CN-370000-HW689-DC24CCO1.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|HW689|a751b87398beb5bfc7861f19a403533e
Contract number
HW689
Issued by
Florida

About this file

Document Summary

This Task Assignment Change Order (TACO #1) amends the original Task Assignment DC024C under Contract HW689 between the State of Florida Department of Environmental Protection (FDEP) and APTIM Environmental & Infrastructure, LLC. The change order addresses cost increases resulting from personnel scheduling conflicts that required team members to mobilize from a Winter Garden office location rather than the originally planned Tampa office.

The change order increases the total task value from $100,556.56 to $103,952.56—an increase of $3,396.00—to cover additional travel expenses including hotel accommodations and per diem for affected personnel. The contract scope involves site assessment activities at the former Southgate Cleaners facility (ERIC_5228) located at 5317 U.S. Highway 19, New Port Richey, Pasco County, Florida, including modified active gas sampling, soil sampling, direct push technology groundwater sampling, and well installations. The task completion date has been extended from April 11, 2025, to July 18, 2025 (98 days total), with the final deliverable due date extended from February 11, 2025, to May 15, 2025. The amended price is structured as a fixed unit rate, with invoicing tied to FDEP approval of specific deliverables: Field Notes Package & Analytical Results ($68,009.02), Boring Log & Field Notes ($15,506.49), and Site Assessment Report & Project Management ($20,437.05).

View the file

Other files

File Type Posted
CN-370000-HW689-BF1BCO1.pdf PDF
CN-370000-HW689-BIL01A.pdf PDF
CN-370000-HW689-BIL1BCO2.pdf PDF
CN-370000-HW689-BIL1DCO1.pdf PDF
CN-370000-HW689-CSS01A.pdf PDF
CN-370000-HW689-DC0013B.pdf PDF
CN-370000-HW689-DC003D.pdf PDF
CN-370000-HW689-DC004C.pdf PDF
CN-370000-HW689-DC005B.pdf PDF
CN-370000-HW689-DC005D.pdf PDF
CN-370000-HW689-DC006B.pdf PDF
CN-370000-HW689-DC007B.pdf PDF
CN-370000-HW689-DC008C.pdf PDF
CN-370000-HW689-DC009A.pdf PDF
CN-370000-HW689-DC009C.pdf PDF
CN-370000-HW689-DC010A.pdf PDF
CN-370000-HW689-DC013C.pdf PDF
CN-370000-HW689-DC014A.pdf PDF
CN-370000-HW689-DC015B.pdf PDF
CN-370000-HW689-DC016C.pdf PDF
CN-370000-HW689-DC017B.pdf PDF
CN-370000-HW689-DC018B.pdf PDF
CN-370000-HW689-DC020A.pdf PDF
CN-370000-HW689-DC021A.pdf PDF
CN-370000-HW689-DC022A.pdf PDF
CN-370000-HW689-DC023B.pdf PDF
CN-370000-HW689-DC024B.pdf PDF
CN-370000-HW689-DC026A.pdf PDF
CN-370000-HW689-DC027A.pdf PDF
CN-370000-HW689-DC032A.pdf PDF
CN-370000-HW689-DC036A.pdf PDF
CN-370000-HW689-DC04ACO1.pdf PDF
CN-370000-HW689-DC05DCO2.pdf PDF
CN-370000-HW689-DC09CCO2.pdf PDF
CN-370000-HW689-DC12BCO1.pdf PDF
CN-370000-HW689-DC12BCO2.pdf PDF
CN-370000-HW689-DC13BCO5.pdf PDF
CN-370000-HW689-DC14BCO1.pdf PDF
CN-370000-HW689-DC16CCO2.pdf PDF
CN-370000-HW689-DC16CCO3.pdf PDF
CN-370000-HW689-DC17BCO1.pdf PDF
CN-370000-HW689-DC18BCO4.pdf PDF
CN-370000-HW689-DC20BCO1.pdf PDF
CN-370000-HW689-DC21BCO2.pdf PDF
CN-370000-HW689-DC24CCO2.pdf PDF
CN-370000-HW689-DC27ACO1.pdf PDF
CN-370000-HW689-DC29ACO2.pdf PDF
CN-370000-HW689-DC30ACO1.pdf PDF
CN-370000-HW689-FIL1.pdf PDF
CN-370000-HW689-FIL13.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

DC024C 1 HW689

Nicole Knutson 850-245-8763 APTIM Environmental & Infrastructure, LLC

Eric Kramer 407-287-3216

ERIC_5228

Southgate Cleaners (former)

$ 103,952.56 $ 100,556.56

$ 103,952.56 $ 100,556.56

04/11/2025 07/18/2025 98

1 1 1

Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2025.03.24 07:46:53 -04'00'

Teresa Booeshaghi

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2025.03.23 09:00:54 -04'00'

3/23/2025

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Alexis A. Lambert Secretary

Memorandum

TO: ERIC_5228

Southgate Cleaners (former)

FROM: Nicole Knutson, Project Manager

SUBJECT: Negotiation Summary

HW689 DC024C CO1

DATE: March 20, 2025

This Change Order reconciles WCD #1, which increases travel expenses for the site assessment work at Southgate Cleaners. Due to scheduling conflicts, several team members from outside of the nearby Tampa office have been assigned to this project. For those personnel, travel expenses such as lodging and per diem have been added to the proposed cost.

Total task amount has increased by $3,396.00. The original price was $100,556.56 and the amended price is $103,952.56. APTIM’s time, labor, and subcontractor costs for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable due date has been extended from February 11, 2025 to May 15, 2025.

Task completion date has been extended from April 11, 2025 to July 10, 2025.

LEVEL OF EFFORT / EXPENSE WORKSHEET

SITE : Southgate Cleaners (Former)

SUBTASK:

DATE: March 20, 2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 2

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 4 S. Flynn Engineer/Scientist 2 K. Howard

Engineer/Scientist 2 K. McDonald

Engineer/Scientist 1 W. Kesterson

Engineer/Scientist 1 R. Kelley

Engineer/Scientist 1 B. Blount Engineer Scientist 1 R. Lindsay

Engineering Technician 1 W. Jahns

Designer 2 S. Ferianc Technical Publications Speciali H. Vining Technical Publications Speciali M. Comins 3

TOTAL LABOR 183

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 4 $480.00

Van or Truck $480.00 Week 2 $960.00

TOTAL VEHICLE $1,440.00

PER DIEM STAFF DESCRIPTION RATE UNIT USEAGE TOTALS

Hotel 2 McDonald, Lindsey $150.00 Day 4 $1,200.00 Hotel 2 Howard, Blount $150.00 Day 4 $1,200.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noon 2 McDonald, Lindsey $30.00 Day 2 $120.00 Day 1-Leave between 6 - Noon 2 Howard, Blount $30.00 Day 2 $120.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 2 McDonald, Lindsey $36.00 Day 4 $288.00 Day 2 Howard, Blount $36.00 Day 4 $288.00

TOTAL PER DIEM $3,216.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

Survtech Solutions Survey and Benchmark Placement $2,750.00 LS 1 $2,750.00 Site Lines Utility Locate Services $900.00 LS 1 $900.00 Atlantic Supply MAGS Well Supplies (Casing, Screen, Sand) $883.31 LS 1 $883.31

TOTAL $4,533.31

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 12 0 $2,400.00

EPA Method 8260 (Full List) Soil $150.00 48 0 $7,200.00

EPA Method 1312 SPLP Extraction (Zero Headspace Method) Soil $55.00 0 0 Contingency $0.00

EPA Method 8260 (VOHs) Leachate $73.00 0 0 Contingency $0.00 EPA Method 8260 (Full List) Well $150.00 0 0 $0.00 Sample Shipping (Small cooler) $110.00 4 $440.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $10,040.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 7 $280.00

Soil Sampling Kit (concrete) $235.00 Day 2 $470.00 MAGS Investigation Kit $500.00 Day 1 $500.00 Tedlar Bags $20.00 bag 9 $180.00 Shallow GW Sampling Kit $290.00 Day 0 $0.00 Encore Sampler $16.00 each 48 $768.00 55 Gallon Drums $100.00 each 1 $100.00

TOTAL EQUIPMENT $2,298.00

Note: Air Analysis by TO-15, Soil Samples by VOCs by EPA Method 8260 (Full List)

Round Trip Travel for three days to site for MAGS Soil Sampling and Testing (6 hrs), Attend Onsite H&S and Scoping meetings (1 hr), Assist with Collection of 12 MAGS Soil Boring Location Samples, for the collection of 48 soil samples at depths of 6", 2', 4 and 6' (12 hrs), Assistance with Installation and Construction of 12 MAGS Testing Wells (12 hrs), Assistance with Installation of 4 Vapor Monitoring Point Locations (3 hrs), Surface and Site Restoration, Drum Handling and Demobilization (3 hrs), Daily Soil Sample Deliveries to Laboratory (2 hrs).

Preparation of Site Specific Health and Safety Plan (3 hrs)

MAGS Testing and Soil Sampling Mobilization and Field Event Preparation (2 hrs), Travel Round Trip for MAGS Well Installations (6 hrs), Perform Onsite H&S and Scoping meetings (1 hr), Installation and Construction of 12 MAGS Testing Wells, including coring (12 hrs), Installation of 4 Vapor Monitoring Point Locations, including coring (3 hrs), Perform MAGS Tests at 12 locations and collection of 12 Vapor Samples (14 hrs), Surface and Site Restoration (2 hrs).

Round Trip Travel for MAGS Testing (4 hrs), Perform MAGS Tests at 12 locations and collection of 12 Vapor Samples (14 hrs), Surface and Site Restoration, Equipment Demobilization (3 hrs).

Onsite Meeting with Property Owner/Property Manager/tenant and perform Utility White-lines for Markouts including travel (10 hrs), Oversight of GPR Utility Subcontract Survey (10 hrs), Oversight of Professional Site Survey (10 hrs), MAGS Testing and Soil Sampling Mobilization and Field Event Preparation (2 hrs), Round Trip Travel for three days to site for MAGS Soil Sampling and MAGS Installations (6 hrs), Perform Onsite H&S and Scoping meetings (1 hr), Advancement of 12 MAGS Soil Borings for the collection of 48 soil samples at depths of 6", 2', 4, and 6' (12 hrs), Assistance with Installation and Construction of 12 MAGS Testing Wells (12 hrs), Assistance with Installation of 4 Vapor Monitoring Point Locations, including coring (3 hrs), Preparation of Soil Boring Logs and MAGS Well Constuction Logs (3 hrs).

2-SiteMeeting, MAGS

MAGS Analytical Data and Graph Reviews for Reporting to FDEP (2 hrs)

Research and Prepare Site Access Agreement for Adjacent Property to east and ROW of Leisure Lane to the west (4 hrs), Site Work Notifications, Submit Sunshine One Markout Requests (2 hrs), Summarize MAGS and MAGS Soil Data for Preliminary Reporting to FDEP (3 hrs).

2-Total Page 3 of 13 HW689 DC024C TACO #1 (Southgate Cleaners)

SUBTASK:

DATE: March 20, 2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 2

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 4 S. Flynn Engineer/Scientist 2 K. Howard Engineer/Scientist 2 K. McDonald Engineer/Scientist 1 W. Kesterson

Engineer/Scientist 1 R. Kelley

Engineer/Scientist 1 B. Blount Engineer Scientist 1 R. Lindsay

Engineering Technician 1 W. Jahns

Designer 2 S. Ferianc Technical Publications Speciali H. Vining Technical Publications Speciali M. Comins

TOTAL LABOR 128

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 1 $120.00

Van or Truck $480.00 Week 1 $480.00

TOTAL VEHICLE $600.00

PER DIEM STAFF DESCRIPTION RATE UNIT USEAGE TOTALS

Hotel 1 Howard $150.00 Day 3 $450.00 Hotel 1 Blount $150.00 Day 3 $450.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noon 1 Howard $30.00 Day 1 $30.00 Day 1-Leave between 6 - Noon 1 Blount $30.00 Day 2 $60.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 1 Howard $36.00 Day 3 $108.00 Day 1 Blount $36.00 Day 2 $72.00

TOTAL PER DIEM $1,170.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

GW Protection DPT Drilling $8,616.00 Lump 1 $8,616.00

TOTAL $8,616.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00

EPA Method 8260 (Full List) Soil $150.00 24 0 $3,600.00

EPA Method 1312 SPLP Extraction (Zero Headspace Method) Soil $55.00 0 0 Contingency $0.00

EPA Method 8260 (VOHs) Leachate $73.00 0 0 Contingency $0.00

EPA Method 8260 (Full List) DPT Groundwater $150.00 27 0 $4,050.00

EPA Method 8260 (Full List) Well/Piezometers $150.00 3 0 $450.00

EPA Method 8260 (Full List) IDW $150.00 0 0 $0.00 EPA Method 6010 (As, Cd, Cr and Pb) IDW $52.00 0 0 $0.00 EPA Method 1311 TCLP Extraction (Zero Headspace Method/VOCs)-Solid $55.00 0 0 $0.00 EPA Method 1311 TCLP Extraction (Bottle Extraction for Metals)-Solid $45.00 0 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $8,100.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 5 $200.00

Soil Sampling Kit (concrete) $235.00 Day 1 $235.00 Monitor Well Installation Kit $325.00 Day 1 $325.00 Total Survey Station $50.00 Day 1 $50.00 Shallow GW Sampling Kit $290.00 Day 2 $580.00 Encore Sampler $16.00 each 24 $384.00 55 Gallon Drums $100.00 each 0 $0.00

TOTAL EQUIPMENT $1,774.00

Soil and Groundwater Samples by VOCs by EPA Method 8260 (Full List)

Collect Remaining Soil Samples at 6 locations including Travel, Coring, Collection of Soil Samples (12 hrs), Site Restoration (2 hrs), Soil Sample Packaging, Chain of Custody and Sample Delivery to Laboratory (2 hrs), Groundwater Sampling and Survey Piezometers with Travel (8 hrs).

Remaining Soil Sampling Field Event Preparation and Mobilization (2 hrs), Round Trip Travel to site (2 hrs), Collect Remaining Soil Samples at 6 locations including, Coring, Collection of 24 Soil Samples (12 hrs), DPT Drilling Field Event Preparation and Mobilization (2 hrs), Travel to Site over 4 days (8 hrs), Installation of one DPT Macrocore to 60 ft bls, installation of 3 Piezometers, DPT Groundwater Sampling at 9 locations (48 hrs), Survey Piezometers (1 hr), Daily DPT Groundwater Sample Chain of Custody preparation, Sample Packaging (3 hrs), Preparation of Soil Boring and Well Construction Logs (4 hrs), Preparation of Summary Tables and Figures of Groundwater Sampling Results for Preliminary Reporting to FDEP (6 hrs).

Finalize Proposed DPT Locations (1 hr), Finalize Proposed Piezometer Locations (1 hr).

Contacting Property Owner, Property Manager, Tenant and/or Offsite Property Owner of Proposed Sampling Schedule and Confirming Access (2 hrs), Compilation of Field Soil Analytical Data, Preparation of Soil Summary Maps for FDEP (3 hrs), Preparation and Review of Cross Section from DPT Core for Recommendations of Proposed GW Sampling Depths with FDEP (3 hrs), Calculation of Well and Watertable Elevations for Flow Direction (2 hrs.), Preparation of Groundwater Flow Map for FDEP (3 hrs), Prepare Map of Final Proposed DPT Locations (1 hr).

3-Soil and Groundwater Field Activities

3-Total Page 4 of 13 HW689 DC024C TACO #1 (Southgate Cleaners)

SUBTASK:

DATE: March 20, 2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 2

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 4 S. Flynn Engineer/Scientist 2 K. Howard Engineer/Scientist 2 K. McDonald Engineer/Scientist 1 W. Kesterson

Engineer/Scientist 1 R. Kelley

Engineer/Scientist 1 B. Blount Engineer Scientist 1 R. Lindsay

Engineering Technician 1 W. Jahns

Designer 2 S. Ferianc Technical Publications Speciali H. Vining Technical Publications Speciali M. Comins

TOTAL LABOR 67

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00

Van or Truck $480.00 Week 1 $480.00

TOTAL VEHICLE $480.00

PER DIEM STAFF DESCRIPTION RATE UNIT USEAGE TOTALS

Hotel 1 Howard $150.00 Day 1 $150.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noon 1 Howard $30.00 Day 1 $30.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 1 Howard $36.00 Day 1 $36.00

TOTAL PER DIEM $216.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

GW Protection Well Installations $4,642.00 LS 1 $4,642.00 Erwin Remediation IDW T&D Soil Drums $110.00 LS 3 $330.00 Erwin Remediation IDW T&D Liquid Drums $125.00 LS 4 $500.00

TOTAL $5,472.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00 EPA Method 8260 (Full List) Soil $150.00 0 0 $0.00

EPA Method 1312 SPLP Extraction (Zero Headspace Method) Soil $55.00 0 0 Contingency $0.00

EPA Method 8260 (VOHs) Leachate $73.00 0 0 Contingency $0.00

EPA Method 8260 (Full List) Wells $150.00 7 0 $1,050.00

EPA Method 8260 (Full List) IDW $150.00 2 0 $300.00

EPA Method 6010 (As, Cd, Cr and Pb) IDW $52.00 2 0 $104.00

EPA 1311 TCLP Extraction (Zero Headspace Method/VOCs)-Soil IDW $55.00 1 0 $55.00

EPA 1311 TCLP Extraction (Bottle Extraction/Metals)-Soil IDW $45.00 1 0 $45.00

Sample Shipping (Small cooler) $110.00 0 $0.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $1,554.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 5 $200.00

Soil Sampling Kit (concrete) $235.00 Day 0 $0.00

Monitor Well Installation Kit $325.00 Day 2 $650.00

Total Survey Station $50.00 Day 1 $50.00

Shallow GW Sampling Kit $290.00 Day 2 $580.00

Encore Sampler $16.00 each 0 $0.00

55 Gallon Drums $100.00 each 1 $100.00

TOTAL EQUIPMENT $1,580.00

Collection of Final Groundwater Samples from 7 wells, with Travel, Survey Wells, Site Restoration (9 hrs), Collection of PFAS Groundwater Samples (4-5 wells) and IDW Samples, with Travel, Drum Handling (8 hrs), Chain of Custody Completion and Packaging (1 hr) and Delivery of FDEP PFAS Samples to Shipper (2 hrs)

Groundwater Samples by VOCs by EPA Method 8260 (Full List)

Prepare Recommendations for Final Well Locations (2 hrs)

Property Owner, Property Manager, Tenant Site Work Notifications (1 hr), Prepare Proposed Well Location Maps and Recommendations (3 hrs), Preparation of PFAS Well Recommendations for FDEP and Order Kit from FDEP Laboratory (2 hrs), Characterization and Waste Profile for Transportation and Disposal of IDW Drums (2 hours).

Round Trip Travel to the Site (4 hrs), Installation of final well network of 3 shallow/1 deep (20 hrs).

Collection of Final Groundwater Samples from 7 wells with travel and Survey Wells (9 hrs), Deliver final samples to laboratory (2 hrs), Preparation of Well Construction Logs (2 hrs).

4-Final Well Installations

4-Total Page 5 of 13 HW689 DC024C TACO #1 (Southgate Cleaners)

SITE :

SUBTASK:

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 4 S. Flynn

Engineer/Scientist 2 K. McDonald

Engineer/Scientist 1 W. Kesterson Engineer/Scientist 1 R. Kelley Engineering Technician 1 W. Jahns Designer 2 S. Ferianc 8

Technical Publications Specia H. Vining

Technical Publications Specia M. Comins

TOTAL LABOR 94

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

$0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method 8270 (PAHs) Soil $110.00 0 0 $0.00 EPA Method 8290 (Dioxins&Furans) Soil $950.00 0 0 $0.00 EPA Method 6010 (Total Arsenic) Soil $13.00 0 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00

Global Positioning System (Handheld G $175.00 Day 0 $0.00 55-gallon Drum $100.00 each 0 $0.00

TOTAL EQUIPMENT $0.00

Vapor Data Tabulation (3 hrs), Step Test and Radius of Influence calculations and graphs (3 hrs)

General Report Drafting

Report Document Production, Formating Tables and Text, Compilation into Adobe Format for Submittal

Compilation of Logs and Prepartion of SAR Cross Sections, Preparation of Physiography, Regional Geology and Regional Hydrogeology Sections, Preparation of Conceptual Model based on Findings, Preparation of Laboratory QA/QC Summary and Data Recommendations, Preparation of Site Assessment Conclusions, Recommendations for Assessment (24 hrs).

Southgate Cleaners (Former)

Preparation of MAGS Assessment Findings text (4 hrs), Revise and Provide Edits to Site Assessment Report (5 hrs), Preparation of Deliverable Email and Submittal of Report (1 hr)

Preparation of SAR text including, Operational History, Previous Investigations, Site Specific Soil and Groundwater Site Characterization, Preparation of Tables, Preparation of Draft Soil, Groundwater Flow and Analytical Summary Figures, Preparation of Assessment Findings (lithologic borings, soil borings, DPT Sampling, Piezometer and Monitoring Well Installations, Groundwater Sampling) (40 hrs).

5-Reporting 4/18/2024

SUBTASK:

DATE: March 20, 2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer Engineer/Scientist 5 G. Roberts Engineer/Scientist 4 S. Flynn Engineer/Scientist 2 K. Howard Engineer/Scientist 2 K. McDonald Engineer/Scientist 1 W. Kesterson Engineer/Scientist 1 R. Kelley Engineer/Scientist 1 B. Blount Engineer Scientist 1 R. Lindsay Engineering Technician 1 W. Jahns Designer 2 S. Ferianc Technical Publications Specialis H. Vining Technical Publications Specialis M. Comins

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00

Van or Truck $120.00 Day 0 $0.00

Van or Truck $480.00 Week 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF DESCRIPTION RATE UNIT USEAGE TOTALS

Hotel 1 Lindsey $150.00 Day 2 $300.00

Hotel 2 Howard, Blount $150.00 Day 4 $1,200.00

Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00

Day 1-Leave between 6 - Noon 1 Lindsey $30.00 Day 1 $30.00

Day 1-Leave between 6 - Noon 2 Howard, Blount $30.00 Day 2 $120.00

Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00

Day 1 Lindsey $36.00 Day 2 $72.00

Day 2 Howard, Blount $36.00 Day 4 $288.00

TOTAL PER DIEM $2,010.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

Survtech Solutions Survey and Benchmark Placement $2,750.00 LS 0 $0.00

Site Lines Utility Locate Services $900.00 LS 0 $0.00

Atlantic Supply MAGS Well Supplies (Casing, Screen, Sand) $883.31 LS 0 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00

EPA Method 8260 (Full List) Soil $150.00 0 0 $0.00

EPA Method 1312 SPLP Extraction (Zero Headspace Method) Soil $55.00 0 0 Contingency $0.00

EPA Method 8260 (VOHs) Leachate $73.00 0 0 Contingency $0.00

EPA Method 8260 (Full List) Well $150.00 0 0 $0.00

Sample Shipping (Small cooler) $110.00 0 $0.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00

Soil Sampling Kit (concrete) $235.00 Day 0 $0.00

MAGS Investigation Kit $500.00 Day 0 $0.00

Tedlar Bags $20.00 bag 0 $0.00

Shallow GW Sampling Kit $290.00 Day 0 $0.00

Encore Sampler $16.00 each 0 $0.00

55 Gallon Drums $100.00 each 0 $0.00

TOTAL EQUIPMENT $0.00

2-SiteMeeting, MAGS

2-Delta Page 8 of 13 HW689 DC024C TACO #1 (Southgate Cleaners)

SUBTASK:

DATE: March 20, 2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer Engineer/Scientist 5 G. Roberts Engineer/Scientist 4 S. Flynn Engineer/Scientist 2 K. Howard Engineer/Scientist 2 K. McDonald Engineer/Scientist 1 W. Kesterson Engineer/Scientist 1 R. Kelley Engineer/Scientist 1 B. Blount Engineer Scientist 1 R. Lindsay Engineering Technician 1 W. Jahns Designer 2 S. Ferianc Technical Publications Specialis H. Vining Technical Publications Specialis M. Comins

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00

Van or Truck $120.00 Day 0 $0.00

Van or Truck $480.00 Week 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF DESCRIPTION RATE UNIT USEAGE TOTALS

Hotel 1 Howard $150.00 Day 3 $450.00

Hotel 1 Blount $150.00 Day 3 $450.00

Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00

Day 1-Leave between 6 - Noon 1 Howard $30.00 Day 1 $30.00

Day 1-Leave between 6 - Noon 1 Blount $30.00 Day 2 $60.00

Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00

Day 1 Howard $36.00 Day 3 $108.00

Day 1 Blount $36.00 Day 2 $72.00

TOTAL PER DIEM $1,170.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

GW Protection DPT Drilling $8,616.00 Lump 0 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00

EPA Method 8260 (Full List) Soil $150.00 0 0 $0.00

EPA Method 1312 SPLP Extraction (Zero Headspace Method) Soil $55.00 0 0 Contingency $0.00

EPA Method 8260 (VOHs) Leachate $73.00 0 0 Contingency $0.00

EPA Method 8260 (Full List) DPT Groundwater $150.00 0 0 $0.00

EPA Method 8260 (Full List) Well/Piezometers $150.00 0 0 $0.00

EPA Method 8260 (Full List) IDW $150.00 0 0 $0.00

EPA Method 6010 (As, Cd, Cr and Pb) IDW $52.00 0 0 $0.00

EPA Method 1311 TCLP Extraction (Zero Headspace Method/VOCs)-Solid $55.00 0 0 $0.00

EPA Method 1311 TCLP Extraction (Bottle Extraction for Metals)-Solid $45.00 0 0 $0.00

Sample Shipping (Small cooler) $110.00 0 $0.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00

Soil Sampling Kit (concrete) $235.00 Day 0 $0.00

Monitor Well Installation Kit $325.00 Day 0 $0.00

Total Survey Station $50.00 Day 0 $0.00

Shallow GW Sampling Kit $290.00 Day 0 $0.00

Encore Sampler $16.00 each 0 $0.00

55 Gallon Drums $100.00 each 0 $0.00

TOTAL EQUIPMENT $0.00

3-Soil and Groundwater Field Activities

3-Delta Page 9 of 13 HW689 DC024C TACO #1 (Southgate Cleaners)

SUBTASK:

DATE: March 20, 2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer Engineer/Scientist 5 G. Roberts Engineer/Scientist 4 S. Flynn Engineer/Scientist 2 K. Howard Engineer/Scientist 2 K. McDonald Engineer/Scientist 1 W. Kesterson Engineer/Scientist 1 R. Kelley Engineer/Scientist 1 B. Blount Engineer Scientist 1 R. Lindsay Engineering Technician 1 W. Jahns Designer 2 S. Ferianc Technical Publications Specialis H. Vining Technical Publications Specialis M. Comins

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00

Van or Truck $120.00 Day 0 $0.00

Van or Truck $480.00 Week 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF DESCRIPTION RATE UNIT USEAGE TOTALS

Hotel 1 Howard $150.00 Day 1 $150.00

Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00

Day 1-Leave between 6 - Noon 1 Howard $30.00 Day 1 $30.00

Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00

Day 1 Howard $36.00 Day 1 $36.00

TOTAL PER DIEM $216.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

GW Protection Well Installations $4,642.00 LS 0 $0.00

Erwin Remediation IDW T&D Soil Drums $110.00 LS 0 $0.00

Erwin Remediation IDW T&D Liquid Drums $125.00 LS 0 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00

EPA Method 8260 (Full List) Soil $150.00 0 0 $0.00

EPA Method 1312 SPLP Extraction (Zero Headspace Method) Soil $55.00 0 0 Contingency $0.00

EPA Method 8260 (VOHs) Leachate $73.00 0 0 Contingency $0.00

EPA Method 8260 (Full List) Wells $150.00 0 0 $0.00

EPA Method 8260 (Full List) IDW $150.00 0 0 $0.00

EPA Method 6010 (As, Cd, Cr and Pb) IDW $52.00 0 0 $0.00

EPA 1311 TCLP Extraction (Zero Headspace Method/VOCs)-Soil IDW $55.00 0 0 $0.00

EPA 1311 TCLP Extraction (Bottle Extraction/Metals)-Soil IDW $45.00 0 0 $0.00

Sample Shipping (Small cooler) $110.00 0 $0.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00

Soil Sampling Kit (concrete) $235.00 Day 0 $0.00

Monitor Well Installation Kit $325.00 Day 0 $0.00

Total Survey Station $50.00 Day 0 $0.00

Shallow GW Sampling Kit $290.00 Day 0 $0.00

Encore Sampler $16.00 each 0 $0.00

55 Gallon Drums $100.00 each 0 $0.00

TOTAL EQUIPMENT $0.00

4-Final Well Installations

4-Delta Page 10 of 13 HW689 DC024C TACO #1 (Southgate Cleaners)

Proposed Scope of Work Southgate Cleaners (Former) 5317 U.S. Highway 19 (Currently 5325 U.S. Hwy 19) New Port Richey, Pasco County, FL 34652 Site Assessment and Reporting Task Assignment DC024C TACO #1 ERIC_5228 (Former Facility No. 519500354) Aptim Environmental & Infrastructure, LLC March 20, 2025

The following proposed scope of work for DC024C TACO #1 is to resolve WCD #1, approved for the former Southgate Cleaners site located in New Port Richey, Pasco County, Florida. WCD #1 was approved to allow for additional costs after several personnel changes were required during the performance of assessment activities, which will require travel expenses because some personnel were mobilizing from a different office than the proposed nearby Tampa office.

Subtask 1-Project Management

Project management hours are calculated based on the labor hours proposed in the scope of work.

Subtask 2-Preliminary Site Activities and Modified Active Gas Sampling Changes in personnel required additional travel expenses including hotel and per diem as shown on the attached Subtask 2 Level of Effort (LOE) spreadsheet.

Subtask 3-Soil Sampling & GW DPT Sampling Field Activities Changes in personnel for the soil sampling and DPT groundwater sampling required additional per diem and hotel travel expenses, as shown on the attached Subtask 3 LOE spreadsheet.

Subtask 4-Well Installations Changes in personnel for the well installation oversight will likely additional per diem and hotel travel expenses as shown on the attached LOE for Subtask 4.

WCD #1 was approved for a total of $3,400 and is being resolved for a total of $3,396.00.

Field activities for Subtask 2 and the soil sampling and drilling in Subtask 3 have been performed, and boring logs and preliminary reporting have been completed. Based on the findings, the single well installation requested by the FDEP, based on the findings, is scheduled to be installed on Friday, March 21st and sampled early next week, additional time is required to review the findings of the groundwater analytical and determine if additional work will be required. The FDEP requested that a single well be installed and sampled at the area previously demonstrating a TCE detection to determine if the assessment can be competed with a single well. Currently the Site Assessment Reporting was due February 14, 2025. A 90-day extension for the completion of the SAR is requested, to May 15, 2025, which should allow for time for the FDEP to review the results and determine the best path forward. The current TA Completion Date of April 11, 2025, will be extended to July 10, 2025.

APTIM proposes to perform this scope of work in accordance with the terms and conditions of the contract executed between APTIM Environmental & Infrastructure, LLC and Florida Department of Environmental Protection No. HW689. APTIM will begin the proposed scope of work upon issuance of the Task Assignment Notification.

If you have any questions, please contact us for clarification.

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW689

DC024C April 11, 2025

APTIM will complete Modified Active Gas Sampling, soil sampling, DPT groundwater sampling, and well installations in accordance with the Site Assessment Work Plan for the former Southgate Cleaners

Nicole Knutson 850-245-8763 Aptim Environmental & Infrastructure, LLC

Aptim Environmental & Infrastructure, LLC

Eric Kramer 407-287-3216

ERIC_5228

5317 US Highway 19, New Port Richey, Pasco County

Southgate Cleaners (former)

$ 100,556.56

$ 100,556.56

Scope of Work

Date: 2024.06.20 14:20:59 -04'00'

Teresa Booeshaghi

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2024.06.19 16:07:17 -04'00'

6/19/2024

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

File details come from the government source that posted it. Updated .