Attachment 03 AF Form 66.xls

Air Force Form XLS spreadsheet 47 KB Posted

Attached to
Repair Marina Infrastructure
Solicitation number
FA481920R0024
Issued by

About this file

This document contains a material submittals schedule template for a federal construction project. The template includes columns for the project and contract numbers, item descriptions, required submission dates from the contractor, dates the submittals were received and sent to the civil engineering team for review, return suspense dates, submittal numbers, and dates for approval or disapproval notifications to the contractor. The related federal contract opportunity is a solicitation by the 325th Contracting Squadron at Tyndall AFB, Florida to complete repair work outlined in the statement of work on the base's marina infrastructure. The solicitation number, project name, opportunity type, issuing agency, and a brief description are provided.

View the file

Other versions and copies of AF Form 66

File Revision Posted Attached to
Attachment 09-AF form 66 03.27.2025.pdf Mar 27, 2025 B611 HVAC Repair
Attachment 2 AF Form 66.pdf Revision not stated REPAIR AC PAVING
AF form 66 Blank.pdf Revision not stated Demo Mini mute sites
AF Form 66-EEPZ260842 Renovate Convert Comm to SAPR B730.xlsx Revision not stated B730 Renovate Convert Comm to SAPR
AF Form 66 B268.xlsx Revision not stated B268 Replace STUS Backup Generator
AF Form 66 B730.xlsx Revision not stated B730 - Renovate RM106 for Emergency Operations Center
AF Form 66.xlsx Revision not stated B836 Replace Electrical in Airfield Lighting Vault
AF Form 66 OSI Flooring.xlsx Revision not stated OSI B926 Flooring
EEPZ254660 Repair Control Tower HVAC B1806 - AF Form 66.xlsx Revision not stated B1806 Repair Control Tower HVAC
AF Form 66 Template.xlsx Revision not stated Replace AAS BAK-15 Controls, B2001, B2003
AF Form 66 EEPZ216808 Replace Security Forces Elevator B926.xlsx Revision not stated B926 Replace Security Forces Elevator
WT 17518487 AF Form 66.xlsx Revision not stated Repair Structural Fire Trainer B17903, 17904
AF Form 66.xlsx Revision not stated RENOVATE/CONVERT 50th 49th SQ OPS, B230
AF Form 66.xlsx Revision not stated T-6 Flightline Shacks
AF Form 66 Template.xlsx Revision not stated Replace Fire Alarms, Multi Facility
EEPZ248229 -- AF Form 66.xlsx Revision not stated Repair Kiddie Pool
Atch 2 AF Form 66.pdf Revision not stated Removal of Underground Storage Tank at Launch Facility E-10 (Laramie County, WY)
Attachment 4 - AF Form 66 Submittal Register.pdf Revision not stated Bldg 65 - Renovation of Telephone Office Area, FE Warren AFB, WY AMENDMENT 03
Attachment 7 - AF Form 66.xlsx Revision not stated Replace Chapel Windows B912
04 - AF form 66.xlsx Revision not stated New Poinsett Tower Installation
Show all 20

Who attaches AF Form 66

State Files
Iowa 1
Massachusetts 1

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

Project Number:
[ enter here ]Project Title:
[ enter here ]Solicitation / Contract Number:

[ enter here ]

Line Number(To be completed by Project Engineer)(To be completed by Contract Administrator)
Number of Copies RequiredRemarks
Item or Description of Item, Contract Reference, Type of SubmittalCertificate of ComplianceShop DrawingsSamplesColor SelectionManufacturer's RecommendationManufacturer's WarrantyCatalog DataOperating InstructionsSchedules, Listings, Reports, PlansTechnical DataTest ReportsField ReportsRequired Submission DateDate Received in ContractingDate to Civil EngineeringReturn Suspense DateSubmittal NumbersDate Contractor
NotifiedContractor ResubmittalFinal Approval
ApprovedDisapproved
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25

&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).

&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE

(MM/DD/YY)

Enter the Submittal Number Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Enter Resubmittal Number Enter the submittal final approval date

(MM/DD/YY)