JA-5_AF_Form_66.pdf

PDF 32 KB Posted

Attached to
Arctic Survival Roof Repair Federal contract opportunity
Solicitation number
FA5004-16-B-C004
Issued by
Department of the Air Force Pacific Air Forces

About this file

JA-5 AF Form 66

View the file

Other files for this federal contract opportunity

Other files attached to Arctic Survival Roof Repair, newest first.
File Type Posted
JA-2_Statement_of_Work.pdf PDF
FA5004-16-B-C004-0001.pdf PDF
JA-6_Site_Map_ _As_Built_Drawings.pdf PDF
JA-8_UFC_3-530-01.pdf PDF
Site_Visit_Record.pdf PDF
JA-7_AF_Forms.pdf PDF
JA-3_Specifications.pdf PDF
JA-1_Other_Contract_Requirements.pdf PDF
JA-2_Statement_of_Work.pdf PDF
JA-6_Site_Map_ _As_Built_Drawings.pdf PDF
JA-4_Wage_Determination.pdf PDF
FA5004-16-B-C004.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT NO.

SCHEDULE OF MATERIAL SUBMITTALS

KEY: 1 SC -1 WEEK PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 2 CM -2 WEEKS PRIOR TO COMMISSIONING 4 15 -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR DIVISION 15

4 SC -4 WEEKS PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 4 CM -4 WEEKS PRIOR TO COMMISSIONING 4 M -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR SPEC SECTION

PR -4 WEEKS PRIOR TO CONSTRUCTION ACTIVITY

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

L

I

N

E

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

C

E R

T

IF

IC

A

T

IO

N O

F C

O M

P L

IA

N

C E

S H

O P

D R

A W

IN

G

S

S A

M P

L E

S

C O

L O

R S

E L

E C

T

IO

N

M A

N U

F A

C T

R 'S

R E

C O

M M

E N

D A

T

IO

N S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

C A

T A

L O

G

D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

S E

R V

IC

E

S

IZ

E

U

S E

S C

H E

D U

L E

O T

H E

R

REQUIRED

SUB-

MISSION

DATE

DATE

RECEIVED

IN CON-

TRACTING

DATE TO

CIVIL

ENGINEER-

ING

RETURN

SUSPENSE

DATE

FOLLOW-UP

DATE

CONTRACTOR

NOTIFIED

CONTRAC-

TOR RE-

SUBMIT-

TAL

FINAL APPROVAL REMARKS

APPROV

ED

DIS-

APPROV

ED

STATEMENT OF WORK

(SOW)

1 Work Plan, SOW 3.1 5 4 wks prior to work

01010 DESCRIPTION OF

WORK AND COORDINATION

AF Form 103

01010 1.11 A

2 wks prior to work start

01000 SUMMARY OF WORK

Welding Permits 01000 - 9.1 (If applicable)

2 wks prior to work

01030 SAFETY,

ENVIRONMENTAL

PROTECTION,

REGULATIONS, AND CODES

4 Construction Operations and

Safety Plan - 1.4

4 wks prior to work

5 Safety and Health Plan - 1.8

4 wks prior to work

6 Environmental Protection Plan

(EPP) - 1.20

6 wks prior to work

7 Hazardous Materials Inventory -

1.21

2 wks prior to work

8 Hazardous Waste

Accumulation Log - 1.22 2 As Applicable

NOI and asbestos abatement plan (if required) 1.26B 4

10 working days prior to work start

Submit only if applicable

Waste disposal/Borrow pit worksheet, 1.26C (if required) 2 w/in 3 days of material transfer Submit only if applicable

Asbestos waste manifests, 1.26D (if required) 2 w/in 3 days of material transfer Submit only if applicable

Abatement Drawings, 1.26F (if required) 2 with Closeout submittals Submit only if applicable

Final Asbestos report, 1.26G (if required) 3 with Closeout submittals Submit only if applicable

14 Schedule- 4.2 2 4 wks prior to work

FTQW 16-1023 Repair Roof At Arctic Survival

(B3347)

SOLICITATION/CONTRACT NO.

SCHEDULE OF MATERIAL SUBMITTALS

KEY: 1 SC -1 WEEK PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 2 CM -2 WEEKS PRIOR TO COMMISSIONING 4 15 -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR DIVISION 15

4 SC -4 WEEKS PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 4 CM -4 WEEKS PRIOR TO COMMISSIONING 4 M -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR SPEC SECTION

PR -4 WEEKS PRIOR TO CONSTRUCTION ACTIVITY

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

L

I

E

U

M

B

E

R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

C

E R

T

IF

IC

A

T

IO

N O

F C

O M

P L

IA

N

C E

S H

O P

D R

A W

IN

G

S

S A

M P

L E

S

C O

L O

R S

E L

E C

T

IO

N

M A

N U

F A

C T

R 'S

R E

C O

M M

E N

D A

T

IO

N S

M A

N U

F A

C T

U R

E R

'S W

A R

R A

N T

Y

C A

T A

L O

G

D

A T

A

O P

E R

A T

IN

G

I N

S T

R U

C T

IO

N

S

S E

R V

IC

E

S

IZ

E

U

S E

S C

H E

D U

L E

O T

H E

R

REQUIRED

SUB-

MISSION

DATE

DATE

RECEIVED

IN CON-

TRACTING

DATE TO

CIVIL

ENGINEER-

ING

RETURN

SUSPENSE

DATE

FOLLOW-UP

DATE

CONTRACTOR

NOTIFIED

CONTRAC-

TOR RE-

SUBMIT-

TAL

FINAL APPROVAL REMARKS

APPROV

ED

DIS-

APPROV

ED

FTQW 16-1023 Repair Roof At Arctic Survival

(B3347)

06100 ROUGH CARPENTRY

15 Product Data - 3.1 2

2 wks prior to ordering materials

07530 SINGLE-PLY

MEMBRANE ROOFING

16 Product Data - 2.1 2

2 wks prior to ordering materials

17 Manufacturer's Warranty - 2.2 2 1 wk after complete

07650 - FLEXIBLE FLASHING

18 Product Data - 3.1 2

2 wks prior to ordering materials

19 Shop Drawings - 3.2 3 4 wks prior to work

075323 - ETHYLENE

PROPYLENE DIENE

MONOMER ROOFING

20 Shop Drawings - SD-02 3 4 wks prior to work

21 Product Data - SD-03 2 4 wks prior to work

22 Design Data - SD-05 2 4 wks prior to work

23 Certificates - SD-07 2 4 wks prior to work

Manufacturer's Instructions -

SD-08

4 wks prior to work

25 Closeout Submittals - SD-11 2 1 wk after complete

File details come from the government source that posted it. Updated .