Attachment 3 - AF Form 66.xlsx
XLSX spreadsheet 69 KB Posted
- Attached to
- Repair Roof Base Ops, B847
- Solicitation number
- FA302225R0003
About this file
The document is an Air Force Form 66 (AF Form 66) Schedule of Material Submittals for Project No. EEPZ246823, detailing a roof repair project for Base Ops Building 847. The submittal schedule covers multiple disciplines including general, environmental, architectural, civil, mechanical, electrical, special systems, and miscellaneous categories, with specific documentation requirements for the roofing project.
Key submittal requirements include project schedules, demolition plans, drawing submittals at 15%, 35%, 95%, and 100% completion stages, metal roof panel details, mechanical fasteners, insulation, and shop drawings. Environmental submittals include safety data sheets, hazardous waste and material reports, storm water pollution prevention plan, state licensing documentation for asbestos work, and disposal manifests. Additional unique requirements include an airfield waiver with detailed site plan, equipment type, maximum height, and work schedule information. The project is part of a Department of the Air Force Air Education and Training Command solicitation (FA302225R0003) with a project value between $500,000 and $1,000,000, scheduled for roof replacement to eliminate water leaks in Building 847.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ246823 | Repair Base Ops Standing Seam Roof, B847 | 25-Feb-25 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 1 | Schedule of Material Submittals (AF Form 66) | SOW | x | ||||||||||||||||
| 2 | Project Schedule | SOW | x | ||||||||||||||||
| 3 | Demolition Plan | SOW | x | ||||||||||||||||
| 4 | 15% Drawing Submittal | SOW | x | ||||||||||||||||
| 5 | 35% Drawing Submittal | SOW | x | ||||||||||||||||
| 6 | 95% Drawing Submittal | SOW | x | ||||||||||||||||
| 7 | 100% Drawing Submittal | SOW | x | ||||||||||||||||
| 8 | Metal Roof Panals | SOW | x | x | x | x | |||||||||||||
| 9 | Mechanical Fasteners | SOW | x | x | x | ||||||||||||||
| 10 | Insulation | SOW | x | x | x | ||||||||||||||
| 11 | Sheathering Material and Fabrication Shop Drawings | SOW | x | ||||||||||||||||
| 12 | Blocking Material, Installation and Shop Drawings | SOW | x | ||||||||||||||||
| 13 | Superintendent's Qualifications and Experience | SOW | x | ||||||||||||||||
| 14 | QC Manager's Qualifications and Experience | SOW | x | ||||||||||||||||
| 15 | Contractor Project Manager's Qualifications and Experience | SOW | x | ||||||||||||||||
| 16 | Completed DD Form 1354 | SOW | x | ||||||||||||||||
| 17 | As-Built Drawings | SOW | x | ||||||||||||||||
| 18 | Guarantees and Warranties | SOW | x |
AF Form 66 (Substitute) GENERAL Page&Pof&N
SCHEDULE OF MATERIAL SUBMITTALS
Environmental
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ246823 | Repair Base Ops Standing Seam Roof, B847 | 25-Feb-25 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 7 | Appropriate SDS | BASIC | |||||||||||||||||
| 8 | Hazardous waste report | BASIC | |||||||||||||||||
| 9 | Hazardous Material Report (AF Form 3000) | BASIC | |||||||||||||||||
| 10 | Recycled Material Report/Construction Debris report | BASIC | |||||||||||||||||
| 11 | Storm Water Pollution Prevention Plan with Best Management Practices Identified | BASIC | |||||||||||||||||
| 12 | Weekly Inspection Reports for Projects | BASIC | |||||||||||||||||
| 13 | State Licenses for workers and supervisors (Asbestos) | BASIC | |||||||||||||||||
| 14 | State license for the firm (Asbestos) | BASIC | |||||||||||||||||
| 15 | 10 Day Notification (Demolition and Asbestos) | BASIC | |||||||||||||||||
| 16 | Work Plan | BASIC | |||||||||||||||||
| 17 | Copy of ACM DisposalManifest | BASIC |
AF Form 66 (Substitute) Environmental Page&Pof &N
SCHEDULE OF MATERIAL SUBMITTALS
Architectural
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ246823 | Repair Base Ops Standing Seam Roof, B847 | 25-Feb-25 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 14 | NONE |
AF Form 66 (Substitute) Architectural Page&Pof&N
Civil
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ246823 | Repair Base Ops Standing Seam Roof, B847 | 25-Feb-25 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| NONE |
AF Form 66 (Substitute) CIVIL Page&Pof &N
Mechanical
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ246823 | Repair Base Ops Standing Seam Roof, B847 | 25-Feb-25 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 17 | NONE |
AF Form 66 (Substitute) Mechanical Page&Pof&N
Electrical
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ246823 | Repair Base Ops Standing Seam Roof, B847 | 25-Feb-25 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| NONE |
AF Form 66 (Substitute) Electrical Page&Pof &N
Special Systems
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ246823 | Repair Base Ops Standing Seam Roof, B847 | 25-Feb-25 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 26 | NONE |
AF Form 66 (Substitute) Special Systems Page&Pof &N
Other&Misc
| Project No: | Project Title: | Date: | |||||||||||||||||
| EEPZ246823 | Repair Base Ops Standing Seam Roof, B847 | 25-Feb-25 | |||||||||||||||||
| LINE NO. | ITEM DESCRIPTION | SPEC REF | NUMBER OF COPIES REQUIRED | DATE KTR REQUIRES APPROVAL | DATE RECEIVED KTR | DATE TO CIVIL ENG | DATE RECEIVED FROM CE | DATE CONTRACTOR NOTIFIED APR DISAPR | CONTRACT RESUBMIT DUE | CONTRACT RESUBMITTAL RECEIVED | FINAL APPROVAL RCVD KTR NOTIFIED | ||||||||
| Certificate of Compliance | Shop Drawings | Samples | Color Selction | Manufacturer's Recommendations | Manufacturer's Warranty | Catalog Data | Operating Instructions | Other | |||||||||||
| GENERAL | |||||||||||||||||||
| 26 | Airfield Waiver | ||||||||||||||||||
| Prepared by CE but contractor must supply: | |||||||||||||||||||
| 1. Site Plan/Area of Work | |||||||||||||||||||
| 2. Type of Equipment to be used | |||||||||||||||||||
| 3. Maximum height of equipment | |||||||||||||||||||
| 4. Work Hours (24/7, nights, non-flying, etc). | |||||||||||||||||||
| 5. Work Schedule |