SCHEDULE OF MATERIALS SUBMITTALS PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.

FXSB19-1095

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

L I N E

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT PREFERENCE, TYPE OF

SUBMITTAL

C E

R

TI

FI

C

A

TI

O N

O F

C O

M P

LI

A

N C

E

D R

A W

IN

G

S

P

LA

N

M S

D S

M A

N F'

R R

E C

O M

M E

N D

A

TI

O N

S

R E

Q U

E S

T

LE

TT

E

R

C A

TA

LO

G D

A

TA

R E

P O

R

TS

O

TH

E R

D A

TA

TE

S

T R

E S

U

LT

S

REQUIRED

SUBMISSION

DATE

DATE

RECEIVED IN

CONTRACTIN

G

DATE TO CIVIL

ENGINEERING

RETURN

SUSPENSE DATE

FOLLOW-UP

DATE CONTRACTOR

NOTIFIED

CONTRACTOR RE-

SUBMITTAL

FINAL APPROVAL REMARKS

1 Section 01010, para. 2.1 Notice of Start of Work

10 days prior to start of any work

2 Section 01010, para. 5.7 Record Drawings

30 days after completion of Work

3 Section 01010, para. 8.1 Utility Outages

14 Days prior to start of start of work

4 Section 01010, para. 9.1 Form 3

After completion of Form

5 Section 01010, para. 13.1 Fence Plan

1 NTP +10 Days

6 Section 01010, para. 26.7 Quality Control Plan

1 20 Days after

NTP

7 Section 01120, para. 5.1.2.1 Material Safety Data Sheet

30 days before brought on Base

8 Section 01120, para. 7.

Radioactive Usage Request

1 60 days prior to start of work

9 Section 01120, para. 8 Fuel Spill Clean Up Plan

1 prior to work start

Section 02200, Para. 1.3 Compaction Test Result 1

3 Days after completion of test

Section 02600 Hot Mix Asphalt Design Mix 1 1 NTP +10 Days

Section 02600 AC Testing and Sampling 1

3 Days after completion of test

Section 02600, Base Course gradation 1

3 Days after completion of test

Section 02600 Tack Coat product data sheet 1 NTP +10 Days

Section 02660 Waterline Materials Product Data 1 NTP +10 Days

Chapel Waterline Repair Bldg 7148

SCHEDULE OF MATERIALS SUBMITTALS PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.

FXSB19-1095

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

L I N E

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT PREFERENCE, TYPE OF

SUBMITTAL

C E

R

TI

FI

C

A

TI

O N

O F

C O

M P

LI

A

N C

E

D R

A W

IN

G

S

P

LA

N

M S

D S

M A

N F'

R R

E C

O M

M E

N D

A

TI

O N

S

R E

Q U

E S

T

LE

TT

E

R

C A

TA

LO

G D

A

TA

R E

P O

R

TS

O

TH

E R

D A

TA

TE

S

T R

E S

U

LT

S

REQUIRED

SUBMISSION

DATE

DATE

RECEIVED IN

CONTRACTIN

G

DATE TO CIVIL

ENGINEERING

RETURN

SUSPENSE DATE

FOLLOW-UP

DATE CONTRACTOR

NOTIFIED

CONTRACTOR RE-

SUBMITTAL

FINAL APPROVAL REMARKS

Chapel Waterline Repair Bldg 7148

Section 03000 Concrete Mix Design 1 NTP +10 Days

Operation of the On-Base Gravel Extraction 1 1

If used, submit before any extraction work

AF66e.XLS