This document is a Task Assignment (TA) entered into between the State of Florida Department of Environmental Protection (FDEP) and Aptim Environmental & Infrastructure, LLC (APTIM), pursuant to an underlying Contract Number HW689. The TA, numbered DC017B, is for environmental assessment services at the Crystal Cleaners site (formerly FDEP Facility ID 509502121, now ERIC_5171) located at 2316 South Dixie Highway, West Palm Beach, Palm Beach County, Florida. The project involves site assessment and reporting conducted under the FDEP Hazardous Waste Cleanup Section.

APTIM will conduct Modified Active Gas Sampling (MAGS), soil sampling, Direct Push Technology (DPT) groundwater sampling, and well sampling, with oversight of installation of four monitoring wells. Field activities will be documented in a Site Assessment Report (SAR). The total task value is $105,396.35 on a fixed unit rate basis. The contract includes two deliverables with corresponding payment milestones: Analytical Results and Field Notes Package (Subtasks 2-4) due January 31, 2024 with payment of $86,002.26 upon FDEP approval, and Site Assessment Report & Project Management (Subtasks 5 & 1) due March 29, 2024 with payment of $19,394.09 upon FDEP approval. The final task completion date is May 31, 2024. The contract cost estimate reflects detailed labor, travel, subcontractor costs for drilling and well installation services, laboratory analysis, and field equipment across multiple subtasks, with all services to be performed in accordance with the terms and conditions of the underlying Contract HW689.

View the file

Other files

File Type Posted
CN-370000-HW689-BF01A.pdf.crdownload CRDOWNLOAD file
CN-370000-HW689-BF01D.pdf PDF
CN-370000-HW689-BIL01G.pdf PDF
CN-370000-HW689-BIL1BCO1.pdf PDF
CN-370000-HW689-BIL1BCO3.pdf PDF
CN-370000-HW689-DC001A.pdf PDF
CN-370000-HW689-DC001B.pdf PDF
CN-370000-HW689-DC001C.pdf PDF
CN-370000-HW689-DC001D.pdf PDF
CN-370000-HW689-DC002A.pdf PDF
CN-370000-HW689-DC003B.pdf PDF
CN-370000-HW689-DC004A.pdf PDF
CN-370000-HW689-DC004B.pdf PDF
CN-370000-HW689-DC005C.pdf PDF
CN-370000-HW689-DC006A.pdf PDF
CN-370000-HW689-DC008B.pdf PDF
CN-370000-HW689-DC010B.pdf PDF
CN-370000-HW689-DC011B.pdf PDF
CN-370000-HW689-DC011D.pdf PDF
CN-370000-HW689-DC012A.pdf PDF
CN-370000-HW689-DC013B.pdf PDF
CN-370000-HW689-DC014B.pdf PDF
CN-370000-HW689-DC015E.pdf PDF
CN-370000-HW689-DC019A.pdf PDF
CN-370000-HW689-DC019B.pdf PDF
CN-370000-HW689-DC024A.pdf PDF
CN-370000-HW689-DC025A.pdf PDF
CN-370000-HW689-DC028A.pdf PDF
CN-370000-HW689-DC029A.pdf PDF
CN-370000-HW689-DC02ACO1.pdf PDF
CN-370000-HW689-DC031A.pdf PDF
CN-370000-HW689-DC034A.pdf PDF
CN-370000-HW689-DC035A.pdf PDF
CN-370000-HW689-DC037A.pdf PDF
CN-370000-HW689-DC03ACO1.pdf PDF
CN-370000-HW689-DC03ACO2.pdf PDF
CN-370000-HW689-DC03CC01.pdf PDF
CN-370000-HW689-DC03DCO1.pdf PDF
CN-370000-HW689-DC05CCO1.pdf PDF
CN-370000-HW689-DC05DCO1.pdf PDF
CN-370000-HW689-DC08CCO1.pdf PDF
CN-370000-HW689-DC08CCO2.pdf PDF
CN-370000-HW689-DC08CCO3.pdf PDF
CN-370000-HW689-DC11CCO5.pdf PDF
CN-370000-HW689-DC11CCO6.pdf PDF
CN-370000-HW689-DC12BCO4.pdf PDF
CN-370000-HW689-DC13BCO2.pdf PDF
CN-370000-HW689-DC13BCO4.pdf PDF
CN-370000-HW689-DC13BCO7.pdf PDF
CN-370000-HW689-DC16CCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW689

DC017B Completion May 31, 2024

APTIM will conduct MAGS, soil sampling, DPT groundwater sampling, and well sampling. APTIM will also oversee the installation of four monitoring wells. Field activities will be documented in the SAR.

Nicole Knutson 850-245-8763 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Aptim Environmental & Infrastructure, LLC (APTIM)

Aptim Environmental & Infrastructure, LLC (APTIM)

Eric Kramer 407-287-3216

ERIC_5171

2316 South Dixie Highway (US-1), West Palm Beach, Palm Beach County

Crystal Cleaners

✔ $ 105,396.35

$ 105,396.35

Scope of Work

Eric Kramer Digitally signed by Eric Kramer Date: 2023.06.29 11:40:09 -04'00'

Teresa Booeshaghi

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.06.29 10:43:42 -04'00'

6/29/2023

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Analytical Results and Field Notes Package - Subtasks 2-4 01/31/2024

Site Assessment Report & Project Management - Subtasks 5 & 1 03/29/2024

FDEP Approval of Analytical Results and Field Notes Package - Subtasks 2-4 $ 86,002.26

FDEP Approval of Site Assessment Report & Project Management - Subtasks 5 & 1 $ 19,394.09

$ 105,396.35

HW689

DC017B

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: ERIC_5171

Crystal Cleaners

FROM: Nicole Knutson, Project Manager

SUBJECT: Negotiation Summary

HW689 DC017B

DATE: June 28, 2023

APTIM will conduct MAGS, soil sampling, DPT groundwater sampling, and well sampling. APTIM will also oversee the installation of four monitoring wells. Field activities will be documented in the SAR.

Total task amount is $105,396.35. APTIM’s time, labor, and subcontractor costs for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable due date is March 29, 2024. Task completion date is May 31, 2024.

ATTACHMENT A

COST ESTIMATE FORM/

LEVEL OF EFFORT

FDEP COST ESTI MATE

Contractor: Aptim Environmental & Infrastructure, LLC

Date: 6/9/2023

Task #: HW689 HW017B ERIC_5171 SubTask 1 Project Management SubTask 6

Site: Crystal Cleaners SubTask 2 2-SiteMeeting, MAGS SubTask 7

Activity/Phase: SAR SubTask 3 3-Soil and Groundwater Field Activities SubTask 8

Project Manager: Kelly Crain (FDEP)/Eric Kramer (APTIM) SubTask 4 4-Final Well Installations SubTask 9

SubTask 5 5-Reporting SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$68.41 Project Manager E. Kramer 34 34.0 $68.41 Engineer/Scientist 5 E. Kramer 15 2 1 2 10 0 0 0 0 0 $64.45 Engineer/Scientist 5 G. Roberts 54 9 15 6 24 0 0 0 0 0 $55.66 Engineer/Scientist 4 J. Cheze 40 0 0 0 40 0 0 0 0 0 $36.08 Engineer/Scientist 2 K. Howard 186 67 89 30 0 0 0 0 0 0 $35.31 Engineer/Scientist 2 K. McDonald 43 37 0 0 6 0 0 0 0 0 $25.12 Engineer Scientist 1 R. Lindsay 21 21 0 0 0 0 0 0 0 0 $27.29 Engineering Technician 1 J. Bell 72 36 24 12 0 0 0 0 0 0 $34.03 Designer 2 S. Ferianc 8 0 0 0 8 0 0 0 0 0 $28.89 Technical Publications Specialist 3 H. Vining 6 0 0 0 6 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 Total Hours 479 34 172 129 50 94 0 0 0 0 0

Direct Labor $20,227.05 $2,327.01 $5,950.66 $4,901.24 $1,933.40 $5,114.74 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 85.58% $17,310.30 $1,991.46 $5,092.57 $4,194.48 $1,654.60 $4,377.19 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 19.38% $3,920.00 $450.97 $1,153.24 $949.86 $374.69 $991.24 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 31.96% $6,464.56 $743.71 $1,901.83 $1,566.44 $617.91 $1,634.67 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $47,921.91 $5,513.15 $14,098.30 $11,612.02 $4,580.60 $12,117.84 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $2,400.00 $1,080.00 $960.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $2,024.00 $920.00 $902.00 $202.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $4,424.00 $2,000.00 $1,862.00 $562.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) Well Materials $1,177.59 $1,177.59 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $1,177.59 $1,177.59 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $117.76 $117.76 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $1,295.35 $1,295.35 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $12,859.00 $0.00 $8,529.00 $4,330.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $4,960.00 $4,960.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $1,000.00 $0.00 $0.00 $1,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $800.00 $800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $19,619.00 $5,760.00 $8,529.00 $5,330.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $1,961.90 $576.00 $852.90 $533.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $21,580.90 $6,336.00 $9,381.90 $5,863.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $18,404.00 $8,000.00 $8,700.00 $1,704.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $300.00 $300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $18,704.00 $8,300.00 $8,700.00 $1,704.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

FDEP COST ESTI MATE

Contractor: Aptim Environmental & Infrastructure, LLC

Date: 6/9/2023

Task #: HW689 HW017B ERIC_5171 SubTask 1 Project Management SubTask 6

Site: Crystal Cleaners SubTask 2 2-SiteMeeting, MAGS SubTask 7

Activity/Phase: SAR SubTask 3 3-Soil and Groundwater Field Activities SubTask 8

Project Manager: Kelly Crain (FDEP)/Eric Kramer (APTIM) SubTask 4 4-Final Well Installations SubTask 9

SubTask 5 5-Reporting SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $600.00 $240.00 $280.00 $80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $1,950.00 $0.00 $1,625.00 $325.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $3,928.00 $2,040.00 $1,258.00 $630.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $200.00 $100.00 $0.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $6,678.00 $2,380.00 $3,163.00 $1,135.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $100,604.16 $5,513.15 $34,409.65 $34,718.92 $13,844.60 $12,117.84 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $4,792.19 $551.32 $1,409.83 $1,161.20 $458.06 $1,211.78 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $105,396.35 $6,064.47 $35,819.48 $35,880.12 $14,302.66 $13,329.62 $0.00 $0.00 $0.00 $0.00 $0.00

LEVEL OF EFFORT / EXPENSE WORKSHEET

SITE : Crystal Cleaners

SUBTASK:

DATE: June 09, 2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 2

Engineer/Scientist 5 G. Roberts 9

Engineer/Scientist 4 J. Cheze

Engineer/Scientist 2 K. Howard 67

Engineer/Scientist 2 K. McDonald 37

Engineer/Scientist 1 R. Lindsay 21

Engineering Technician 1

J. Bell 36

Designer 2 S. Ferianc Technical Publications Speciali H. Vining

TOTAL LABOR 172

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 1 $120.00 Van or Truck $480.00 Week 2 $960.00

TOTAL VEHICLE $1,080.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 3 $130.00 Day 5 $650.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noon 3 $30.00 Day 3 $90.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 3 $36.00 Day 5 $180.00

TOTAL PER DIEM $920.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

Survtech Solutions Survey and Benchmark Placement $4,960.00 LS 1 $4,960.00 Site Lines Utility Locate Services $800.00 LS 1 $800.00 Hole Products MAGS/Well Supplies (Casing, Screen, Sand) $1,177.59 LS 1 $1,177.59

TOTAL $6,937.59

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOC Soil Vapor) $200.00 10 0 $2,000.00 EPA Method 8260 (Full List) Soil $150.00 40 0 $6,000.00 EPA Method 1312 SPLP Extraction (Zero Headspace Method) Soil $50.00 0 0 Contingency $0.00 EPA Method 8260 (VOHs) Leachate $73.00 0 0 Contingency $0.00 EPA Method 8260 (Full List) Well $150.00 0 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 2 $300.00

TOTAL LAB $8,300.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 6 $240.00 Soil Sampling Kit (concrete) $235.00 Day 2 $470.00 MAGS Investigation Kit $500.00 Day 1 $500.00 Tedlar Bags $20.00 bag 7 $140.00 Shallow GW Sampling Kit $290.00 Day 1 $290.00 Encore Sampler $16.00 each 40 $640.00 55 Gallon Drums $100.00 each 1 $100.00

TOTAL EQUIPMENT $2,380.00

Round Trip Travel for two days to site for MAGS Soil Sampling and Testing (6 hrs), Perform Onsite H&S and Scoping meetings (1 hr), Assist with Collection of 10 MAGS Soil Boring Location Samples, for the collection of 40 soil samples at depths of 6", 2', 4 and 6' (12 hrs), Assistance with Installation and Construction of 10 MAGS Testing Wells (5 hrs), Assistance with Installation of 2 Vapor Monitoring Point Locations (2 hrs), Assitance with Installation of Interior Monitoring Well, including Coring (3 hrs), Surface and Site Restoration, Drum Handling and Demobilization (3 hrs), Two Soil Sample Deliveries to Laboratory (4 hrs).

Round Trip Travel for MAGS Testing (6 hrs), Perform MAGS Tests at 10 locations and collection of 10 Vapor Samples (12 hrs), Surface and Site Restoration, Drum Handling and Demobilization (3 hrs).

Note: Air Analysis by TO-15, Soil Samples by VOCs by EPA Method 8260 (Full List)

Onsite Meeting with Property Owner and Property Manager and Utility White-lines for Markouts including travel (12 hrs), Oversight of GPR Utility Subcontract Survey (12 hrs), Oversight of Professional Site Survey (12 hrs), MAGS Testing and Soil Sampling Mobilization and Field Event Preparation (2 hrs), Round Trip Travel for two days to site for MAGS Soil Sampling and Well Installations (5 hrs), Perform Onsite H&S and Scoping meetings (1 hr), Advancement of 10 MAGS Soil Borings for the collection of 40 soil samples at depths of 6", 2', 4, and 6' (10 hrs), Assistance with Installation and Construction of 10 MAGS Testing Wells (5 hrs), Assistance with Installation of 2 Vapor Monitoring Point Locations, including coring (2 hrs), Installation of Interior Monitoring Well, including Coring (3 hrs), Preparation of Soil Boring Logs and MAGS Well Constuction Logs (3 hrs).

MAGS Analytical Data and Graph Reviews for Reporting to FDEP (2 hrs) Research and Prepare Site Access Agreement for Adjacent Properties including to the North (Church) and to the south (Parking Area) (4 hrs), Site Work Notifications, Submit Sunshine One Markout Requests (2 hrs), Summarize MAGS and MAGS Soil Data for Preliminary Reporting to FDEP (3 hrs).

2-SiteMeeting, MAGS

MAGS Testing and Soil Sampling Mobilization and Field Event Preparation (2 hrs), Travel Round Trip for MAGS Well Installations (6 hrs), Perform Onsite H&S and Scoping meetings (1 hr), Installation and Construction of 10 MAGS Testing Wells, including coring (12 hrs), Installation of 2 Vapor Monitoring Point Locations, including coring (2 hrs), Perform MAGS Tests at 10 locations and collection of 10 Vapor Samples (12 hrs), Surface and Site Restoration (2 hrs).

2-Meeting & MAGS Page 3 of 6 HW689 DC017B est (Crystal Cleaners)

SUBTASK:

DATE: June 09, 2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 4 J. Cheze

Engineer/Scientist 2 K. Howard

Engineer/Scientist 2 K. McDonald Engineer/Scientist 1 R. Lindsay

Engineering Technician 1 J. Bell

Designer 2 S. Ferianc Technical Publications Specialis H. Vining

TOTAL LABOR 129

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00 Van or Truck $480.00 Week 2 $960.00

TOTAL VEHICLE $960.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 2 $130.00 Day 5 $650.00 Day 1-leave before 6:00 AM 2 $36.00 Day 2 $72.00 Day 1-Leave between 6 - Noon 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 5 $36.00 Day 5 $180.00

TOTAL PER DIEM $902.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

Groundwater Protection DPT Drilling $8,529.00 Lump 1 $8,529.00

TOTAL $8,529.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00 EPA Method 8260 (Full List) Soil $150.00 28 0 $4,200.00 EPA Method 1312 SPLP Extraction (Zero Headspace Method) Soil $50.00 0 0 Contingency $0.00 EPA Method 8260 (VOHs) Leachate $73.00 0 0 Contingency $0.00 EPA Method 8260 (Full List) DPT Groundwater $150.00 27 0 $4,050.00 EPA Method 8260 (Full List) Well/Piezometers $150.00 3 0 $450.00 EPA Method 8260 (Full List) IDW $150.00 0 0 $0.00 EPA Method 6010 (As, Cd, Cr and Pb) IDW $39.00 0 0 $0.00 EPA Method 1311 TCLP Extraction (Zero Headspace Method/VOCs)-Solid $50.00 0 0 $0.00 EPA Method 1311 TCLP Extraction (Bottle Extraction for Metals)-Solid $45.00 0 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $8,700.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 7 $280.00 Soil Sampling Kit (concrete) $235.00 Day 2 $470.00 Monitor Well Installation Kit $325.00 Day 5 $1,625.00 Total Survey Station $50.00 Day 1 $50.00 Shallow GW Sampling Kit $290.00 Day 1 $290.00 Encore Sampler $16.00 each 28 $448.00 55 Gallon Drums $100.00 each 0 $0.00

TOTAL EQUIPMENT $3,163.00

Soil and Groundwater Samples by VOCs by EPA Method 8260 (Full List)

Remaining Soil Sampling Field Event Preparation and Mobilization (2 hrs), Round Trip Travel to site (6 hrs), Collect Remaining Soil Samples at 7 locations including, Coring, Collection of 28 Soil Samples (10 hrs), DPT Drilling Field Event Preparation and Mobilization (2 hrs), Travel to Site (5 hrs), Installation of two DPT Macrocores to 60 ft bls and installation of 3 Piezometers, DPT Groundwater Sampling at 9 locations (50 hrs), Survey Piezometers (1 hr), Daily DPT and Piezometer Groundwater Chain of Custody preparation, Sample Packaging (3 hrs), Preparation of Soil Boring and Well Construction Logs (4 hrs), Preparation of Summary Tables and Figures of Groundwater Sampling Results for Preliminary Reporting to FDEP (6 hrs).

Collect Remaining Soil Samples at 7 locations including Travel, Coring, Collection of Soil Samples (12 hrs), Site Restoration, Drum Labeling (2 hrs), Soil Sample Packaging, Chain of Custody and Sample Delivery to Laboratory (2 hrs), Groundwater Sampling and Survey Piezometers with Travel

3-Soil and Groundwater Field Activities

Finalize Proposed DPT Locations (1 hr), Finalize Proposed Piezometer Locations (1 hr).

Contacting Property Owner, Business Manager and Offsite Property Owners of Proposed Sampling Schedule and Confirming Access (2 hrs), Compilation of Field Soil Analytical Data, Preparation of Soil Summary Maps for FDEP (3 hrs), Preparation and Review of Cross Section from DPT Core for Recommendations of Proposed GW Sampling Depths with FDEP (3 hrs), Calculation of Well and Watertable Elevations for Flow Direction (2 hrs.), Preparation of Groundwater Flow Map for FDEP (3 hrs), Prepare map of Final Proposed DPT Locations (1 hr), Prepare Map of Final Proposed Piezometer Locations (1 hr).

3-Soil & GW Sampling Page 4 of 6 HW689 DC017B est (Crystal Cleaners)

SUBTASK:

DATE: June 09, 2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 2

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 4 J. Cheze

Engineer/Scientist 2 K. Howard

Engineer/Scientist 2 K. McDonald Engineer/Scientist 1 R. Lindsay

Engineering Technician 1 J. Bell

Designer 2 S. Ferianc Technical Publications Specialis H. Vining

TOTAL LABOR 50

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 3 $360.00 Van or Truck $480.00 Week 0 $0.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 1 $130.00 Day 1 $130.00 Day 1-leave before 6:00 AM 1 $36.00 Day 1 $36.00 Day 1-Leave between 6 - Noon 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 1 $36.00 Day 1 $36.00

TOTAL PER DIEM $202.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

GW Protection Well Installations $4,330.00 LS 1 $4,330.00 Erwin Remediation IDW T&D $125.00 LS 8 $1,000.00

TOTAL $5,330.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00 EPA Method 8260 (Full List) Soil $150.00 0 0 $0.00 EPA Method 1312 SPLP Extraction (Zero Headspace Method) Soil $50.00 0 0 Contingency $0.00 EPA Method 8260 (VOHs) Leachate $73.00 0 0 Contingency $0.00 EPA Method 8260 (Full List) Wells $150.00 8 0 $1,200.00 EPA Method 8260 (Full List) IDW $150.00 2 0 $300.00 EPA Method 6010 (As, Cd, Cr and Pb) IDW $52.00 2 0 $104.00 EPA 1311 TCLP Extraction (Zero Headspace Method/VOCs)-Soil IDW $55.00 1 0 $55.00 EPA 1311 TCLP Extraction (Bottle Extraction/Metals)-Soil IDW $45.00 1 0 $45.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $1,704.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 2 $80.00 Soil Sampling Kit (concrete) $235.00 Day 0 $0.00 Monitor Well Installation Kit $325.00 Day 1 $325.00 Total Survey Station $50.00 Day 1 $50.00 Shallow GW Sampling Kit $290.00 Day 2 $580.00 Encore Sampler $16.00 each 0 $0.00 55 Gallon Drums $100.00 each 1 $100.00

TOTAL EQUIPMENT $1,135.00

Collection of Final Groundwater Samples and IDW Samples, with Travel, Survey Wells, Site Restoration, Collect IDW Samples, Drum Handling (10 hrs), Chain of Custody Completion, Packaging and Delivery of FDEP PFAS Samples to Shipper (2 hrs)

Groundwater Samples by VOCs by EPA Method 8260 (Full List)

4-Final Well Installations

Prepare Recommendations for Final Well Locations (2 hrs) Property Owner and Property Manager Site Work Notifications (1 hr), Prepare Proposed Location Maps and Recommendations (3 hrs), Characterization and Waste Profile for Transportation and Disposal of IDW Drums (2 hours).

Round Trip Travel to the Site (5 hrs), Installation of final well network of 3 shallow/1 deep (12 hrs).

Collection of Final Groundwater Samples (8 wells) with travel and Survey Wells (9 hrs), Deliver final samples to laboratory (2 hrs), Preparation of Well Construction Logs (2 hrs).

4-Final Well Installations Page 5 of 6 HW689 DC017B est (Crystal Cleaners)

SITE :

SUBTASK:

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 4 J. Cheze

Engineer/Scientist 2 K. Howard

Engineer/Scientist 2 K. McDonald 6

Engineer/Scientist 1 R. Lindsay Engineering Technician 1 J. Bell Designer 2 S. Ferianc 8

Technical Publications Specia H. Vining 6

TOTAL LABOR 94

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST TOTALS

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method 8270 (PAHs) Soil $110.00 0 0 $0.00 EPA Method 8290 (Dioxins&Furans) Soil $950.00 0 0 $0.00 EPA Method 6010 (Total Arsenic) Soil $13.00 0 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00 Global Positioning System (Handheld G $175.00 Day 0 $0.00 55-gallon Drum $100.00 each 0 $0.00

TOTAL EQUIPMENT $0.00

Compilation of Logs and Prepartion of SAR Cross Sections, Preparation of Physiography, Regional Geology and Regional Hydrogeology Sections, Preparation of Conceptual Model based on Findings, Preparation of Laboratory QA/QC Summary and Data Recommendations, Preparation of Site Assessment Conclusions, Recommendations for Additional Soil and Groundwater Assessment (24 hrs).

Crystal Cleaners

Preparation of MAGS Assessment Findings text (4 hrs), Revise and Provide Edits to Site Assessment Report (5 hrs), Preparation of Deliverable Email and Submittal of Report (1 hr)

Preparation of SAR text including, Operational History, Previous Investigations, Site Specific Soil and Groundwater Site Characterization, Preparation of Tables, Preparation of Draft Soil, Groundwater Flow and Analytical Summary Figures, Cross Sections, Preparation of Assessment Findings (lithologic borings, soil borings, DPT Sampling, Piezometer and Monitoring Well Installations, Groundwater Sampling) (40 hrs).

5-Reporting 6/9/2023

Vapor Data Tabulation (3 hrs), Step Test and Radius of Influence calculations and graphs (3 hrs)

General Report Drafting Report Document Production, Formating Tables and Text, Compilation into Adobe Format for Submittal

Proposed Scope of Work Crystal Cleaners 2316 South Dixie Highway (US-1), West Palm Beach, Palm Beach County, FL 33401 Site Assessment and Reporting Task Assignment DC017B ERIC_5171 (Former Facility No. 509502101) Aptim Environmental & Infrastructure, LLC June 9, 2023

The following is the proposed scope of work for DC017B for the former Crystal Cleaners site located in West Palm Beach, Palm Beach County, Florida. The proposed scope of work under Task Assignment DC017B includes the onsite assessment of soil and groundwater, as well as the preparation of a SAR summarizing the findings of the investigation. Maps showing the proposed soil and groundwater sampling locations, are attached for convenience.

Subtask 1-Project Management Project management hours are calculated based on the labor hours anticipated in the scope of work.

Subtask 2 Meeting & MAGS Preliminary Site Activities A preliminary meeting will be held at the drycleaning location, primarily to meet onsite and discuss the proposed scope of work to be performed with the current property owner or representative. Prior to the site visit, access requests will be submitted to the surrounding properties, including the adjacent properties to the north and south, which may be necessary to complete the assessment.

Since known underground utilities exist surrounding the former drycleaner, a geophysical survey including ground-penetrating radar and electromagnetic induction will be performed to mark and document all the onsite utilities.

The preliminary site assessment activities will also include the oversight of a professional site survey and placement of benchmarks referenced to NAVD88 east and west of the former drycleaning space.

Modified Active Gas Sampling The initial assessment activity at the site will include performing modified active gas sampling (MAGS) to locate potential source areas at the site. The test should assist in identifying the locations of any suspected soil and groundwater areas that deserve additional investigation. APTIM proposes ten (10) MAGS locations inside and surrounding the space occupied by the drycleaner, as shown on Figure 5.

The MAGS extraction points will be installed with a 4-inch concrete core machine and a 3-inch auger to place a 5-foot screened interval from 1 to 6 ft bls. If the groundwater is encountered at a depth deeper or shallower than the anticipated interval, the MAGS screened interval may be adjusted to place the base of the screen to within 12-inches of the depth to groundwater. The locations will be screened continuously with a photo-ionization detector (PID) in accordance with the MAGS procedures, and an active gas sample will be collected at the end of the test for analysis by a fixed laboratory for analysis by Modified EPA Method TO-15.

Prior to the installation of the ten (10) MAGS wells, the soil samples will be collected at each location from depths of 6-inches, 2-foot, 4-foot, and 6-foot for fixed laboratory analysis. The location of the proposed MAGS soil samples is shown on Figure 6. The laboratory samples will be analyzed by Environmental

Protection Agency (EPA) Method 8260 analysis for the presence of VOCs (full list) by a fixed based laboratory. Additional material will be collected from each sample location (Encores) for possible SPLP extraction (EPA Method 1312) and analysis of the leachate for volatile organic halocarbons (VOHs) by EPA Method 8260.

Following the soil sampling and vapor extraction well installations, the MAGS testing will be performed.

During the initial MAGS test, a soil vacuum extraction (SVE) step test will be performed at one location to obtain data which can be used for SVE design, if needed. In addition, the test will determine the relationship of groundwater entrainment and vacuum extraction, if within the capacity of the test equipment. During the step test and MAGS testing, two (2) vapor monitoring points (VMPs) will be hand installed at select locations (Figure 5) to allow for collection of vacuum measurements at a distance of 10 ft and 20 ft from the vacuum extraction well being tested. The VMPs will be 1-inch diameter, with a total depth, screen interval and sand pack intervals similar to the larger diameter extraction wells.

The MAGS wells will be left in place for possible future use in the event active remediation is required, such as SVE at the site. The wells will be capped, covered with fine sand, and grouted to seal the surface. The grout seal can easily be removed for future access to the well screens. The VMPs will be removed upon completion of the vacuum extraction test.

While onsite, one shallow well will be hand-installed, inside the building at the location shown on Figure 5. The shallow well will also be constructed of 1-inch diameter PVC with 5 or 10 feet of fine mesh pre-pack 0.006-inch slotted screen with a 30/65 sand pack and installed as deep as possible, or to 15 ft bls, dependent on the depth to groundwater encountered at the site. Thereafter, the well will also be sampled for VOCs (full list) to obtain preliminary groundwater analytical data by utilizing a fixed laboratory.

Subtask 3 Soil & GW Field Activities DPT Lithologic Core To develop a lithologic cross-section of the site, two (2) continuous soil cores will be installed to approximately 60 ft bls or to refusal. The two lithologic macro-cores® will be installed by DPT drilling.

The continuous soil core will be visually characterized and logged onsite by a geologist. Special attention will be devoted to the identification of any clay-bearing and/or other low permeable strata that may serve as a confining or semi-confining layer. A qualitative moisture assessment will also be logged throughout the entire bore (wet and dry sections). The findings of the lithologic core will be used to construct the appropriate direct push sampling intervals. The proposed locations for the two lithologic borings are shown on Figure 4.

Installation of Piezometers To determine the surficial groundwater flow, three (3) piezometers will be installed following the installation of the continuous soil cores. The DPT rig will install 1-inch diameter polyvinyl chloride (PVC) piezometers screened across the water table to a total depth of approximately 15 ft bls. The shallow piezometer wells will be constructed with 10 feet of 1-inch diameter, Schedule 40 PVC fine mesh pre-pack screen constructed of a 0.006-inch slotted screen with 30/65 sand pack. The proposed locations of the piezometers are shown on Figure 4.

The piezometers will be surveyed for top of casing elevations and water levels will be measured to determine the general direction of shallow groundwater flow at the site. Thereafter, the piezometers will also be sampled for volatile organic compounds or VOCs (full list) to obtain preliminary groundwater analytical data by utilizing a fixed laboratory. The piezometers will be completed as permanent monitoring points.

Soil Sampling Subtask 3 includes the collection of the remaining seven (7) hand-augered borings will be advanced to an average depth of 6 ft bls to the water table or to the zone of collapse, whichever is first. A lithologic log will be prepared from the notes at each bore. Soil samples will be collected from depths of 6-inches, 2-foot, 4-foot, and 6-foot for fixed laboratory analysis and identification of potential source areas. The location of the proposed soil samples are shown on Figure 6. The laboratory samples will be analyzed by Environmental Protection Agency (EPA) Method 8260 analysis for the presence of VOCs (full list) by a fixed based laboratory. Additional material will be collected from each sample location (Encores) for possible SPLP extraction (EPA Method 1312) and analysis of the leachate for volatile organic halocarbons (VOHs) by EPA Method 8260.

DPT Groundwater Sampling Groundwater beneath the facility will be characterized by collecting three discrete groundwater samples from proposed direct-push technology (DPT) boring locations. Groundwater samples will be collected from nine (9) DPT locations using a GeoProbe® screen point sampler. The sampler will be advanced to the target depths of approximately 10, 20, and 30 ft bls for a total of 27 groundwater samples. The exact depth of groundwater sampling will be adjusted according to potential semi-confining layers identified during previous assessment activities including the lithologic borings. The groundwater samples will be submitted to a fixed laboratory for analysis by EPA Method 8260 for the presence of VOCs (full list).

Onsite DPT groundwater sample locations are shown on Figure 7.

Subtask 4-Well Installations After conferring with the FDEP to determine the necessary locations and depths for monitoring wells, based on the site-specific assessment data, three (3) additional shallow and one (1) deep monitoring well will be installed at the site. The shallow wells will be installed similar to the piezometers, with a direct push drilling rig. The shallow wells will be similarly constructed of 1-inch diameter PVC with 10 feet of fine mesh pre-pack 0.006-inch slotted screen with a 30/65 sand pack and installed to a 15 ft total depth, dependent on the depth to groundwater encountered at the site.

The deep well will be installed by direct push to an estimated total depth of 35 ft bls. The well will be constructed of 1-inch diameter PVC with 5 feet of fine mesh pre-pack 0.006-inch slotted screen with a 30/65 sand pack installed from 30 to 35 ft bls. A two to three foot fine silica sand seal will be installed above the screen and the remaining annulus will be tremie grouted to just below the surface.

Locations and actual installation depths for the monitoring wells will be discussed and approved by the FDEP prior to installation. The proposal funding is currently limited to the 4 additional wells discussed above. If additional wells are deemed necessary, a change order for the additional scope will be requested.

Well Sampling Groundwater samples will be collected from the piezometers (3), the hand installed interior monitoring well (1) and the exterior shallow and deep monitoring wells (4) and submitted to a State of Florida-certified fixed-base laboratory for analyses by EPA Method 8260 (full list). In addition, the proposed scope of work includes the collection of samples from up to four (4) selected monitoring wells or piezometers for analysis by DEP SOP: LC-001-3 at the FDEP State Laboratory for PFAS constituents.

During the well sampling event, soil and aqueous samples of the generated investigative-derived waste (IDW) will be sampled for characterization and disposal. Characterization soil samples will be collected for TCLP Extraction by EPA Method 1311 and leachate analysis will be performed by EPA Method 8260 (full list) and the RCRA four metals arsenic (As), cadmium (Cd), chromium (Cr) and lead (Pb) by EPA Method 6010. Liquid IDW samples will be submitted for the same analysis as the soil.

Subtask 5-SAR Reporting The soil and groundwater results will be compiled and summarized in a Site Assessment Report, prepared in accordance with the requirements of Chapter 62-780, the Contaminated Site Cleanup Criteria.

Field activities will commence in August 2023, upon approval of the task assignment. The work will be scheduled for completion by March 2024. Completion of the preliminary data, including the well network sampling results for FDEP review should be completed before January 31, 2024, and the completed SAR report should be submitted by March 29, 2024. A Task Completion date should be set for May 31, 2024, to allow for review and approval of the SAR, which will be signed and sealed upon submittal.

APTIM proposes to perform this scope of work in accordance with the terms and conditions of the contract executed between APTIM Environmental & Infrastructure, LLC and Florida Department of Environmental Protection No. HW689. APTIM will begin the proposed scope of work upon issuance of the Task Assignment Notification.

If you have any questions, please contact us for clarification.

ATTACHMENT B

PROPOSED SOW

DOCUMENTS

725 U.S. HIGHWAY 301 SOUTH

TAMPA, FLORIDA 33619

(813) 612-3600 office

(813) 626-1663 fax

INFRASTRUCTURE, LLC

APTIM ENVIRONMENTAL &

LOCATION

SITE

SITE LOCATION MAP

LOCAL LAND USE MAP

TAMPA, FLORIDA 33619

(813) 612-3600 office

(813) 626-1663 fax

INFRASTRUCTURE, LLC

APTIM ENVIRONMENTAL &

SITE MAP

725 U.S. HIGHWAY 301 SOUTH

TAMPA, FLORIDA 33619

(813) 612-3600 office

(813) 626-1663 fax

APTIM ENVIRONMENTAL & INFRASTRUCTURE, LLC

TAMPA, FLORIDA 33619

(813) 612-3600 office

(813) 626-1663 fax

APTIM ENVIRONMENTAL & INFRASTRUCTURE, LLC

PROPOSED LITHOLOGIC BORING

and PIEZOMETER LOCATION MAP

TAMPA, FLORIDA 33619

(813) 612-3600 office

(813) 626-1663 fax

APTIM ENVIRONMENTAL & INFRASTRUCTURE, LLC

PROPOSED MODIFIED ACTIVE GAS

SAMPLE LOCATION MAP

TAMPA, FLORIDA 33619

(813) 612-3600 office

(813) 626-1663 fax

APTIM ENVIRONMENTAL & INFRASTRUCTURE, LLC

PROPOSED SOIL BORING

LOCATION MAP

TAMPA, FLORIDA 33619

(813) 612-3600 office

(813) 626-1663 fax

APTIM ENVIRONMENTAL & INFRASTRUCTURE, LLC

PROPOSED DPT PUSH GROUNDWATER

ATTACHMENT C

BID SUMMARIES

Item Description Days Estimated Total Days Estimated Total Days Estimated Total Services (Mobilization 1) 3 Lump $8,529.00 5 Lump $12,800.00 4 Lump $13,525.00 Services (Mobilization 2) 1 Lump $4,330.00 1 Lump $4,535.00 1.5 Lump $8,015.00 Estimated Total Drums

Totals

Item Description Units Unit Price Total

Amount Units Unit Price Total

Amount Units Unit Price Total

Amount Pickup/Transporation 8 $51.00 $408.00 Included in Drum Disposal Cost Included in Drum Disposal Cost Disposal (soil) 4 $104.40 $417.60 4 $120.00 $480.00 4 $125.00 $500.00 Disposal (liquid) 4 $122.40 $489.60 4 $120.00 $480.00 4 $125.00 $500.00 Additional 1 $272.40 $272.40 1 $96.00 $96.00

Totals $1,179.60 $1,056.00 $1,000.00 Estimated 8 Total Drums

Vendor Bid Site Lines $800.00

GPRS $1,025.00

$1,500.00

Vendor Bid Hole Products $1,177.59 Atlantic Supply $1,201.96 Drillers Service Inc. No Response

Vendor Bid $4,960.00

US Ecology EnviroServe IDW Disposal

$17,335.00 $21,540.00 6 Total Drums 4 Total Drums 15 Total Drums

June 2, 2023

Preferred Drilling Solutions

SurvTech Solutions, Inc.

Bid Summaries Crystal Cleaners (Former)

2316 South Dixie Highway (US-1) West Palm Beach, Palm Beach County, Florida 33401

FDEP Site No. ERIC_5171 (Former FAC ID #509502121)

Well Supplies

Professional Survey

Groundwater Protection Ambient Technology

Erwin Remediation

None

GeoTek

$12,859.00

DPT Drilling

GPR Survey

Request for Quotation (RFQ) FDEP Hazardous Waste Cleanup Section (HWCS)

DPT Cores, DPT GW Sampling and Well Installations

RE: Crystal Cleaners (Former) 2316 South Dixie Highway (US-1) West Palm Beach, Palm Beach County, Florida 33401 ERIC_5171 (Former FAC ID No. 509502121)

Vendors:

SECTION 1

You are hereby invited to submit a quotation in accordance with the instructions and items below in support of Aptim Environmental & Infrastructure, Inc. (APTIM), www.aptim.com.

Please submit your complete proposal, prepared as specified herein, to APTIM by close of business 6/1/23.

Proposal submission before or on the required date by e-mail is acceptable.

SECTION 2

YOUR PROPOSAL SHOULD INCLUDE THE FOLLOWING: The omission of any of the following may deem your response as non-responsive. Note, for regular bidders only provide the following red highlighted, if the information has not been submitted within the last month.

A. Submit your proposal on the Attached Lump Sum DPT Drilling Quote Form. You may include additional backup as required.

B. Schedule of values (individual hourly rates) C. Your proposal is valid for 120 days.

D. Provide Insurance Certificate, show evidence that your Workman’s Comp insurance is valid in

Florida (if not on file with APTIM).

E. Provide Experience Modification Rate (EMR) certified by your carrier for Workmen’s Comp (if not on file with APTIM).

F. Please identify any restrictions on your ability to meet the period of performance.

SECTION 3

REQUIREMENT AND SCHEDULE:

Technical issues will be addressed by the Project Manager, Gregg Roberts at 813-612-3687 or gregg.roberts@aptim.com.

General

1. Drilling locations have the potential for exposure to chlorinated solvents. Assume Level D PPE, with APTIM conducting health and safety monitoring.

2. Sunshine Utility mark outs must be requested and performed prior to the work being performed.

In addition, the drilling contractor will also hand auger each location to a depth of 10 feet or to refusal (but not less than 5 ft bls) below the surface to check for utilities.

3. Property access arrangements will be made by APTIM. However, the drilling contractor is responsible for any necessary State or Local drilling permits, including Water Management District requirements.

4. The small property contains a single building which is an active drop-off clothes cleaning facility.

Working spaces will be extremely restricted due to the site parking limitations and the drive though pickup lanes located on the west side of the building (US-1). Water and electricity should be available from the current property owner/operator. APTIM will have more information regarding access to water and power before the work begins.

5. Drillers are to provide and utilize safety vests and cones in pedestrian, active parking and vehicle traffic areas. Some of the work could possibly be performed within the ROW of the west and south boundaries of the property, or on adjacent properties.

6. Drilling equipment must be properly decontaminated between locations in accordance with FDEP 2017 DEP-SOP-001/01 Standard Operating Procedures for Field Activities procedures.

7. Driller to provide NEW 55-gallon drums for all IDW containment (decon fluids, soil, and groundwater purge water). At the end of the project, all drums are to be consolidated to one location at the rear (south end) of the property.

18. Approximate start and completion date of the project is August 2023.

Specific:

The site location:

The former cleaners building is a single-story building located in the center of the small property.

The property is located at the northeast corner of Valencia Road and South Dixie Highway (US- 1). A church is located adjacent to the property to the north and a single family residence is located to the east.

The property was originally developed in 1959.

The former Crystal Cleaners was accepted into the Drycleaning Solvent Cleanup Program in

1997 under FDEP Facility Identification Number 509502121 (now listed as ERIC_5171). The work is being performed for the FDEP Waste Cleanup Section.

Based on the historical site screening report in the FDEP files, the Crystal Cleaners began operating in 1987 and operated until the facility was closed in 1997 (approximately 10 years).

Scope-of-Work: For bidding purposes, please consider the following scope of work for the site:

1. Advance two (2) Lithologic Cores:

a. Installation of one (1) continuous soil cores by direct push to 60 ft bls (or first refusal). The Macro cores will be installed to identify the depth to groundwater and log the lithology at the boring location. Upon completion of the lithologic core, the borehole must be properly abandoned by tremie-grouting the hole under pressure from the bottom to the surface. The approximate proposed location of the DPT lithologic core is shown on the attached figure.

2. Installation of three (3) Shallow Piezometers:

a. Utilize 3 1/4 inch OD or equivalent rods

b. 1-inch diameter, schedule 40, PVC well riser and 0.006” slotted screen installed to a total depth of 15 feet bls (or shallower, dependent on the depth to groundwater).

c. 10 feet Pre-Pak Well Screen with a 30/65 grade sand pack.

d. Flush-threaded PVC bottom caps and well riser piping.

e. Allow for borehole collapse to top of screen at 5 feet bls, then place silica sand seal (30/65 grade or equivalent) to 4 ft bls.

f. Grout borehole to within 0.5 feet bls

g. At surface, flush, 8-inch diameter steel bolt-down manhole set in high strength 2ft x 2ft concrete, pad with water-tight expandable plug well seal.

h. Please utilize a wood frame for the construction of the manhole pad, if not within concrete or asphalt.

i. The piezometers will require development by rigorously over-pumping and surging.

j. Consolidate IDW to an area on south side of the Property at a designated area for future characterization, removal and disposal.

k. The proposed locations for the three (3) Piezometers are shown on the attached figures.

3. Outdoor DPT Groundwater Sampling (Exterior):

a. Nine (9) outdoor DPT groundwater locations are proposed within the parking areas and offsite surrounding the former cleaners. Three (3) screen point groundwater samples will be collected from each location at approximately 10, 20, and 30 ft bls for the collection of a groundwater samples.

b. All bores, including DPT groundwater locations will be properly abandoned by tremie-grouting the hole under pressure from the bottom up.

c. Please include all equipment and supplies, pumps, tubing, foot valves, connectors and miscellaneous materials necessary for the collection of the groundwater samples. Sample containers will be provided by the laboratory.

d. The proposed locations for the DPT groundwater sampling are shown in the attached figures.

4. Additional Monitoring Well Installations (Separate Mobilization):

a. Note that the installation of wells will be performed separately from the DPT groundwater sampling, therefore, the Driller should include a separate mobilization for the well installations.

b. After conferring with the FDEP, the quote should include the installation of three (3) additional shallow wells and one (1) deep monitoring well.

c. The shallow wells will be installed similar to the piezometers, utilizing a direct push drilling rig.

The shallow wells will also be similarly constructed of 1-inch diameter PVC with 10 feet of fine mesh pre-pack 0.006-inch slotted screen with a 30/65 sand pack and installed to a 15 ft total depth or shallower, dependent on the depth to groundwater encountered at the site. The wells will also be flush mounted within 8-inch diameter steel bolt-down manholes.

d. The deep well will also be installed by direct push to an estimated total depth of 35 ft bls. The well will be constructed of 1-inch diameter PVC with 5 feet of fine mesh pre-pack 0.006-inch slotted screen with a 30/65 sand pack installed from 30 to 35 ft bls. A two to three foot fine silica sand seal will be installed above the screen and the remaining annulus will be tremie grouted to just below the surface. The deep well will also be flush mounted within 8-inch diameter steel bolt-down manholes.

e. The location of the final wells has not determined at this time.

Please call Gregg Roberts at (863) 670-0215 should you have any questions.

Provide the following:

1. All bidders please include the make and model of the rig intended to perform this scope-of-work.

2. Note that the actual construction and depth of the shallow wells will be dependent on the depth to shallow groundwater determined in the field.

3. Also note that all IDW will need to be consolidated to a designated area for future characterization, removal and disposal.

3. All bidders please include an estimated number of drums in their bid.

4. All bidders please include an estimated time required to complete the scope at the site.

5. Please provide an all-inclusive price quote by close of business Thursday, June 1, 2023, if possible.

SECTION 4

This request for proposal does not constitute a commitment on the part of APTIM, Offeror's proposal shall in no way be binding upon APTIM unless and until it is accepted in writing. APTIM reserves the right to reject any and/or all proposals received, and to negotiate separately with any offeror if such action is considered to be in the best interest of APTIM. APTIM shall not be liable to Offeror for any costs incurred by Offeror in the submission of its proposal in reply hereto. Offerors are cautioned to initially submit their most favorable proposal price and other factors considered. The possibility exists that APTIM may award a Purchase Order without holding discussion with any Offeror prior to award.

APTIM reserves the right to consider for award any alternate proposal if it appears to be in the best interest of APTIM. An alternate proposal providing for technical improvements and/or cost reduction considerations may be submitted. Any alternate proposal must be separately packaged and clearly marked Alternate Proposal.

Deviations and/or assumptions pursuant to the requirements stated herein shall be accompanied by rationale and explanation and clearly identified. APTIM will, if no deviations and/or assumptions are submitted, assume full compliance to the requirements set forth herein. Award will be made to that proposal determined to be most advantageous to APTIM and as a result the award may be made to other than the Offeror with the lowest proposed price. Any Purchase Order resulting from this RFQ shall be subject to the Terms and Conditions as stated below:

SECTION 5

The selected subcontractor by signing a purchase order will agree to perform the approved scope of work at the approved costs. Any changes to the scope of work or cost must be approved in writing by APTIM prior to the completion of the project. Subcontractor must notify APTIM immediately either verbally or in writing once a change in scope is identified.

No first-tier contractor or vendor awarded work under this purchase order shall further subcontract, assign, or transfer any work that costs $2,500 or more without the prior written consent of APTIM. Violations of this provision shall result in forfeiture of payment for the associated work.

The contractor represents it services and installations shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professionals under similar circumstances at the time of services are performed and that the services meet the requirements as required by State statute.

The contractor agrees to be responsible for the fulfillment of all work elements included in any subcontract consented to by APTIM and agrees to be responsible for the payment of all monies due under any subcontract in accordance with Section 287.0585, F.S. It is understood and agreed by the contractor that APTIM shall not be liable to any subcontractor or vendor for any expenses or liabilities incurred under the subcontract and that the contractor shall be solely liable to the subcontractor or vendor for all expenses and liabilities incurred under the subcontract.