This document is a schedule of material submittals for a federal contract to repair sunshades at a CDC playground. The contractor must submit 14 items by the dates specified, including a work/construction plan, safety plan, shade design specifications, concrete specifications, and as-built drawings. Submittals require approval from the Air Force Resident Officer in Charge of Construction and the Civil Engineering department. The solicitation was issued by the Air Force Air Education and Training Command for project number EEPZ223515 to repair sunshades at building B940 for the Centers for Disease Control and Prevention.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B940 RFIs 20230807.pdf | ||
| B940 RFIs 20230802.pdf | ||
| Design Build SOW_20230726.pdf | ||
| Amendment 1 FA302223R00180001 .pdf | ||
| Attachment 4- Proof of Insurance.pdf | ||
| Attachment 1- Statement of Work.pdf | ||
| Attachment 2- Wage Determination.pdf | ||
| Attachment 3- AF Form 66.xlsx | XLSX spreadsheet | |
| Solicitation - FA302223R0018.pdf | ||
| Attachment 5- Form DD1354.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Project No: EEPZ223515 Project Title: Repair CDC Sunshades Playground, B940 Date: 26-Jul-23
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 1 | Schedule of Material Submittals (AF Form 66 - mod) | RFP | X | ||||||||||||||||
| 2 | Work/Construction Plan | RFP | X | ||||||||||||||||
| 3 | Safety Plan | RFP | X | ||||||||||||||||
| 4 | Completed DD Form 1354 | RFP | X | ||||||||||||||||
| 5 | List of Equipment | RFP | X | ||||||||||||||||
| 6 | Rubber Material Specifications | RFP | X | X | X | X | X | ||||||||||||
| 7 | Cantileiver Shade Design Specifications and Material | RFP | X | X | X | X | X | X | |||||||||||
| 8 | Sail Canopy Design and Material Specifications | RFP | X | X | X | X | X | X | |||||||||||
| 9 | Concrete Material Specifications & Mix Design | RFP | X | ||||||||||||||||
| 10 | Concrete Break Testing Data | RFP | X | ||||||||||||||||
| 11 | 95% & 100% Design Submittals | RFP | X | ||||||||||||||||
| 12 | As-Built Drawings | RFP | X | ||||||||||||||||
| 13 | Work Schedule | RFP | X | ||||||||||||||||
| 14 | Shade Poles Paint | RFP | X | X |
AF Form 66 (Substitute) GENERAL Page&Pof&N
SCHEDULE OF MATERIAL SUBMITTALS