This document is an Excel spreadsheet titled "AF Form 66" which is a Schedule of Material Submittals for a capital project to replace three 7.5-ton rooftop packaged HVAC units at Building 140. The project is part of Solicitation/Contract No. FA303024Q0026 for the "HVAC Replacement for Building 140" at Goodfellow Air Force Base.
The key details include: the required submittals such as accident prevention plan, dumpster location, warranties, parking and storage area, work clearance request, planned outages, disposition of waste materials, environmental hazardous waste record, hazardous materials, air emissions report, construction waste management, construction product minimums, and daily reports. The required number of copies, certification required, and due dates for each submittal are specified. This is an attached document to the overall federal contract opportunity, which is a small business set-aside solicitation for the HVAC replacement project. The government is seeking quotes due by June 21, 2024 at 2:30 PM CDT.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA303024Q00260002 SF 30.pdf | ||
| B140 HVAC Vendor Questions 18JUN24_GOV Responses.pdf | ||
| Solicitation Amendment - FA303024Q00260002.pdf | ||
| Solicitation Amendment FA303024Q00260001 SF 30.pdf | ||
| Solicitation Amendment - FA303024Q00260001.pdf | ||
| 6) (CUI) BAL Template.docx | DOCX document | |
| 5) Wage Determinations.pdf | ||
| Solicitation - FA303024Q0026.pdf | ||
| 6) Wage Determinations.pdf | ||
| 7) (CUI) BAL Template.docx | DOCX document | |
| 1) B140 HVAC_Statement of Work.pdf | ||
| 4) TE-1 Images and Equipment.pdf | ||
| 3) DoD Contractor Guide 2021.pdf | ||
| 5) Liquidated Damages - B140 HVAC Package Units.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIAL SUBMITTALS | CAPITAL PROJECT: | PROJECT TITLE: B140 Package Unit Replacement | SOLICITATION/CONTRACT NO.: | |||||||||||||||||
| TO BE COMPLETED BY THE PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||
| NO. OF COPIES REQUIRED | ||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL (Ref spec & para no.) | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | OPERATING INSTRUCTIONS | SEE PARA ON COPIES | OTHERS AS SPECIFIED | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CON-TRACTING | DATE TO CIVIL ENGINEER-ING | RETURN SUSPENSE DATE | FOLLOW UP | DATE CONTRACTOR NOTIFIED | CONTRACT-TOR RE-SUBMITTAL | FINAL APPROVAL | REMARKS | |
| APPROVED | DISAPPROVED | |||||||||||||||||||
| 2 | Part 1, 1.7.1 Accident Prevention Plan | 4 | (e) | FIO | ||||||||||||||||
| 3 | Part 1, 1.9.4 Dumpster Location | 4 | (c) | GA | ||||||||||||||||
| 4 | Part 1, 1.12 Warranties | 4 | (b) | GA | ||||||||||||||||
| 5 | Part 1, 1.13.1 Parking and Storage Area | 4 | (c) | GA | ||||||||||||||||
| 6 | Part 1, 1.14.1.1 Work Clearance Request, AF Form 103 | 4 | (e) | GA | ||||||||||||||||
| 7 | Part 1, 1.14.2 Planned Outages | 4 | 14 Days Prior (d) | GA | ||||||||||||||||
| 8 | Part 1, 1.15, Disposition of Waste Materials | 4 | (b) | FIO | ||||||||||||||||
| 9 | Part 2, 2.2, Environmental Hazardous Waste Record | 4 | (a) | GA | ||||||||||||||||
| Part 2, 2.4.1, Certificate certifing no asbestos was used in construction | 4 | (b) | FIO | |||||||||||||||||
| 8 | Part 2, 2.5, Hazardous Materials, SDS | 4 | (c) | GA | ||||||||||||||||
| 9 | Part 2, 2.8, Air Emissions Report | 4 | Monthly (d) | FIO | ||||||||||||||||
| 10 | Part 2, 2.9, Construction Waste Management Form Submittal | 4 | (d) | GA | ||||||||||||||||
| 11 | Part 2, 2.11.2.2 Construction Product minimums | 4 | (d) | GA | ||||||||||||||||
| Part 3, 3.4, Parts and Materials | 4 | (e) | GA | |||||||||||||||||
| 12 | Part 4, 4.3 Daily Reports | 4 | (d) | GA |
| AF Form 66 |
| When applicable: |
| (a) As soon as possible but in no case later than 45 calendar days after NTP |
| (b) Prior to Final Inspection |
| (c) Prior to Use. |
| (d) As Required. |
| (e) Prior to Start of Construction |
PAGE &P OF &N
FORM66.xls