CN-370000-HW689-BF1BCO1.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|HW689|a751b87398beb5bfc7861f19a403533e
Contract number
HW689
Issued by
Florida

About this file

Document Summary

This document is a Task Assignment Change Order (TACO #1) issued by the State of Florida Department of Environmental Protection (FDEP) to Aptim Environmental & Infrastructure, LLC under Contract HW689. The change order modifies Task Assignment BF01B for a Supplemental Site Assessment project at the U.S. 192 Solid Waste Management Facility (formerly Deseret Ranch) located in Melbourne, Brevard County, Florida. The services are being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement administered by FDEP on behalf of the U.S. Environmental Protection Agency (EPA).

The change order reflects a cost reduction of $115.68 due to the contractor's inability to locate and sample monitoring well MW041 during a December 13, 2022 sampling event. The total Task Assignment value decreased from $9,060.31 to $8,944.63, with reductions distributed across Project Management ($11.70) and SSA Activities ($103.99). The specific cost reductions resulted from decreased labor hours and laboratory analytical costs. Additionally, the completion date was extended 28 days from March 31, 2023 to April 28, 2023 to allow for report review, final approvals, and TACO processing. All invoicing is contingent upon FDEP approval of deliverables, which include the SSA Workplan and Health and Safety Plan, field documentation, and the final SSA Report with project management components. The work is funded through the SRP18 Grant (Project HW689) with a federal appropriation code of 101494.

View the file

Other files

File Type Posted
CN-370000-HW689-BF01A.pdf PDF
CN-370000-HW689-BF01C.pdf PDF
CN-370000-HW689-BF1ACO1.pdf PDF
CN-370000-HW689-BIL01CC1.pdf PDF
CN-370000-HW689-BIL01D.pdf PDF
CN-370000-HW689-BIL01E.pdf PDF
CN-370000-HW689-CSS2AC02.pdf PDF
CN-370000-HW689-DC005A.pdf PDF
CN-370000-HW689-DC007A.pdf PDF
CN-370000-HW689-DC008A.pdf PDF
CN-370000-HW689-DC012B.pdf PDF
CN-370000-HW689-DC013A.pdf PDF
CN-370000-HW689-DC015D.pdf PDF
CN-370000-HW689-DC016A.pdf PDF
CN-370000-HW689-DC016B.pdf PDF
CN-370000-HW689-DC020B.pdf PDF
CN-370000-HW689-DC020C.pdf PDF
CN-370000-HW689-DC021B.pdf PDF
CN-370000-HW689-DC022B.pdf PDF
CN-370000-HW689-DC023A.pdf PDF
CN-370000-HW689-DC024C.pdf PDF
CN-370000-HW689-DC024D.pdf PDF
CN-370000-HW689-DC030A.pdf PDF
CN-370000-HW689-DC033A.pdf PDF
CN-370000-HW689-DC03BCO2.pdf PDF
CN-370000-HW689-DC04CCO1.pdf PDF
CN-370000-HW689-DC05CCO3.pdf PDF
CN-370000-HW689-DC06BCO1.pdf PDF
CN-370000-HW689-DC10ACO1.pdf PDF
CN-370000-HW689-DC11CCO2.pdf PDF
CN-370000-HW689-DC11CCO3.pdf PDF
CN-370000-HW689-DC11CCO4.pdf PDF
CN-370000-HW689-DC11DCO1.pdf PDF
CN-370000-HW689-DC13BCO1.pdf PDF
CN-370000-HW689-DC13BCO3.pdf PDF
CN-370000-HW689-DC14BCO2.pdf PDF
CN-370000-HW689-DC15CCO1.pdf PDF
CN-370000-HW689-DC15CCO2.pdf PDF
CN-370000-HW689-DC15DCO1.pdf PDF
CN-370000-HW689-DC15DCO2.pdf PDF
CN-370000-HW689-DC17BCO4.pdf PDF
CN-370000-HW689-DC18BCO2.pdf PDF
CN-370000-HW689-DC20CCO1.pdf PDF
CN-370000-HW689-DC30ACO2.pdf PDF
CN-370000-HW689-DC32ACO1.pdf PDF
CN-370000-HW689-DC35ACO1.pdf PDF
CN-370000-HW689-FIL 3.pdf PDF
CN-370000-HW689-FIL12.pdf PDF
CN-370000-HW689-FIL19.pdf PDF
CN-370000-HW689-FIL20.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

BF01B 1 HW689

As stated in Aptim's email from 02/08/2023, sampling was performed on 12/13/2022, however MW041 could not be located and sampled. Due to this, there is a reduction in labor and lab costs.

Justin Cross 850-245-8968 Aptim Environmental & Infrastructure, LLC

Eric Kramer 407-287-3216

ERIC_7391

US Hwy 192 at Clayton Road, Melbourne, Brevard County, Florida

$ 8,944.63 $ 9,060.31

$ 8,944.63 $ 9,060.31

03/31/2023 04/28/2023 28

1 1 1

Aptim Environmental & Infrastructure, LLC

Eric Kramer Digitally signed by Eric Kramer Date: 2023.02.14 11:06:46 -05'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2023.02.14 10:44:11 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: Aptim Environmental & Infrastructure, LLC - HW689 Contract File

FROM: Justin Cross, Contract Manager

DATE: February 10, 2023

SUBJECT: Negotiation Summary – SRP18 Grant Task Assignment (TA) Change Order #1 – TA BF01BC1 U.S. 192 Brevard Co. Solid Waste Management Facility (SWMF) Supplemental Sampling

This Task Assignment Change Order (TACO) is for a reduction in labor and lab costs associated with the contractor being unable to locate MW041 during a sampling event on December 13, 2022. This work was conducted at the U.S. 192 Brevard Co. SWMF site, formerly referred to as Deseret Ranch in Melbourne, Brevard County. The services under this task are being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement that is administered by the Department on behalf of the U.S. Environmental Protection Agency (EPA).

Subtask 1: Project Management The reduction in labor hours produced a decrease in Project Management. This change resulted in a cost actual decrease of $11.70.

Subtask 2: Site Specific QAPP / Workplan No cost changes were associated with this Subtask.

Subtask 3: SSA Activities There is a reduction in labor and lab costs due to Aptim being unable to locate and sample MW041. This change resulted in a cost decrease of $103.99.

Subtask 4: SSA Report No cost changes were associated with this Subtask.

Summary The Department’s SRP Contract Manager and Aptim’s Contract Manager have both agreed to the above changes. All changes noted above represent a total overall cost decrease of $115.69, as shown in the Cost Actual LOE. The changes were noted in the TACO Request received from Aptim on February 8, 2023. The final cost associated with this TA decreased from $9,060.31 to $8,944.63 (Excel rounding error noted on CP/LOE spreadsheet). Documentation of the changes is included in the attached TACO Request, Negotiation Summary – Task Assignment Change Order #1 TA BF01BC1 U.S. 192 Brevard Co. Solid Waste Management Facility (SWMF)

– ERIC_7391

February 10, 2023 the Delta LOE spreadsheet and the Cost Actual LOE spreadsheet, and the TACO Form for BF01BC1 prepared by the Department. The final deliverable for Subtask 4 – Site Specific Activity Report, was due and received by the Department on February 3, 2023.

FDEPCOST ESTIMATE

Contractor: Aptim Environmental & Infrastructure, LLC Date: 2/8/2023

Task#: HW689 BF01A ERIC 7391 SubTask 1 Project Management Site: US192 Solid Waste Management Facility Sub Task 2 2-SSA QAPP Workplan

Activity/Phase: Supplemental Site Assessment (SSA) Sub Task 3 Project Manager: Justin Cross (FDEP)/Eric Kramer (APTIM) SubTask 4

Sub Task 5

Totals 2 3 4 5 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $70.00 $0.00 $70.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping io.oo io.oo io.oo io.oo io.oo

Total Laboratory $70.00 $0.00 $70.00 $0.00 $0.00 Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $0.00 $40.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $580.00 $0.00 $580.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) io.oo io.oo io.oo io.oo io.oo

Total Field Expenses $620.00 $0.00 $620.00 $0.00 $0.00

Subtotal $8,205.12 $850.76 $1,721.39 $2,207.43 $3,425.54 $0.00 Completion Fee $739.51 $85.08 $172.14 $139.74 $342.55 $0.00

Total Estimated Cost $8,944.631 $935.84 $1,893.53 $2,347.17 $3,768.09 $0.00

TA $9,060.31 $947.53 $1,893.53 $2,451.16 $3,768.09 $0.00

Delta ($115.69) ($11.70) $0.00 ($103.99) $0.00 $0.00

CEF Rounding Error $0.01 $0.00 $0.00 $0.01 $0.00 $0.00 $8,944.63 $935.83 $1,893.53 $2,347.18 $3,768.09 $0.00

REV: 02/03 CEF SHAW Page 2

($115.68)*

*Corrected due to rounding error Digitally signed by Jennifer Farrell Date: 2023.02.15 15:00:09 -05'00'

Eric Kramer Digitally signed by Eric Kramer Date: 2023.02.16 09:45:28 -05'00'

Cross_JL Cross-Out

Cross_JL Cross-Out

LEVEL OF EFFORT / EXPENSE WORKSHEET

SITE : US192 Solid Waste Management Facility

SUBTASK:

DATE: February 08, 2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 3 B. Dempsey

Engineer/Scientist 2 K. Howard -1 Engineering Technician 1 K. Gartland

Designer 2 S. Ferianc

Technical Pub Specialist 3 H. Vining

TOTAL LABOR -1

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00

Van or Truck $120.00 Day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $110.00 Day 0 $0.00

Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00

Day 1-Leave between 6 - Noon 0 $30.00 Day 0 $0.00

Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00

Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method 6020 (As) Groundwater $14.00 -1 0 ($14.00)

Sample Shipping (large cooler) $104.00 0 $0.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB ($14.00)

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00

Shallow GW Sampling Kit $290.00 day 0 $0.00

Water Level Indicator $25.00 Day 0 $0.00

Total Survey Station $50.00 Day 0 $0.00

55-gallon Drum $100.00 each 0 $0.00

TOTAL EQUIPMENT $0.00

3-SSA Field Activities

Order Sampling Kits (1 hr)

Notes: MW041 could not be located and Sampled

Remove Collection of Groundwater Samples from 1 Monitoring Well for EPA Method 6020 (1 hr).

3-Field Activities Delta Page 2 of 3 Copy of BF01B TACO #1 est (003).xlsx

SUBTASK:

DATE: October 11, 2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 3 B. Dempsey

Engineer/Scientist 2 K. Howard

Engineering Technician 1 K. Gartland

Designer 2 S. Ferianc

Technical Pub Specialist 3 H. Vining

TOTAL LABOR 22

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00

Van or Truck $120.00 Day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $110.00 Day 0 $0.00

Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00

Day 1-Leave between 6 - Noon 0 $30.00 Day 0 $0.00

Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00

Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method 6020 (As) Groundwater $14.00 5 1 Equip(1) $84.00

Sample Shipping (large cooler) $104.00 0 $0.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $84.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 1 $40.00

Shallow GW Sampling Kit $290.00 day 2 $580.00

Water Level Indicator $25.00 Day 0 $0.00

Total Survey Station $50.00 Day 0 $0.00

55-gallon Drum $100.00 each 0 $0.00

TOTAL EQUIPMENT $620.00

Mobilization for Groundwater Samling (1 hr), Round trip Travel to Site (4 hrs). Locate, Open, Collect Depth to Groundwater Measurements from the wells proposed to be sampled, clear surrounding area for Sampling (1 hr). Preparation and Testing/Calibration of GW Sampling Field Equipment (1 hr).

Collection of Groundwater Samples from 2 Monitoring Wells for EPA Method 6020, total arsenic (2 hrs). Site Restoration (1 hr).

Notes: Proposed sampling MW018, MW028, MW031, MW041 and MW042 (5 Total Wells), and equipment blank by EPA Method 6020

3-SSA Field Activities

Order Sampling Kits (1 hr)

Mobilization for Groundwater Samling (1 hr), Round trip Travel to Site (4 hrs). Locate, Open, Collect Depth to Groundwater Measurements from the wells proposed to be sampled, clear surrounding area for Sampling (1 hrs). Preparation and Testing/Calibration of GW Sampling Field Equipment (1 hr).

Collection of Groundwater Samples from 3 Monitoring Wells for EPA Method 6020, total arsenic (3 hrs). Chain of custody preparation, Sample Packaging, Delivery of Samples to Laboratory (2 hrs).

3-SSA Field Activities Page 1 of 3 Copy of BF01B TACO #1 est (003).xlsx

SUBTASK:

DATE: February 08, 2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

TITLE STAFF WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer

Engineer/Scientist 5 G. Roberts 1 Engineer/Scientist 3 B. Dempsey

Engineer/Scientist 2 K. Howard

Engineering Technician 1 K. Gartland

Designer 2 S. Ferianc

Technical Pub Specialist 3 H. Vining

TOTAL LABOR 22

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00

Van or Truck $120.00 Day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $110.00 Day 0 $0.00

Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00

Day 1-Leave between 6 - Noon 0 $30.00 Day 0 $0.00

Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00

Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method 6020 (As) Groundwater $14.00 4 1 Equip(1) $70.00

Sample Shipping (large cooler) $104.00 0 $0.00

Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $70.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 1 $40.00

Shallow GW Sampling Kit $290.00 day 2 $580.00

Water Level Indicator $25.00 Day 0 $0.00

Total Survey Station $50.00 Day 0 $0.00

55-gallon Drum $100.00 each 0 $0.00

TOTAL EQUIPMENT $620.00

3-SSA Field Activities

Order Sampling Kits (1 hr)

Mobilization for Groundwater Samling (1 hr), Round trip Travel to Site (4 hrs). Locate, Open, Collect Depth to Groundwater Measurements from the wells proposed to be sampled, clear surrounding area for Sampling (1 hr). Preparation and Testing/Calibration of GW Sampling Field Equipment (1 hr).

Collection of Groundwater Samples from 2 Monitoring Wells for EPA Method 6020, total arsenic (2 hrs). Site Restoration (1 hr).

Notes: Proposed sampling MW018, MW028, MW031, MW041 and MW042 (5 Total Wells), and equipment blank by EPA Method 6020

Mobilization for Groundwater Samling (1 hr), Round trip Travel to Site (4 hrs). Locate, Open, Collect Depth to Groundwater Measurements from the wells proposed to be sampled, clear surrounding area for Sampling (1 hrs). Preparation and Testing/Calibration of GW Sampling Field Equipment (1 hr).

Collection of Groundwater Samples from 2 Monitoring Wells for EPA Method 6020, total arsenic (2 hrs). Chain of custody preparation, Sample Packaging, Delivery of Samples to Laboratory (2 hrs).

3- Field Activities Total Page 3 of 3 Copy of BF01B TACO #1 est (003).xlsx

Proposed Scope of Work U.S. 192 Solid Waste Management Facility Former Deseret Ranch Supplemental Site Assessment Task Assignment BF01B TACO #1 ERIC_7391 (Former COM_312749) Aptim Environmental & Infrastructure, LLC February 8, 2023

The following Task Assignment Change Order (TACO) for the former Deseret Ranch and future U.S. 192 Brevard County Solid Waste Management Facility, located in Melbourne, Brevard County, Florida has been prepared to remove the costs associated with the field personnel being unable to locate and sample MW-41 while onsite. The TACO #1 removes the sampling and analytical costs associated with that well.

Subtask 3: SSA Field Activities:

Subtask 3 includes the collection of groundwater samples from monitoring wells MW018, MW028, MW031, MW041 and MW042. However, upon arrival for groundwater sampling on December 13, 2022, monitoring well MW041 was not located and could not be sampled. As previously reported, the site appeared to have been cleared, likely by a tractor or skid steer brush cutter. For that reason, many of the wells could not be located and the stakes and flags placed at all the well locations were missing, making location of the wells difficult.

TACO #1 removes the associated sampling labor and analytical costs for the well (MW041) that was not located and therefore, not sampled.

Field activities have been completed and the report has been submitted to the FDEP for review.

However, a 30-day extension to the BF01B TA Completion Date (March 31, 2023) is requested to allow for report review and final approvals, as well as processing the TACO. The extension would change the TA Completion date to April 28, 2023.

APTIM proposes to perform this scope of work in accordance with the terms and conditions of the contract No. HW689executed between Florida Department of Environmental Protection and APTIM Environmental & Infrastructure, LLC. APTIM will begin the proposed scope of work upon issuance of the Task Assignment Notification.

If you have any questions, please do not hesitate to call.