Attachment 3- AF Form 66.xlsx
XLSX spreadsheet 18 KB Posted
- Attached to
- B940 CDC Sunshades Federal contract opportunity
- Solicitation number
- FA302223R0018
About this file
This document contains a schedule of material submittals required for the Repair CDC Sunshades Playground, B940 federal contract opportunity issued by the Department of the Air Force Air Education and Training Command. The contractor must submit a schedule of material submittals, work/construction plan, safety plan, DD Form 1354, list of equipment, specifications for rubber and shade materials, concrete material specifications and mix design, concrete break testing data, 95% and 100% design submittals, and as-built drawings. The contractor must also provide a work schedule. Key submittal dates include dates for when the contractor requires approval, dates items are received by the government, dates for resubmittals if needed, and the final approval receipt date.
The solicitation number for the Repair CDC Sunshades Playground, B940 opportunity is FA302223R0018. The schedule of material submittals document provides details on the types of documents and information the contractor must provide to the government over the course of the project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B940 RFIs 20230807.pdf | ||
| B940 RFIs 20230802.pdf | ||
| CDC_AF Form 66_20230726.xlsx | XLSX spreadsheet | |
| Design Build SOW_20230726.pdf | ||
| Amendment 1 FA302223R00180001 .pdf | ||
| Attachment 5- Form DD1354.pdf | ||
| Attachment 4- Proof of Insurance.pdf | ||
| Attachment 1- Statement of Work.pdf | ||
| Attachment 2- Wage Determination.pdf | ||
| Solicitation - FA302223R0018.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Project No: EEPZ223515 Project Title: Repair CDC Sunshades Playground, B940 Date: 24-May-23
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 1 | Schedule of Material Submittals (AF Form 66 - mod) | RFP | X | ||||||||||||||||
| 2 | Work/Construction Plan | RFP | X | ||||||||||||||||
| 3 | Safety Plan | RFP | X | ||||||||||||||||
| 4 | Completed DD Form 1354 | RFP | X | ||||||||||||||||
| 5 | List of Equipment | RFP | X | ||||||||||||||||
| 6 | Rubber Material Specifications | RFP | X | X | X | X | X | ||||||||||||
| 7 | Shade Design Specifications and Material | RFP | X | X | X | X | X | ||||||||||||
| 8 | Concrete Material Specifications & Mix Design | RFP | X | ||||||||||||||||
| 9 | Concrete Break Testing Data | RFP | X | ||||||||||||||||
| 10 | 95% & 100% Design Submittals | RFP | X | ||||||||||||||||
| 11 | As-Built Drawings | RFP | X | ||||||||||||||||
| 12 | Work Schedule | RFP | X |
AF Form 66 (Substitute) GENERAL Page&Pof&N
SCHEDULE OF MATERIAL SUBMITTALS