaluation of the maximum GRDCS participant capability.
Summary: Due to the additional GRDCS hardware/software implementation of SIR 451
“Integration of NDI-AIU C-Band Beacon data into GRDCS and RCS
External Track Data” with development version 55, test flights are being supported to verify the maximum GRDCS participant capability.
Date Initiated: 24 April 2009
Completion Date (Estimated): TBD, depending on availability of mission(s).
Current Status: 85% complete.
Problems anticipated or encountered: None.
b. Short Title: Test TM connectivity with Bldg. 223 in order to evaluate the external
NDI-AIU C-Band Beacon data with Safety.
Summary: Due to the additional GRDCS hardware/software implementation of SIR 451
“Integration of NDI-AIU C-Band Beacon data into GRDCS and RCS
External Track Data” with development version 55, a connectivity test with
TM Bldg 223 is still pending to evaluate the data into GRDCS and RCS.
Date Initiated: 13 July 2009
Completion Date (Estimated): TBD, depending on TM shop and testing results.
Current Status: 0% complete.
Problems anticipated or encountered:
First test on 13 July 2009 was not successful. Bldg. 223 personnel could not start the program. More work on their side is required.
83rd 82nd ROOT USAF_Administr ator
Wetstone MSCT
Hours 8.00 27.50 19.00 38.00 456.00 456.00
RCS User Accounts
Unclassified Page 20 of 40 Distribution: A
c. Short Title: Software installation (Release Candidates 3 & 4) and demonstration of SIRs of GRDCS Software/Hardware Version 61.0 – 61.0.7
Summary: Testing is complete.
Date Initiated: 21 August 2018
Completion Date: 04 December 2019
Current Status: Awaiting Sufficiency of Test Review (SOTR) for fielding authorization.
Problems anticipated or encountered: None at this time.
d. Short Title: User software (increment-13, based on v60.4) installation for the QF-16 DR2
Hardware Changes (SIR 843).
Summary: In process of supporting ground and test flights for the QF-16 DR2 Hardware
Changes with Autopilot v1.7 software.
Date Initiated: 29 June 2018
Completion Date (Estimated): TBD
Current Status: Flight testing is complete at Tyndall and is presently taking place at
Holloman. SIR 843 scheduled to be included in v62 software upgrade.
e. Short Title: Software installation of GRDCS Software V62.0 (29Mar19).
Summary: In process of supporting DT testing for v62.0 for the software upgrade.
Date Initiated: 29 March 2019
Completion Date (Estimated): TBD
Current Status: Demo Phase; Start date 28 Feb 2019 with video (SIR844) and .sml file
(SIR878). Continued on 29 May 19, with SIR 739, 822, 874, 849, 877, and 674.
Supported DT phase at Eglin 21-22 January 2020, 18-19 & 26 February 2020.
11. Special Projects:
a. In process of enhancing locally developed ‘safe flight script’ to handle QF-16 telemetry during the different phases of the safe flight profile (10% complete).
b. Supporting Wendover system evaluation as a first look of the new hardware (console and computer) and software to include local RF environment. (Ongoing effort at this time, no
ETA available yet).
c. Attending GRDCS v62.x Demo/Pre-DT/DT events in support of the 96th RNCS/Torch at
Eglin AFB. Cumulative time for three Master Console Operators over 5 total days is currently 85 man-hours. Completion of this effort is TBA.
Unclassified Page 21 of 40
12. ATIS Mission Support (Over-the-Horizon Airborne Relays using platform aircraft):
a. Mission # 0586 / 04-Feb-20
Number of Aircraft Scheduled: 4
Number of Aircraft Provided: 5
Aircraft Data Quality:
Call Sign
Data Link
Rate
(DLR)
Remarks –
(Mandatory if DLR < 90% else observations of feedback)
PLT1
(Tail#486)
95%
PLT2
(Tail#485)
95%
PLT3
(Tail#487)
95%
PLT4
(Tail#480)
95%
SPR
(Tail#N3GT)
N/A
Unclassified Page 22 of 40 Distribution: A
TAB 4 – MAINTENANCE DATA SYSTEM ANALYSIS (MDSA)
METRICS
1. MDSA Metrics:
a. Abort Rate: SDS Criteria FSAT/SSAT < 12%
FSAT = 6.3% (0 AAB + 5 GAB with 79 sorties flown and 0 chargeable GAB lines)
((0 / 79) + (5 / (79 + 0))) x100)
Hydraulics
EPU
Engine
FTIT
Battery
SSAT = 0.0% (0 AAB + 0 GAB with 4 sorties flown and 0 GAB lines)
((0 / 4) + (0 / (4 + 0))) x100)
b. Repeat/Recur Rate: SDS Criteria FSAT/SSAT < 7%
FSAT = 4.8% (0 Repeat + 1 Recur with 21 PRDs) ((1 / 21) x 100)
SSAT = 0.0% (0 Repeat & 0 Recur with 0 PRDs) ((0 / 0) x 100)
c. Cannibalization Rate: 14.5% (12 Canns with 83 Sorties Flown) ((12 / 83) x 100)
d. Data Integrity Error Rate: SDS Criteria - 98% of correctable errors corrected
100.0% (16 Errors with 1 Uncorrectable and 15 Corrected) (15 / (16 - 1)) (2,836
DDRs checked)
e. Break Rate = 9.6% (8 Code 3s with 83 Sorties Flown) ((8 / 83) x 100)
f. Primary Aerospace Vehicle Authorized (PAA) vs. Possessed (PP) Rate:
FSAT = 100.0% (30 assigned with 30 possessed, 50 baseline and 0 CLIN 4/6 inventory at EOM) ((30 / 30) x 100)
SSAT = 100.0% (42 PAA with 42 possessed and 0 CLIN4/6 inventory at EOM) ((42 /
42) x 100)
g. FSAT Mission Success Rate: SDS Criteria - 95%, Critical Standard – 98%
100.0% (111 Sorties attempted with 79 successful and 32 non-chargeable non-successful) ((79 / (111 - 32)) x 100)
h. SSAT Mission Success Rate: SDS Criteria - 95%, Critical Standard – 98%
100.0% (15 Sorties attempted with 4 successful and 11 non-chargeable non-successful) ((4 / (15 - 11)) x 100)
2. Maintenance and Flying Schedule Effectiveness (MSE and FSE)
Unclassified Page 23 of 40
a. MSE = 87.9% (660 points scheduled with 580 complied with) ((580 / 660) x 100)
b. FSE = 44.7% (83 sorties flown, with 43 sorties cancelled, 3 sortie added and 68 total
FSE deviations) (((123 - 68) / 123) x 100)) (Of the 68 chargeable deviations, 1 was attributed to maintenance.)
The main drivers was 43 Cancels.
Add Lines = 3 (2 Ops, 1 Project)
Add Tails = 0
Cancels = 43 (27 Wx, 1 Ops, 15 Project)
Early T/O = 3 (3 Ops)
Late T/O = 19 (5 Projects, 11 Wx, 1 Mx, 2 Sympathy)
GAB Lines = 0
3. Narratives:
Ground & Air Aborts
a. FSAT – There were no air aborts and 5 ground aborts at Tyndall in February, with none at Holloman. These aborts involved 5 aircraft.
(1) There was little in the way of trends on this month’s aborts. There were no aircraft with multiple aborts, no systems with multiple aborts, and only one aircraft with similar aborts in previous months:
(a) AF026 aborted for B system hydraulic pressure loss (Bled B system). It had aborted twice in January of last year for hydraulics issues, once for Hydraulics
(R2 B-system reservoir) and 3 weeks later for ACU Hydraulics (R2 A-system hydraulics indicator). This brings it to a total of 6 ground aborts and 2 air aborts, near the middle of the pack as far as its abort total.
(b) AF022 aborted for FTIT Inop (R2 T5.6 sensor), its first for this system. This aircraft’s last unrelated abort was last month. AF022 has now recorded a total of 16 ground aborts as a QF-16, the seventh highest since the start of the program and second highest of the surviving QF-16s.
(c) At the other end of the spectrum, AF048 experienced its first abort as an FSAT
– EPU did not operate in bleed air mode (R2 Emergency GCU).
(2) The numerical breakouts for December were:
(a) The 5 aborts involved 5 QF-16Cs, all at Tyndall.
(b) Four aborts occurred on O&M flights, one on a customer sortie. All occurred on manned flights.
Unclassified Page 24 of 40
(c) The weekly abort distribution was 3 on Mondays, and 1 each on a Thursday and a Friday. Four aborts occurred on scheduled morning sorties and 1 on a noon sortie.
(d) No sorties were lost to an abort line.
b. SSAT – None
Date Base AF # Reason Corrective Action
FSAT
10 Feb TAFB 26 B system hydraulic pressure loss Bled B system
10 Feb TAFB 48 EPU d/n operate in bleed air mode R2 emergency GCU
21 Feb TAFB 52 Multiple engine MFLs In work
24 Feb TAFB 22 FTIT inop R2 T5.6 sensor
27 Feb TAFB 30 Battery dead R2 battery
SSAT
TAB 5 – TECHNICAL REPORT STATUS
Negative this report period.
Unclassified Page 25 of 40 Distribution: A
TAB 6 – QUALITY CONTROL (QC) SUMMARY REPORT
1. Full-Scale - Tyndall:
a. Eleven Quality Verification Inspections, twenty Special Inspections, five Personnel
Evaluations, and three program audits were accomplished. Thirty-eight inspections passed.
There were one major failures this period consisting of FOD/Boss Audit. There were Zero minor discrepancies.
b. Problem Area: None
c. PQDRs: Two this report period.
DR control # Date CAT Serial # Acft Noun
FA4881-20-
0003 2/3/2020 PQDR
QF048 Radar Altimeter
d. AFTO Form 22’s: None this report period.
e. TODO: Fifty-nine technical order changes and revisions received this period.
f. Impoundments: None this report period.
g. FOD/DOP/Lost item: None this report period.
2. Full-Scale - Holloman:
a. One Quality Verification Inspections, three Special Inspections, ten audits, and one Personnel
Evaluation were accomplished. Fifteen inspections passed.
b. Problem Areas: None this report.
c. PQDRs: None this report period.
d. AFTO Form 22’s: None this report period.
e. TODO: Reviewed 38 Technical Order changes/revisions.
g. FOD/DOP/Lost item: None this report period.
Unclassified Page 26 of 40
3. Subscale:
a. Twenty-two Quality Verification Inspections, seven Special Inspections, four Personnel
Evaluations, and two Program Audit were accomplished. Thirty-five passed, Zero fail. There were eight minor discrepancies found consisting of SSAT Mx actions and Training Records
b. Problem Areas: None this report period.
d. AFTO Form 22s: None this report period.
e. TODO: Twelve technical order change and revision received this period.
f. Impoundments: One this report period.
g. DOP/Lost Item: None this report period.
4. GRDCS - Tyndall:
a. Twelve inspections this period. Twelve passed, Zero failed. One minor in Tool Control Audit
(RADAR)
b. AFTO Form 22s: None this report period.
d. TODO: Two technical orders change and revision this period.
e. Problem Areas: None this report period.
5. ESH - Tyndall:
a. Six Special Inspections were accomplished and 3 Audits. Nine Inspections passed Zero
Failed. Two minors in PPE, respirator Protection program.
6. ESH - Holloman:
a. Two were accomplished this month. Zero Failed.
Unclassified Page 27 of 40 Distribution: A
7. Publications and Forms: No contractual impacts this period. See CDRL A009, Master
Document List.
0.7
0.8
0.9
TYN HMN SSAT RIS ESH
QA Inspection Pass Rate Dec 2019 - Feb 2020
Dec
Jan
Feb
Unclassified Page 28 of 40 Distribution: A
TAB 7 – RIS MAINTENANCE ANALYSIS REQUESTS
1. ELECTRO-MAGNETIC INTERFERENCE (EMI):
No EMI reported this period.
2. RIS MAINTENANCE ACTIONS:
RIS NUMBER: DISCREPANCY: ACTION TAKEN: MISSION IMPACT:
183020001 CARRY OVER:
All poles holding Antenna systems at B1801 down due to Hurricane Michael.
N/A No mission impact noted.
MAINT. AREA:
RIS
START DATE:
20181029
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
DISCR. HOURS: EQUIPMENT MAKE: EQUIPMENT MODEL: EQUIPMENT S/N:
N/A N/A N/A N/A
Unclassified Page 29 of 40
183020002 CARRY OVER:
Runway West tower down due to Hurricane Michael.
Temporarily installed mobile DLS trailer at site.
No mission impact noted.
MAINT. AREA:
RIS
START DATE:
20181029
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
183020003 CARRY OVER:
Runway North tower down due to Hurricane
Michael.
Temporarily installed mobile DLS trailer at site.
No mission impact noted.
MAINT. AREA:
RIS
START DATE:
20181029
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
Unclassified Page 30 of 40 Distribution: A
RIS NUMBER: DISCREPANCY: ACTION TAKEN: MISSION IMPACT:
183020007 CARRY OVER:
ACDS Missile and Drone, Primary and Backup antenna systems down due to Hurricane Michael.
(See RIS# 183020001)
Temporarily installed ACDS
Missile Primary and Backup antennas on Tower 1802.
Temporarily installed Drone
Primary and backup antennas on Tower B1830.
No mission impact noted.
MAINT. AREA:
RIS
START DATE:
20181029
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
183020011 CARRY OVER:
Runway west video is down due to Hurricane
Michael. (See RIS#
183020002)
N/A No mission impact noted.
MAINT. AREA:
RIS
START DATE:
20181029
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
Unclassified Page 31 of 40
190980001 CARRY OVER:
RCS MULTI (RBZ94)
took a lightning strike.
Job opened with COMM
Focal Point (283-4896).
Put GRDCS Multi in RCS
Multi’s slot.
None
MAINT. AREA:
COMM
START DATE:
20190408
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
DISCR. HOURS: BRAND: EQUIPMENT MODEL: EQUIPMENT S/N:
192120101 CARRY OVER:
GSM Transceiver
Communication Error during attempted Self-
Calibration.
IAW w/ T.O., checked all connections. Rebooted system, symptom persisted.
Reported to SPO, awaiting direction. SPO picked up unit for delivery to MSI for repair.
None
MAINT. AREA:
DLS
START DATE:
20190731
STOP DATE:
N/A
REPAIRED BY:
D. Holmes
MAN HOURS:
N/A
COST:
N/A
N/A MSI 915 DTS 003
Unclassified Page 32 of 40
200220001 No receive on
WETSTONE GATR-A
radio (288.5).
Opened a remedy ticket. No mission impact noted.
MAINT. AREA:
COMM
START DATE:
20200122
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
200220002 DLSr serial number 30 at
Runway East is not responding during Eglin testing.
Removed DLSr and installed DLS.
Operational checks good.
Awaiting DLSr repair.
No mission impact noted.
MAINT. AREA:
GRDCS
START DATE:
20200122
STOP DATE:
REPAIRED BY:
D.HOLMES
MAN HOURS:
1.0
COST:
N/A
N/A N/A N/A
Unclassified Page 33 of 40 Distribution: A
RIS NUMBER: DISCREPANCY: ACTION TAKEN: MISSION IMPACT:
200220101 60% data quality reported on DLSr at
SUBW
Performed DLSr FAT, Oscillator Calibration, and
Pulses Present tests, all tests passed except for
“PA Enable.” RMA requested from MSI.
None
MAINT. AREA:
DLS
START DATE:
20200122
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
N/A MSI DLSr 051
200240101 No output reported from DLSr at RWER
No pulses present, oscillator will not calibrate, no output.
RMA requested from
MSI.
None
MAINT. AREA:
DLS
START DATE:
20200124
STOP DATE:
N/A
REPAIRED BY:
N/A
MAN HOURS:
N/A
COST:
N/A
N/A MSI DLSr 030
Unclassified Page 34 of 40
200380101 Unit removed from
MUII after failure.
No response during bench check on any address.
Removed and replaced address switch, no change.
Troubleshot to faulty RT unit, no spares available, unit decommissioned for parts.
None
MAINT. AREA:
DLS
START DATE:
20200207
STOP DATE:
20200211
REPAIRED BY:
D. Holmes
MAN HOURS:
5.0
COST:
0.0
101.0 IBM DLS 092
200430001 No GPS Reference signal for ACDS/Audio recording.
Removed and replaced
GPS receiver.
Operational checks good.
No mission impact noted.
MAINT. AREA:
UHF DESTRUCT
START DATE:
20200212
STOP DATE:
20200212
REPAIRED BY:
A.BIGGINS
MAN HOURS:
0.5
COST:
$4745.00
1.0 TRUETIME GPS RECEIVER SR035143714
Unclassified Page 35 of 40
200510001 ACDS Drone Right has intermittent FAIL OVER condition at CARRIER
UP.
Removed and replaced
HPA with spare on hand.
Operational checks good.
No mission impact noted.
MAINT. AREA:
UHF DESTRUCT
START DATE:
20200220
STOP DATE:
20200220
REPAIRED BY:
A.BIG/K.GIA
MAN HOURS:
2.0
COST:
N/A
2.5 N/A N/A N/A
200520001 On the ACS/EMC shoutdown, EMC has no receive or audio indicator.
Had ACS bump transmit level +12dB.
Operational checks good.
No mission impact noted.
MAINT. AREA:
COMM
START DATE:
20200221
STOP DATE:
20200221
REPAIRED BY:
E.ROSAMOND
MAN HOURS:
1.0
COST:
N/A
3.0 N/A N/A N/A
Unclassified Page 36 of 40 Distribution: A
RIS NUMBER: DISCREPANCY: ACTION TAKEN: MISSION IMPACT:
200550001 While converting
AATTCS Console 8 from new hardware to old hardware after testing, the
ProLog failed startup.
Removed and replaced
Prolog with parts on hand.
Operational checks good.
No mission impact noted.
MAINT. AREA:
GRDCS
START DATE:
20200224
STOP DATE:
20200224
REPAIRED BY:
D.CONTRERAS
MAN HOURS:
1.0
COST:
N/A
1.0 N/A N/A N/A
Unclassified Page 37 of 40
TAB 8 – FACILITIES OPEN WORK REQUESTS
TOP FIVE WORK REQUESTS
TOP 5
JOB NO.
BLDG WORK DESCRIPTION STATUS DATE
SUBMITTED
38912
1801 Repair raised floor in room 114. Note:
Submitted by the 81st Range Control Squadron.
CES/CEO
REVIEW
25 Jan 18
239 Repair 239 above-ground storage tank CES/CENPD
In work
13 Nov 19
8513 LP Gate Repair CES
REVIEW
31 Jul 19
38125
45 Pave access road/checkpoint. CES/CENPD
REVIEW
1 Apr 15
59188
Extend existing permanent static ground system inside buildings.
CES/CENM
REVIEW
7 Aug 13
Full Scale Facilities – Building Manager – S. Davis
JOB NO. BLDG WORK DESCRIPTION STATUS DATE SUBMITTED
38125 45 Pave access road/checkpoint.
CES/CENPD
REVIEW
1-Apr-15
59222 45 Roadway Improvement
CES/CENP
REVIEW
21-Nov-13
E2953 9310
Plumb emergency eyewash drain to the building exterior. Install shower pans under emergency showers in Bays 1 and 3 and plumb to drain outside.
CES/FM
PLUMBER
AWT
SCHEDULE
11-Aug-17
38672 9310 Install 26 electrical outlets.
CES/CENP
REVIEW
24-Jan-17
G-0424 156 Install ice maker
CES/CENPD
REVIEW
26-Jul-19
G-0425 9310 Install ice maker
CES/CENPD
IN WORK
26-Jul-19
G-3547 9310 Exit lights INOP in tool room west door and hangar bay 1 south door
CES/CENPD
IN WORK
30-Dec-19
Unclassified Page 38 of 40 Distribution: A
Range Instrumentation Systems Facilities – Building Manager - R. Williams
JOB NO. BLDG WORK DESCRIPTION STATUS DATE
SUBMITTED
38912 1801 Repair raised floor in room 114. Note:
Submitted by the 81st Range Control Squadron.
CES/CEO
REVIEW
25 Jan 2018
39126 9401 Paint facility. CES/ALOP
SUBMITTED
16 Aug 2018
39211 9350 Replace galvanized communication tower due to
Hurricane Michael damage
CES/ALOP
SUBMITTED
13 Dec 2018
39210 9349 Replace galvanized communication tower due to
Hurricane Michael damage
CES/ALOP
SUNMITTED
13 Dec 2018
39209 1810 Replace galvanized communication tower due to
Hurricane Michael damage
CES/ALOP
SUBMITTED
13 Dec 2018
39285 9352 Tower Alignment-Tensioning and LPS repair CES/ALOP
SUBMITTED
10 Jan 2019
39297 9317 R&R 20’ Tower Ladder. Reinstall LPS
(Ladder Portion Complete)
CES/ALOP
SUBMITTED
(In Progress)
10 Jan 2019
39389 9401 R&R Perimeter Security Fence CES/ALOP
SUBMITTED
31 Jan 2019
39431 9901 Comprehensive tower inspection
(St. George Island)
CES/ALOP
SUBMITTED
13 Feb 2019
Sub Scale Launch Pad – Building Manager - B. Prince
JOB
NO.
BLDG WORK DESCRIPTION STATUS DATE
SUBMITTED
34672 8500 Area Paint buildings and floors. CES/CEPD
REVIEW
24 Jan 06
37441 8519 Install pavement southwest of building.
Project No. XLWU142051D
CES/CENPD
CONTRACT
15 Jun 12
59188 8519
Extend existing permanent static ground system inside buildings.
CES/CENM
REVIEW
7 Aug 13
C7092 8519 Install emergency eyewash/shower stations in the north and south bays.
CES/PLUMER
IN PROGRESS
24 Nov 15
F2434 8525
Rail #4
Repair rail #4 hoist electrical power conduit. CES/ALOP
SUBMITTED
30 Aug 18
8513 LP Gate Repair CES/CEPD
Review
30 Jul 19
G0555 8519 Overhead Light fixture repair CES
Submitted
30 Jul 19
Unclassified Page 39 of 40
Sub Scale Maintenance Facilities – Building Manager - D. Jacobs
JOB NO. BLDG WORK DESCRIPTION STATUS DATE
SUBMITTED
39890 239 Repair 239 above ground storage tank CES/CENPD
In work
13 Nov 19
Unclassified Page 40 of 40
TAB 9 – CONTRACTOR PROGRAM MANAGEMENT CONCERNS
The lack of aircraft deliveries from Boeing is impacting our overall aircraft fleet numbers as well as our ability to manage aircraft hours. Once Boeing has worked through production issues, we expect the number of aircraft deliveries will increase past the 2 deliveries/month as called out in the PWS.
This will impact PAE’s ability to meet Safe Flight time requirements and create a backlog of aircraft awaiting Safe Flights.
All the cleanup of failed data documentation and maintenance processes in aircraft generation from
AMARG and/or Boeing continues to fall on PAE for correction prior to SAFE flight.
Failure to receive delivery aircraft is impacting available manned flyers (Tyndall & Holloman).
Correspondingly, NULLO fleet health/quantity is becoming an issue. Expect continued movement of aircraft to and from Holloman and early De-Man of flyers to keep Tyndall’s NULLO fleet minimally populated.
Severe damage to most of our facilities is causing many workarounds and much turmoil. PAE is managing the situation the best we can. Construction of temporary facilities is almost complete and for the most part the facilities are adequate with a few workarounds.
Base Supply functions and support are slowly coming back but lack of wheels and tires this past month did have an impact on aircraft availability.
A major concern is safely moving into temporary facilities while still complying with all AF regulations governing the safe handling and storage of explosive items.