This document is a Task Assignment (TA) under Contract HW689 between the State of Florida Department of Environmental Protection (FDEP) and APTIM Environmental & Infrastructure, LLC. The task assignment authorizes work at the Former One Stop Cleaners site located at 3303 University Drive, Coral Springs, Broward County, Florida (Site ID ERIC_4123). The work is managed by Nicole Knutson for FDEP and Eric Kramer for APTIM, with a task completion date of July 24, 2026.

APTIM will provide remedial system operation and maintenance (O&M) services and groundwater monitoring for 12 months, including four quarters of SVE (soil vapor extraction) system operation, semi-annual and annual reporting, and groundwater sampling from designated monitoring wells. The total task value is $49,987.78, comprising $46,387.78 in fixed unit rate charges and $3,600.00 in cost reimbursement for utilities. Deliverables include quarterly O&M reports due on specified dates between July 2025 and May 2026, with invoicing tied to FDEP approval of each subtask. Erwin Remediation has been selected for IDW (investigation-derived waste) transportation and disposal. The scope excludes extensive system diagnostics and repairs, which will be estimated and funded separately as needed. Labor costs cover engineering, technician, designer, and technical publication specialist time; equipment includes expendables, O&M kits, and sampling supplies; laboratory costs cover VOC analysis and sample shipping; and subcontractor costs include electrical utility services and telemetry monitoring.

View the file

Other files

File Type Posted
CN-370000-HW689-BF01B.pdf PDF
CN-370000-HW689-BF01E.pdf PDF
CN-370000-HW689-BF1ECO1.pdf PDF
CN-370000-HW689-BIL01B.pdf PDF
CN-370000-HW689-BIL01C.pdf PDF
CN-370000-HW689-BIL01F.pdf PDF
CN-370000-HW689-BIL1ECO1.pdf PDF
CN-370000-HW689-CSS1ACO1.pdf PDF
CN-370000-HW689-DC001E.pdf PDF
CN-370000-HW689-DC002B.pdf PDF
CN-370000-HW689-DC003C.pdf PDF
CN-370000-HW689-DC009B.pdf PDF
CN-370000-HW689-DC011A.pdf PDF
CN-370000-HW689-DC011C.pdf PDF
CN-370000-HW689-DC015A.pdf PDF
CN-370000-HW689-DC015C.pdf PDF
CN-370000-HW689-DC017A.pdf PDF
CN-370000-HW689-DC018A.pdf PDF
CN-370000-HW689-DC026B.pdf PDF
CN-370000-HW689-DC03A.pdf PDF
CN-370000-HW689-DC03BCO1.pdf PDF
CN-370000-HW689-DC04BCO1.pdf PDF
CN-370000-HW689-DC05CCO2.pdf PDF
CN-370000-HW689-DC08BCO1.pdf PDF
CN-370000-HW689-DC08CCO4.pdf PDF
CN-370000-HW689-DC09CCO1.pdf PDF
CN-370000-HW689-DC11BCO1.pdf PDF
CN-370000-HW689-DC11BCO2.pdf PDF
CN-370000-HW689-DC11CCO1.pdf PDF
CN-370000-HW689-DC12BCO3.pdf PDF
CN-370000-HW689-DC13BCO6.pdf PDF
CN-370000-HW689-DC14ACO1.pdf PDF
CN-370000-HW689-DC15ACO1.pdf PDF
CN-370000-HW689-DC15DCO3.pdf PDF
CN-370000-HW689-DC15DCO4.pdf PDF
CN-370000-HW689-DC15ECO1.pdf PDF
CN-370000-HW689-DC16CCO4.pdf PDF
CN-370000-HW689-DC17BCO2.pdf PDF
CN-370000-HW689-DC17BCO3.pdf PDF
CN-370000-HW689-DC19BCO1.pdf PDF
CN-370000-HW689-DC24BCO1.pdf PDF
CN-370000-HW689-DC28ACO1.pdf PDF
CN-370000-HW689-DC29ACO3.pdf PDF
CN-370000-HW689-DC29ACO4.pdf PDF
CN-370000-HW689-DC32ACO3.pdf PDF
CN-370000-HW689-FIL10.pdf PDF
CN-370000-HW689-FIL11.pdf PDF
CN-370000-HW689-FIL14.pdf PDF
CN-370000-HW689-FIL17.pdf PDF
CN-370000-HW689-FIL18.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW689

DC003D July 24, 2026

This TA authorizes APTIM to operate and maintain the remedial system at One Stop

Cleaners for four quarters and collect VOH groundwater samples during the final quarter.

Nicole Knutson 850-245-8763 APTIM Environmental & Infrastructure

Eric Kramer 407-287-3216

ERIC_4123

3303 University Drive, Coral Springs, Broward County

Former One Stop Cleaners

$ 46,387.78

$ 3,600.00

$ 49,987.78

Scope of Work

APTIM Environmental & Infrastructure

Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2025.05.29 08:48:51 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2025.05.28 15:42:36 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Alexis A. Lambert Secretary

Memorandum

TO: ERIC_4123

Former One Stop Cleaners

FROM: Nicole Knutson, Project Manager

SUBJECT: Negotiation Summary

HW689 DC003D

DATE: May , 2025

This TA authorizes APTIM to operate and maintain the remedial system at One Stop Cleaners for four quarters and collect VOH groundwater samples during the final quarter. Erwin Remediation has been selected for IDW transportation & disposal.

Total task amount is $ . APTIM’s time, labor, and subcontractor costs for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable due date is May 22, 2026. Task completion date is July 24, 2026.

SITE :

SUBTASK:

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 6

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 1 K. McDonald 12

Engineering Technician 2 J. Bell 28

Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining

TOTAL LABOR 46

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

$0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 1 0 $200.00

EPA Method 8260 (Halos Only) $73.00 0 0 $0.00

EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00

Sample Shipping (Small cooler) $110.00 1 $110.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $310.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 3 $120.00 Construction/O&M Kit $360.00 Day 3 $1,080.00

Construction O&M Supplies $75.00 Day 3 $225.00

TOTAL EQUIPMENT $1,425.00

One Stop Cleaners

Qtr 1 O&M Apr-June 2025

4/30/2025

Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.). Submital of Quarterly reports of monthly O&M data collection sheets. (3 hrs.)

Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x 3 months = 9 hrs). SVE performance evaluation and system optimization (3 hrs).

Monthly Base Work - {Mob (1 hr), Travel Round Trip (2 hrs), SVE O&M (5 hrs) {total = 8 hrs x 3 mo = 24 hrs}. Additional work (each quarter) includes SVE Vacuum Readings and collection of VOC Vapor Sample (total 4 hrs).

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 6

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 1 K. McDonald 12

Engineering Technician 2 J. Bell 28

Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining

TOTAL LABOR 46

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

$0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 1 0 $200.00

EPA Method 8260 (Halos Only) $73.00 0 0 $0.00

EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00

Sample Shipping (Small cooler) $110.00 1 $110.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $310.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 3 $120.00 Construction/O&M Kit $360.00 Day 3 $1,080.00

Construction O&M Supplies $75.00 Day 3 $225.00

TOTAL EQUIPMENT $1,425.00

Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x 3 months = 9 hrs). SVE performance evaluation and system optimization (3 hrs).

Monthly Base Work - {Mob (1 hr), Travel Round Trip (2 hrs), SVE O&M (5 hrs) {total = 8 hrs x 3 mo = 24 hrs}. Additional work (each quarter) includes SVE Vacuum Readings and collection of VOC Vapor Sample (total 4 hrs).

One Stop Cleaners

Qtr 2 Jul-Sept 2025

4/30/2025

Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.). Submital of Quarterly reports of monthly O&M data collection sheets. (3 hrs.)

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 4

Engineer/Scientist 5 G. Roberts 2

Engineer/Scientist 1 K. McDonald 25

Engineering Technician 2 J. Bell Designer 2 S. Ferianc 3 Technical Pub Specialist 3 H. Vining 3

TOTAL LABOR 37

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

$0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00

EPA Method 8260 (Halos Only) $73.00 0 0 $0.00

EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00

Sample Shipping (Small cooler) $110.00 0 $0.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00 Construction/O&M Kit $360.00 Day 0 $0.00

Construction O&M Supplies $75.00 Day 0 $0.00

TOTAL EQUIPMENT $0.00

Semi-Annual O&M Report (Document Production)

Preparation of Semi-Annual O&M Report includes preparation of SVE operational tables, calculations, figures, O&M site visit summary, SVE system operation & performance.

Semi-Annual O&M Report (Drafting)

One Stop Cleaners

Semi-Annual Report

4/30/2025

Engineering evaluation of monthly data for first six months system operation, PE seal of Semi-Annual O&M report, evaluate data, develop recommendations and conclusions (4 hrs.)

Data quality evaluation and report documentation

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 1 K. McDonald

Engineering Technician 2 J. Bell

Designer 2 S. Ferianc

Technical Pub Specialist 3 H. Vining

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00

Van or Truck $120.00 Day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00

Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00

Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00

Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00

Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

FPL-Electrical Service April to September $300.00 Month 6 $1,800.00

Handling fee Electrical $20.00 Month 6 $120.00

EOS annula telemetry telemetry $309.00 each 1 $309.00 $2,109.00 Handling fee telemetry telemetry $20.00 each 1 $20.00

TOTAL $2,249.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00

EPA Method 8260 (Halos Only) $73.00 0 0 $0.00

EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00

Sample Shipping (Small cooler) $110.00 0 $0.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00

Construction/O&M Kit $360.00 Day 0 $0.00

Construction O&M Supplies $75.00 Day 0 $0.00

TOTAL EQUIPMENT $0.00

Utilites Quarters 1 & 2

One Stop Cleaners

4/30/2025

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 6

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 2 K. McDonald 12

Engineering Technician 2 J. Bell 28

Designer 2 S. Ferianc

Technical Pub Specialist 3 H. Vining

TOTAL LABOR 46

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00

Van or Truck $120.00 Day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00

Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00

Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00

Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00

Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 1 0 $200.00

EPA Method 8260 (Halos Only) $73.00 0 0 $0.00

EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00

Sample Shipping (Small cooler) $110.00 1 $110.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $310.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 3 $120.00

Construction/O&M Kit $360.00 Day 3 $1,080.00

Construction O&M Supplies $75.00 Day 3 $225.00

TOTAL EQUIPMENT $1,425.00

One Stop Cleaners

Qtr 3 Oct-Dec 2025

4/30/2025

Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.).

Submittal of quarterly O&M data collections sheets (3 hrs.).

Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x 3 months = 9 hrs). SVE performance evaluation and system optimization (3 hrs).

Monthly Base Work - {Mob (1 hr), Travel Round Trip (2 hrs), SVE O&M (5 hrs) {total = 8 hrs x 3 mo = 24 hrs}. Additional work (each quarter) includes SVE Vacuum Readings and collection of VOC Vapor Sample (Total 4 hrs).

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 6

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 2 K. McDonald 12

Engineering Technician 2 J. Bell 49

Designer 2 S. Ferianc

Technical Pub Specialist 3 H. Vining

TOTAL LABOR 67

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00

Van or Truck $120.00 Day 5 $600.00

TOTAL VEHICLE $600.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00

Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00

Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00

Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00

Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

Erwin Remediation Non-Haz Soil/Water T&D $195.00 Drum 1 $195.00

TOTAL $195.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

EPA Method TO-15 (VOC Soil Vapor) $200.00 1 0 $200.00

EPA Method 8260 (Halos Only) $73.00 9 0 $657.00

EPA Method 8260 (Halos Only/IDW) $73.00 1 $73.00

Sample Shipping (Small cooler) $110.00 2 $220.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $1,150.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 5 $200.00

Construction/O&M Kit $360.00 Day 5 $1,800.00

Construction O&M Supplies $75.00 Day 5 $375.00

Shallow GW Sampling Kit $290.00 Day 2 $580.00

Drum $100.00 Each 1 $100.00

TOTAL EQUIPMENT $3,055.00

Proposed groundwater samples: multi-sampling well MS003 (from 11’, 23’, 38’, 50’ bls); from monitoring wells MW007, MW012, MW016, MW028, MW030. Water level gauging in 29 monitor wells. Quarterly VOC Vapor Samples by TO-15 Modified.

Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x3 months = 9 hrs). SVE performance evaluation and system optimization (3 hrs).

Monthly Base Work - {Mob (1 hr), Travel Round Trip (2 hrs), SVE O&M (5 hrs) {total = 8 hrs x 3 mo = 24 hrs}. Additional work (each quarter) includes SVE Vacuum Readings and collection of VOC Vapor Sample (Total 4 hrs). Groundwater Sampling: Travel Preparation and Mobilization (1 hr), Round trip Travel (2 hrs). Locate and collect water levels and total depth measurements from 29 monitor wells (4 hrs). Preparation and Testing/Calibration of GW Sampling Field Equipment (1 hr/day- 2 total). Annual groundwater sampling from MS003 (from 11’, 23’, 38’, 50’ bls) and MW007, MW012, MW016, MW028, MW030 at 1 hr per sample (9 hrs), Purge Water Handling (1 hr), Sample Preparation, Chain of custody preparation, Sample Packaging, Delivery to Laboratory (1 hr). Site Restoration and Cleanup (1 hr).

One Stop Cleaners

Qtr 4 Jan-Mar 2026

4/30/2025

Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.).

Submittal of quarterly O&M data collections sheets (3 hrs.).

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer Engineer/Scientist 5 G. Roberts Engineer/Scientist 1 K. McDonald Engineering Technician 2 J. Bell Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

FPL-Electrical Service March to August $300.00 Month 6 $1,800.00 Handling fee Electrical $20.00 Month 6 $120.00

TOTAL $1,920.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00 Construction/O&M Kit $360.00 Day 0 $0.00

Construction O&M Supplies $75.00 Day 0 $0.00

TOTAL EQUIPMENT $0.00

One Stop Cleaners

Utilities Qtr 3 & 4

4/30/2025

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 4

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 2 K. McDonald 24

Engineering Technician 2 J. Bell Designer 2 S. Ferianc 3 Technical Pub Specialist 3 H. Vining 3

TOTAL LABOR 54

VEHICLE TYPE RATE UNIT USEAGE TOTALS

Automobile $80.00 Day 0 $0.00

Van or Truck $120.00 Day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE TOTALS

Hotel 0 $110.00 Day 0 $0.00

Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00

Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00

Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00

Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE TOTALS

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC TOTALS

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Annual Groundwater and O&M Report (Document Production)

Preparation of Annual O&M Report (24 hrs which includes preparation of SVE operational tables, calculations, figures, O&M site visit summary, SVE system operation & performance)

Annual Groundwater and O&M Reporting (Drafting)

One Stop Cleaners

Annual Report

4/30/2025

Engineering evaluation of monthly data, PE seal of Annual O&M report, evaluate data, develop recommendations and conclusions (4 hrs.)

Assimilate field notes and laboratory report. Prepare GW Elevation and GW Analytical Data figures (4 hrs), Prepare Groundwater Related Data Summary Text (16 hrs).

Proposed Scope of Work O&M Services & Groundwater Monitoring (12 months) Former One Stop Cleaners DC003D 3303 University Drive, Coral Springs, Broward County, FL 33065 Site ID No. ERIC_4123, Former FAC ID No. 069501160 Aptim Environmental & Infrastructure, LLC (APTIM) 4/30/25

This proposed scope of work is to provide remedial system operation and maintenance (O&M) services and groundwater monitoring activities for a period of 12 months at the former One Stop Cleaners site. Supplementing this scope outline are the Cost Estimate Form (CEF) and Level of Effort (LOE) that provides a project cost budget as Task Assignment DC003D. The proposed level of effort includes four quarters of O&M activities in support of SVE operation, annual groundwater monitoring and a semi-annual and annual report that documents the work.

Subtask 2: This task includes quarter #1 O&M services (April through June 2025) for the remedial system operation. The services include system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample (June 2025) from the remediation system for field screening with a PID and fixed base laboratory analysis. One quarterly monitoring report will be submitted as a deliverable that will present monthly O&M data for each of the three months per quarter.

Subtask 3: This task includes quarter #2 O&M services (July through September 2025) for the remedial system operation. The services include system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample (September 2025) from the remediation system for field screening with a PID and fixed base laboratory analysis. One quarterly monitoring report will be submitted as a deliverable that will present monthly O&M data for each of the three months per quarter.

Subtask 4: This task includes preparation of a semi-annual remedial system O&M report (April through September 2025) for two quarters of remedial system operation.

The O&M Report will include quarterly influent vapor analytical results, associated forms summarizing field activities performed in support of the remedial system operation, and conclusions and recommendations for continued system operation.

Subtask 5: This task includes the estimated cost associated with providing electrical power to the remedial system for the first six (6) month period of operation in this Task Assignment. The annual cost for cellular telemetry for EOS Research is included in this quarter. In addition, Broward County requires an air license that has a two-year duration, so this cost is not included in the task assignment.

Subtask 6: This task includes quarterly O&M services (October through December 2025) for the remedial system operation. The services include system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample (December 2025) from the remediation system for field screening with a PID and fixed base laboratory analysis. One quarterly monitoring report will be submitted as a deliverable that will present monthly O&M data for each of the three months per quarter.

Subtask 7: This task includes quarterly O&M services (January through March 2026) for the remedial system operation. The services include system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample (March 2026) from the remediation system for field screening with a PID and fixed base laboratory analysis. One quarterly monitoring report will be submitted as a deliverable that will present monthly O&M data for each of the three months per quarter.

In addition, this task includes annual groundwater sampling. The designated monitoring well set will remain the same as in previous years, originally based on the FDEP October 24, 2011, Deliverable Review Letter, and includes samples from multi-chambered well MS003 (from 11’, 23’, 38’, 50’ bls) and from monitoring wells MW007, MW012, MW016, MW028, and MW030. If additional wells are requested, prior to that time, based on data presented in the currently tasked annual report, the additional sampling will be incorporated into the sampling effort under a change order. Included in this subtask is IDW disposal. APTIM used a bid from a nearby site to select the lowest competent bid for this service and Erwin Remediation provided the lowest bid.

Subtask 8: This task includes the estimated cost associated with providing electrical power to the remedial system for the second six (6) month period of operation in this Task Assignment.

Subtask 9: Included in this subtask is preparation of an annual report that includes the second six months of SVE operation and maintenance, and annual groundwater sampling. The Annual Groundwater and O&M Report will be prepared summarizing the O&M data and groundwater monitoring data throughout the year of remedial system operation. The O&M Report will include quarterly influent vapor analytical results, associated forms summarizing field activities performed in support of the remedial system operation, and conclusions and recommendations for continued system operation.

A schedule of the proposed O&M, groundwater sampling, and reporting activities follows:

Qtr. 1 O&M Reporting Due Date 7/15/25

Qtr. 2 O&M Reporting Due date 10/18/25

Semi-Annual O&M Report Due Date 11/15/25

Qtr. 3 O&M Reporting Due date 1/17/26

Qtr. 4 O&M Reporting Due date 4/18/26

Annual O&M Report Due date 5/23/26

TA completion Due Date 7/26/26

This proposed scope of work does not include extensive system diagnostics and repairs.

Required diagnostic and repair services will be estimated, approved and funded individually, as required and based on O&M findings.

APTIM proposes to perform this scope of work in accordance with the terms and conditions of the contract No. HW689 that was executed December 21, 2021 between Florida Department of Environmental Protection and APTIM Environmental & Infrastructure, LLC. APTIM will begin the proposed scope of work upon written authorization. APTIM has an existing Access Agreement in place from the current site owner dated 7/2/99.

If you have any questions, please contact us for clarification.