Task Assignment DC006B Summary

This Task Assignment (TA) is a contract modification issued by the State of Florida Department of Environmental Protection (FDEP) to APTIM Environmental & Infrastructure, LLC for groundwater monitoring and reporting services at the House of Lorraine Valet Services site in Hallandale Beach, Broward County. The task was executed under the parent Contract Number HW689, with FDEP Project Manager Nicole Knutson (850-245-8763) and APTIM Project Manager Eric Kramer (407-287-3216) serving as the primary contacts.

The scope of work includes annual groundwater sampling for volatile organic halocarbons (VOHs) and per- and polyfluoroalkyl substances (PFAS) at eight selected monitoring wells, one recovery well, and two potentially accessible offsite wells. APTIM will collect depth-to-groundwater measurements, submit samples to fixed-base laboratories for EPA Method 8260 analysis (VOHs) and Florida DEP Laboratory analysis by Method LC-001-3 (PFAS), and prepare an Annual Groundwater Monitoring Report. Safety-Kleen was selected for investigation-derived waste (IDW) transportation and disposal at $492.75 total cost. The total fixed unit rate task value is $12,732.66, with labor costs of $9,598.76, travel costs of $240.00, subcontractor costs of $542.03, laboratory costs of $657.00, and field expenses of $735.00. The final deliverable is due July 18, 2025, with task completion by September 18, 2025.

View the file

Other files

File Type Posted
CN-370000-HW689-BF01A.pdf.crdownload CRDOWNLOAD file
CN-370000-HW689-BF01D.pdf PDF
CN-370000-HW689-BIL01G.pdf PDF
CN-370000-HW689-BIL1BCO1.pdf PDF
CN-370000-HW689-BIL1BCO3.pdf PDF
CN-370000-HW689-DC001A.pdf PDF
CN-370000-HW689-DC001B.pdf PDF
CN-370000-HW689-DC001C.pdf PDF
CN-370000-HW689-DC001D.pdf PDF
CN-370000-HW689-DC002A.pdf PDF
CN-370000-HW689-DC003B.pdf PDF
CN-370000-HW689-DC004A.pdf PDF
CN-370000-HW689-DC004B.pdf PDF
CN-370000-HW689-DC005C.pdf PDF
CN-370000-HW689-DC006A.pdf PDF
CN-370000-HW689-DC008B.pdf PDF
CN-370000-HW689-DC010B.pdf PDF
CN-370000-HW689-DC011B.pdf PDF
CN-370000-HW689-DC011D.pdf PDF
CN-370000-HW689-DC012A.pdf PDF
CN-370000-HW689-DC013B.pdf PDF
CN-370000-HW689-DC014B.pdf PDF
CN-370000-HW689-DC015E.pdf PDF
CN-370000-HW689-DC019A.pdf PDF
CN-370000-HW689-DC019B.pdf PDF
CN-370000-HW689-DC024A.pdf PDF
CN-370000-HW689-DC025A.pdf PDF
CN-370000-HW689-DC028A.pdf PDF
CN-370000-HW689-DC029A.pdf PDF
CN-370000-HW689-DC02ACO1.pdf PDF
CN-370000-HW689-DC031A.pdf PDF
CN-370000-HW689-DC034A.pdf PDF
CN-370000-HW689-DC035A.pdf PDF
CN-370000-HW689-DC037A.pdf PDF
CN-370000-HW689-DC03ACO1.pdf PDF
CN-370000-HW689-DC03ACO2.pdf PDF
CN-370000-HW689-DC03CC01.pdf PDF
CN-370000-HW689-DC03DCO1.pdf PDF
CN-370000-HW689-DC05CCO1.pdf PDF
CN-370000-HW689-DC05DCO1.pdf PDF
CN-370000-HW689-DC08CCO1.pdf PDF
CN-370000-HW689-DC08CCO2.pdf PDF
CN-370000-HW689-DC08CCO3.pdf PDF
CN-370000-HW689-DC11CCO5.pdf PDF
CN-370000-HW689-DC11CCO6.pdf PDF
CN-370000-HW689-DC12BCO4.pdf PDF
CN-370000-HW689-DC13BCO2.pdf PDF
CN-370000-HW689-DC13BCO4.pdf PDF
CN-370000-HW689-DC13BCO7.pdf PDF
CN-370000-HW689-DC16CCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW689

DC006B Completion September 18, 2025

APTIM will conduct annual groundwater sampling for VOHs and PFAS at the House of Lorraine site in Hallandale Beach, Broward County.

Nicole Knutson 850-245-8763 Contractor APTIM Environmental & Infrastructure, LLC Contractor

Contractor Eric Kramer Contractor 407 287 3216

ERIC_4075

500 East Hallandale Beach Boulevard, Hallandale Beach, Broward County

House of Lorraine Valet Services, Inc.

Contractor Contractor

✔ $ 12,732.66

$ 12,732.66

Scope of Work

APTIM Environmental & Infrastructure, LLC Contractor

Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2025.04.18 13:46:55 -04'00'

John Travis

John Travis Digitally signed by John Travis Date: 2025.04.18 11:32:37 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtasks 1-4: Annual Groundwater Monitoring Report (including PFAS reporting) &

PM 07/18/2025

Subtasks 1-4: DEP Approval of Annual Groundwater Monitoring Report (including PFAS reporting) & PM $ 12,732.66

$ 12,732.66

HW689

DC006B

FFLORIDAA DEPARTMENTT OF

EEnvironmentall Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ronn DeSantis Governor

Jeanette Nuñez Lt. Governor

Alexiss A.. Lambert Secretary

Memorandum

TO: ERIC_4075

House of Lorraine Valet Services, Inc.

FROM: Nicole Knutson, Project Manager

SUBJECT: Negotiation Summary

HW689 DC006B

DATE: , 2025

APTIM will conduct annual groundwater sampling for VOHs and PFAS at the House of Lorraine site in Hallandale Beach, Broward County. Safety-Kleen has been selected for IDW transportation & disposal services.

Total task amount is $1 . APTIM’s time, labor, and subcontractor costs for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable due date is July 18, 2025. Task completion date is September 18, 2025.

FDEP COST ESTIMATE

Contractor: Aptim Environmental & Infrastructure, LLC

Date: 4/16/2025

Task #: HW689 DC006B SubTask 1 Project Management SubTask 6

Site: House of Lorraine Valet Services ERIC_7394 SubTask 2 2-Annual Sampling SubTask 7

Activity/Phase: Groundwater Monitoring SubTask 3 3-Annual Reporting SubTask 8

Project Manager: Nikki Knutson (FDEP)/Eric Kramer (APTIM) SubTask 4 4-Additional PFAS Sampling/Reporting SubTask 9

SubTask 5 SubTask 10

TTotals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$73.18 PProject Manager E. Kramer 6 6.4 $73.18 Engineer/Scientist 5 E. Kramer 2 0 2 0 0 0 0 0 0 0 $68.63 Engineer/Scientist 5 G. Roberts 32 3 24 5 0 0 0 0 0 0 $28.77 Engineering Technician 1 J. Bell 25 22 0 3 0 0 0 0 0 0 $35.95 Designer 2 S. Ferianc 8 0 6 2 0 0 0 0 0 0 $30.00 Technical Publications Specialist 3 H. Vining 6 0 2 4 0 0 0 0 0 0 $28.00 Technical Publications Specialist 3 L. Houser 2 2 0 0 0 0 0 0 0 0

Total Hours 81 6 27 34 14 0 0 0 0 0 0

Direct Labor $4,051.47 $466.10 $894.83 $2,069.18 $621.36 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 85.58% $3,467.25 $398.89 $765.80 $1,770.80 $531.76 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 19.38% $785.18 $90.33 $173.42 $401.01 $120.42 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 31.96% $1,294.86 $148.97 $285.99 $661.31 $198.59 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $9,598.76 $1,104.29 $2,120.04 $4,902.30 $1,472.13 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $492.75 $492.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $492.75 $492.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $49.28 $49.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $542.03 $542.03 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF SHAW Page 1

FDEP COST ESTIMATE

Contractor: Aptim Environmental & Infrastructure, LLC

Date: 4/16/2025

Task #: HW689 DC006B SubTask 1 Project Management SubTask 6

Site: House of Lorraine Valet Services ERIC_7394 SubTask 2 2-Annual Sampling SubTask 7

Activity/Phase: Groundwater Monitoring SubTask 3 3-Annual Reporting SubTask 8

Project Manager: Nikki Knutson (FDEP)/Eric Kramer (APTIM) SubTask 4 4-Additional PFAS Sampling/Reporting SubTask 9

SubTask 5 SubTask 10

TTotals 1 2 3 4 5 6 7 8 9 10 LLaboratory

Analytical Costs $657.00 $657.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $$657.00 $657.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $80.00 $80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $580.00 $580.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $75.00 $75.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $735.00 $735.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $11,772.79 $1,104.29 $4,294.07 $4,902.30 $1,472.13 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $959.87 $110.43 $212.00 $490.23 $147.21 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $12,732.66 $1,214.72 $4,506.07 $5,392.53 $1,619.34 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF SHAW Page 2

LEVEL OF EFFORT / EXPENSE WORKSHEET

SITE :

SUBTASK:

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer

Engineer/Scientist 5 G. Roberts

Engineering Technician 1 J. Bell

Designer 2 S. Ferianc Technical Publications SpeciaH. Vining Technical Publications SpeciaL. Houser Update Health and Safety Plan 2

TOTAL LABOR 27

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 2 $240.00 Van or Truck $480.00 Week 0 $0.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST TOTALS

Safety-Kleen Liquid IDW T&D 1 Drum $492.75 Drum 1 $492.75

TOTAL $492.75

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method 8260 (VOHs) Wells $73.00 8 0 $584.00 EPA Method 8260 (VOHs) GW IDW $73.00 1 0 $73.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $657.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 2 $80.00 Shallow GW Sampling Kit $290.00 Day 2 $580.00 Water Level Indicator $25.00 each 0 $0.00 Poly Drum $75.00 each 1 $75.00

TOTAL EQUIPMENT $735.00

Monitoring Wells Proposed: Including MW001, MW003, MW010, MW019, MW020, MW021, RW001 (at 34 ft bls), and MW1AM by EPA Method 8260 (VOHs only). IDW (groundwater) by EPA Method 8260 (VOHs only)

Travel Preparation, Loading and Mobilization for Groundwater Sampling (2 hours), Order and Pickup Sampling Equipment (1 hr). Travel Round Trip for Groundwater Sampling, two trips (4 hrs), Open and Collect Depth to Groundwater Measurements from all wells, including interior wells (4 hrs), Sample eight wells including MW001, MW003, MW010, MW019, MW020, MW021, RW001 (at 34 ft bls), and MW1AM for VOHs by EPA Method 8260 (8 hrs). Collect IDW Sample (1 hr), Fixed Laboratory VOHs Samples preparation, Chain of custody preparation, Sample Packaging and Delivery to Laboratory (1 hr), Site Restoration and Cleanup (1 hr), 4-Additional PFAS Sampling/Reporting House of Lorraine Valet Services

April 16, 2025

Sampling Notification of Owners and Tenants for Access (1 hr), Order VOH Sampling Laboratory Kits from Fixed Laboratory (1 hr), Preparation of IDW manifest and profile and Scheduling Pickup (1 hr)

2-Sampling Page 3 of 5 DC006B House of Lorraine rev3

SUBTASK:

DATE: April 16, 2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 2

Engineer/Scientist 5 G. Roberts 24

Engineering Technician 1 J. Bell Designer 2 S. Ferianc 6

Technical Publications SpecialistH. Vining

Technical Publications SpecialistL. Houser

TOTAL LABOR: 34

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00 Van or Truck $480.00 Week 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noon 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST TOTALS

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

House of Lorraine Valet Services

Preparation of Groundwater Sampling Recommendations text and evaluation of remedial options as necessary (2 hrs), Provide Edits for Report Text, Tables and Figures (2 hrs).

Preparation of GW Elevation and Analytical Summary Results Maps (4 hrs). Update of GW Summary Tables (3 hrs), Letter Report Text and Preparation of Conclusions (26 hrs), Finalize Groundwater Tables and Figures (2 hrs)

3-Annual Reporting

Biennial Report Drafting and Map Preparation including Soil and Groundwater

Report Document Production and Formatting Tables and Text, Compilation of Attachments, Conversion into Adobe Format for Submittal

3-Reporting Page 4 of 5 DC006B House of Lorraine rev3

SUBTASK:

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer

Engineer/Scientist 5 G. Roberts

Engineering Technician 1 J. Bell

Designer 2 S. Ferianc 2

Technical Publications Specialist 3 H. Vining

TOTAL LABOR 14

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00 Van or Truck $480.00 Week 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noon 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST TOTALS

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method 8260 (VOHs) GW $73.00 0 0 $0.00 State Laboratory DEP SOP: LC-001-3 (PFAS) GW $0.00 3 1 Fld Regent Blk $0.00 State Laboratory DEP SOP: LC-001-3 (PFAS) IDW $0.00 1 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00 Shallow GW Sampling Kit $290.00 Day 0 $0.00 Poly Drum $75.00 each 0 $0.00

TOTAL EQUIPMENT $0.00

House of Lorraine Valet Services 4-Additional PFAS Sampling/Reporting

4/16/2025

Fieldwork Preparation and PFAS Kit Order with FDEP Laboratory (1 hr), Preparation and Incorporation of PFAS Text, Tables, and Figures into Annual Reporting (4 hrs)

Collection of additional PFAS samples from MW003, MW020 and RW001 (at 34 ft bls) (1 hr). Collection and document PFAS Field Regent Blank and Collection of PFAS Drum purge Water IDW Sample and Document (1 hr), Sample preparation, Chain of custody preparation, PFAS Sample Packaging and Delivery to Shipper (1 hr).

PFAS Report Drafting and Map Preparation

Report Document Production and Formatting PFAS Tables and Text, including PFAS Summary Tables, Compilation into Adobe Format for Submittal (2 hrs), Conversion of Text Files to Excel and Formatting of State Laboratory Files for FDEP (2 hrs)

Notes: Proposed PFAS Wells Expanded Monitoring, including MW003, MW020 and RW001 (at 34 ft bls), IDW, and Field Regent Blank by DEP SOP: LC-001-3 (FDEP Laboratory)

4-Additional PFAS Sampling Page 5 of 5 DC006B House of Lorraine rev3

Proposed Scope of Work Groundwater Monitoring House of Lorraine Valet Services Inc.

500 East Hallandale Beach Boulevard Hallandale Beach, Broward County, Florida 33009 Task Assignment DC0006B ERIC_4075 (Former Facility ID #069500422) Aptim Environmental & Infrastructure, LLC 3/17/2025

The following proposed Task Assignment DC006B is for continued groundwater monitoring and reporting. The scope of work was developed from discussions with the FDEP after consideration of abandonment of the existing recovery well was delayed until groundwater quality could be updated.

Subtask 2 – Groundwater Sampling:

This proposed scope of work includes the collection of depth-to-groundwater measurements from the 15 remaining House of Lorraine monitoring wells (MW001 through MW011 and MW015 through MW018), the recovery well RW001, and if accessible Mobil Station wells MW01M, MW1AM, MW08M, MW10M, MW11M. Monitoring wells MW012, MW013 and MW014 were destroyed during development of the former offsite parking area.

Following the collection of depth to groundwater measurements, eight (8) selected monitoring wells will be sampled for the presence of volatile organic halocarbons (VOHs). The proposed wells for sampling include MW001, MW003, MW010, MW019, MW020, MW021, MW1AM and the recovery well RW001 (at a depth of 34 ft bls). The samples will be submitted to a fixed base laboratory for analysis by EPA Method 8260 (VOHs only).

Investigation derived waste (IDW) generated during the groundwater sampling activities will be characterized by the collection of one liquid composite sample for analysis by EPA Method 8260 (VOHs only). Safety-Kleen has been selected to provide IDW transportation and disposal, based on bids procured for the IDW transportation and disposal.

Subtask 3 – Annual Groundwater Reporting:

An Annual Groundwater Sampling Report will be provided summarizing the collected groundwater measurements and analytical results in tables, figures and text including conclusions and recommendations.

Subtask - 4: Additional PFAS Sampling and Reporting During the collection of VOC groundwater samples, continued PFAS monitoring will be performed with the additional collection of PFAS samples from monitoring wells MW003, MW020 and RW001 (at a depth of 34 ft bls). The three (3) additional groundwater samples will be collected during the purging of the wells. One field regent blank utilizing laboratory provided PFAS-free DI water will also be collected for analysis.

The PFAS groundwater samples from the six wells will be collected in accordance with the Perfluorinated Compounds Field Sampling Protocols. The PFAS samples will be shipped to the Florida DEP Laboratory in Tallahassee, Florida, and analyzed for the presence of perfluorinated substances, by Method DEP SOP: LC-001-3, including PFOA and PFOS. The purge and decon water will also be placed in a DOT approved drum, and further characterized by the collection of an IDW sample for PFAS testing (also submitted to State Laboratory).

APTIM recommends the following schedule:

Description Due Date

Collection of Samples 5/30/2025

Submit Letter Report 7/18/2025

Task Expiration Date 8/31/2025

APTIM proposes to perform this scope of work in accordance with the terms and conditions of contract No. HW689 executed between Florida Department of Environmental Protection and APTIM Environmental & Infrastructure, LLC. APTIM will begin the proposed scope of work upon issuance of the Task Assignment Notification.

If you have any questions, please contact us for clarification.

Item Description Units Unit Price Total

Amount Units Unit Price Total

Amount Units Unit Price Total

Amount Units Unit Price Total

Amount Transporation 1 $400.00 $400.00 Disposal (soil) 0 0 0 0 Disposal (liquid) 1 $132.00 $132.00 1 $286.00 $286.00 1 $195.00 $195.00 Additional Costs/Fees 1 $145.00 $145.00 1 $206.75 $206.75 1 $350.00 $350.00

Total $677.00 No Bid $492.75 $545.00

Republic Services Clark Environmental Safety-Kleen

March 8, 2025

Included in Disposal

Erwin Remediation

Included in Disposal

IDW Pickup and Disposal Bid Summary Former House of Lorraine Valet Services, Inc.

500 East Hallandale Beach Boulevard Hallandale Beach, Florida 33009

FDEP Site No. ERIC_4075 (Former FAC ID #069500422)

Preliminary Proposal

18500 N. Allied Way Phoenix, AZ 85054 | RepublicServices.com | Environmental Services, Recycling & Waste

Rev. 6.20.24

PROPOSAL #: MS-081424-TAM

COMPANY: Aptim ADDRESS: 725 US Highway 301 South

Tampa, FL 33619 CONTACT: Gregg Roberts

PHONE: (813) 612-3687

EMAIL: gregg.roberts@aptim.com

08/14/24

Dear Gregg Roberts:

Republic Services appreciates this opportunity to provide you with environmental solutions. Following up on our earlier discussion, we are pleased to present this preliminary proposal.

Republic Services now offers comprehensive environmental solutions, including waste treatment, field and industrial services and 24/7 emergency response services. With a network of 40,000 employees and more than 175 dedicated Environmental Solutions locations, our customers benefit from working with an industry leader that can provide innovative solutions for hazardous and regulated waste, in addition to our recycling and waste services you have relied on for years.

Republic Services’ Tampa Facility offers a single source option for your waste management needs, providing premier service to companies in a wide variety of industries. This RCRA Part B facility manages most waste codes and specializes in lab packing, pharmaceutical wastes, small quantity services (LTL and household hazardous waste), waste generated by the travel/tourism industry, remediation, emergency response, and industrial cleaning.

We understand you need a professional, integrated solution, and we have designed this proposal to meet those needs. Our best-in-class customer service leverages our industry-leading capabilities and will allow us to deliver the strongest solution available in the market today. We look forward to supporting you on this project!

Scope of Work:

Republic Services’ Tampa Facilities group is please to submit this proposal to provide, labor material, and equipment necessary to properly package, transport, and dispose of designated waste materials from your location in Hallandale, FL. Republic Services proposes to perform the following work:

Properly segregate and label all designated waste materials in accordance with all applicable regulations (as necessary)

Provide all necessary shipping documents and transport the materials in licensed vehicles.

Customer/Generator prepared material must be in DOT-shippable containers.

Pricing applicable on all containers (percentage of 55-gallon drum price): 5-15 Gallons 35%; 16-

30 Gallons 75%; 31-55 Gallons 100%; 56-85 Gallons 150%; CYB 300%

Preliminary Proposal

18500 N. Allied Way Phoenix, AZ 85054 | RepublicServices.com | Environmental Services, Recycling & Waste

Rev. 6.20.24

Facility: Republic Services Tampa Facility

Treatment Type: Various

Rates:

Description Treat Group Size Unit Rate Quantity Minimums Ext Cost

IDW Liquids – Non-Regulated 1216 55 Gal $110.00 $132.00 IDW Solids – Non-Regulated 1446 55 Gal $85.00 $102.00

Profile Fee $125.00 $125.00

RCRA Haz Waste Fee - Haz Waste only 3% E-Manifest Fee $20.00

Estimated Disposal Subtotal

Transportation – Hallandale Beach, FL to Tampa, FL Size Unit Rate Quantity Minimums Ext Cost

Transportation Minimum $400.00 Container Rate 55 Gal $60.00 $60.00

Fuel Surcharge - Varies Weekly

Demurrage - After 1 Hour Free Hour

Estimated Transportation Total

Environmental, Energy & Compliance Fee 20% Included

Estimated Project Total

TERMS & CONDITIONS

THE ADDRESSEE OF THIS PROPOSAL IS THE “CUSTOMER”. “REPUBLIC SERVICES” IS THE DIVISION ENTITY IDENTIFIED BELOW THAT IS OFFERING TO PERFORM THE SERVICES. ALL SERVICES PROVIDED UNDER THIS PROPOSAL ARE SUBJECT TO REPUBLIC SERVICE’S ENVIRONMENTAL SERVICES TERMS AND CONDITIONS

(“SERVICE TERMS”) INCORPORATED HEREIN BY THIS REFERENCE AND LOCATED AT:

www.RepublicServices.com/ServiceTermsES. A HARD COPY OF THE SERVICE TERMS WILL BE PROVIDED

From: Roberts, Gregg To: Craig Burns Cc: Kramer, Eric Subject: Request for Quotation for Non-Hazardous IDW T&D – House of Lorraine (former), Hallandale Beach Date: Tuesday, August 13, 2024 7:09:00 PM Attachments: image001.png

Hello Craig:

I need an estimate to include in a proposal to pick-up and dispose of non-hazardous liquids and solids which will be generated during upcoming drilling, well removal, well installation and well development activities at the following site:

Here are the site specifics:

House of Lorraine Valet Services Inc (former) 500 East Hallandale Beach Boulevard Hallandale, Florida ERIC_4075 (Former FAC ID #069500422)

Please estimate the IDW transportation and disposal estimate is for non-hazardous waste. Please provide a Lump Sum Estimate per Drum, as the actual disposal count may vary from the estimate below:

a. 1 drum of purge/decon water (liquid)

b. 1 drum of soil/sand/mud (solid)

c. Please include transportation, disposal and preparation of the waste profiles and manifests in the cost estimate.

The former House of Lorraine Valet Services was accepted into the Drycleaning Solvent Cleanup Program in 1997 under FDEP Facility Identification Number 069500422. The work is being performed for the FDEP Waste Cleanup Section.

There is no analytical available now, but the proposal is for non-hazardous transportation and disposal. Please note that PFAS constituents have been previously identified in the groundwater beneath the former House of Lorraine Cleaners exceeding the FDEP Provisional GCTL.

Characterization of the IDW liquid and soil will both be sampled and submitted for analysis for EPA Method 8260 (VOHs only) and for PFAS constituents by method DEP SOP: LC-001-3 (FDEP Laboratory). If you need additional analysis for the waste characterization, please indicate so in your response.

I do not need a formal proposal, an email response by the end of Friday, August 16, 2024, would be appreciated.

Thank you, Gregg

GREGG ROBERTS, PG

August 16, 2024

House of Lorraine Valet Services Inc 500 East Hallandale Beach Boulevard Hallandale, Florida 33009

Dear Gregg, We are pleased to present this price estimate to you and look forward to answering any questions you may have.

Waste pickup:

Purge/Decon water - $286.00 per 55-gal drum Soil/Sand/Mud- $231.00 per 55-gal drum

Administration Fee:

Profile fee-$125.00 per profile E-Manifest fee $27.00 per pickup

Florida Recovery Fee: 12.5% of invoice ($19.50 Min and $338.00 Max)-$99.25

Total:

$286.00 x 1 $231.00 x 1 $125.00 x 2 $27.00 x 1 $99.25 $893.25

Keep in mind these prices include all fees (pickup, disposal, transportation). Safety-Kleen is a comprehensive environmental company that is fully licensed and insured, and we work with you to maintain your facility’s environmental compliance. We are ready to proceed when you say go. If you have any questions, please don’t hesitate to call me at 954-295-4782.

Sincerely, Lee McLaughlin

From: Robert Donado To: Roberts, Gregg Cc: Kramer, Eric Subject: Re: Request for Quotation for Non-Hazardous IDW T&D – House of Lorraine (former), Hallandale Beach Date: Wednesday, August 14, 2024 9:40:19 AM Attachments: image001.png

EXTERNAL SENDER

Gregg, The cost of transport of each drum of soil or water will be $195.00 per drum. A profiling fee of $350.00 will also be charged once for this site.

Thank you, Robert Donado robert@erwinremediation.com Erwin Remediation, Inc.

PO Box 884 Gulf Breeze, FL 32562

(850) 466-2358

On Tue, Aug 13, 2024 at 6:09 PM Roberts, Gregg <Gregg.Roberts@aptim.com> wrote:

Hello Robert:

I need an estimate to include in a proposal to pick up and dispose of non hazardous liquids and solids which will be generated during upcoming drilling, well removal, well installation and well development activities at the following site:

Here are the site specifics:

House of Lorraine Valet Services Inc (former)

500 East Hallandale Beach Boulevard

Hallandale, Florida

ERIC_4075 (Former FAC ID #069500422)

Please estimate the IDW transportation and disposal estimate is for non hazardous waste.

Please provide a Lump Sum Estimate per Drum, as the actual disposal count may vary from the estimate below:

a. 1 drum of purge/decon water (liquid)

b. 1 drum of soil/sand/mud (solid)

c. Please include transportation, disposal and preparation of the waste profiles and manifests in the cost estimate.

The former House of Lorraine Valet Services was accepted into the Drycleaning Solvent Cleanup Program in 1997 under FDEP Facility Identification Number 069500422. The work is being performed for the FDEP Waste Cleanup Section.

There is no analytical available now, but the proposal is for non hazardous transportation and disposal. Please note that PFAS constituents have been previously identified in the groundwater beneath the former House of Lorraine Cleaners exceeding the FDEP Provisional GCTL. Characterization of the IDW liquid and soil will both be sampled and submitted for analysis for EPA Method 8260 (VOHs only) and for PFAS constituents by method DEP SOP: LC-001-3 (FDEP Laboratory). If you need additional analysis for the waste characterization, please indicate so in your response.

I do not need a formal proposal, an email response by the end of Friday, August 16, 2024, would be appreciated.

Thank you, Gregg

GREGG ROBERTS, PG

Project Manager

APTIM | ENVIRONMENT & SUSTAINABILITY

O 813 612 3687

M 863 670 0215

E gregg.roberts@aptim.com