About this file

This document contains a submittal register and federal contract opportunity for replacing carpet in Building 34 at FE Warren AFB, Wyoming. The contractor shall supply, deliver, and install carpet for rooms 290, 292, 293, 294, 295, and 299 by 13 March 2024. The submittal register requires the contractor to submit a hazardous materials authorization form, carpet tile color choices, and a one-year workmanship warranty. A statement from the installer confirming prices are at or below tier 1 contract rates must be included with the quote. The site visit date to arrange measurements will be coordinated by the contracting specialist. The Department of the Air Force Global Strike Command is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to B34 Purchase and Install Carpet, FE Warren AFB, WY AMENDMENT 02, newest first.
File Type Posted
Atch 6 Solicitation Questions and Answers.pdf PDF
FA461324Q00100002 Amd 02.pdf PDF
FA461324Q00100001 Amd 01.pdf PDF
Solicitation Questions 12March24.pdf PDF
Solicitation Questions 12March24.pdf PDF
Atch 1 Statement of Work 26 Feb 24.pdf PDF
Solicitation - FA461324Q0010.pdf PDF
Atch 4 HazMat Authorization Request.pdf PDF
Atch 2 Asbestos and Lead Report.pdf PDF
Atch 3 Drawing.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 01

SCHEDULE OF MATERIAL SUBMITTALSPROJECT: Replace Carpet Bldg. 34 Rooms 290, 292, 293, 294, 295, and 299SOLICITATION/CONTRACT NO.
AF FORM 66Page 1 of 1Tririga # 11258583
TO BE COMPLETED BY ARCHITECT-ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR

LINE NUMBER ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL CERTIFICATION OF COMPLIANCE SHOP DRAWINGS SAMPLES COLOR SELECTION SCHEDULE OF MATERIALS TECHNICAL DATA INSTALLATION INSTRUCTIONS OPERATING INSTRUCTIONS MSDS SHEETS TEST REPORTS MANUFACTURER'S WARRANTY REQUIRED SUBMISSION DATE fergusog: Enter the due date from the Contractor (DD/MMM/YY)

DATE RECEIVED IN CONTRACTING

fergusog: Enter the date received from the Contractor. (DD/MMM/YY)

DATE TO CIVIL ENGINEERING

fergusog: Enter the date submittal was given to CE for review. (DD/MMM/YY)

RETURN SUSPENSE DATE

fergusog: Enter the date the submittal is due back from CE

(DD/MMM/YY)

SUBMITTAL NUMBER

fergusog: Enter the Submittal Number

CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL

fergusog: Enter Resubmittal Number

FINAL APPROVAL

fergusog: Enter the submittal final approval date

(DD/MMM/YY)

REMARKS

fergusog: Enter any comments pertaining to the sumittal

1 Hazmat Authorization Form. To be filled out by contractor for hazardous materials used. X X App'd fergusog: Enter date the Contractor was notified of submittal approval

(DD/MMM/YY)

fergusog: Enter any comments pertaining to the sumittal Disapp'd fergusog: Enter date the Contractor was notified of submittal disapproval

(DD/MMM/YY)

2Carpet tiles. Color choices for user to chooseXXXXXX
3Warranty. One year workmanship warranty by contractor.XX

Section 02 SCHEDULE OF MATERIAL SUBMITTALS PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONSCHEDULES, LISTINGS,REPORTS, PLANSMANUFACTURER'S RECOMMENDATIONTECHNICAL DATAOPERATING INSTRUCTIONSTEST REPORTSFIELD REPORTSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERCONTR NOTIACTOR FIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
AD
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35

Resubmittals SCHEDULE OF MATERIAL SUBMITTALS PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONSCHEDULES, LISTINGS,REPORTS, PLANSMANUFACTURER'S RECOMMENDATIONTECHNICAL DATAOPERATING INSTRUCTIONSTEST REPORTSFIELD REPORTSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERCONTR NOTIACTOR FIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
AD