JA-5_AF_Form_66.pdf
PDF 32 KB Posted
- Attached to
- Arctic Survival Roof Repair Federal contract opportunity
- Solicitation number
- FA5004-16-B-C004
About this file
JA-5 AF Form 66
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| JA-2_Statement_of_Work.pdf | ||
| FA5004-16-B-C004-0001.pdf | ||
| JA-6_Site_Map_ _As_Built_Drawings.pdf | ||
| JA-8_UFC_3-530-01.pdf | ||
| Site_Visit_Record.pdf | ||
| JA-7_AF_Forms.pdf | ||
| JA-3_Specifications.pdf | ||
| JA-1_Other_Contract_Requirements.pdf | ||
| JA-2_Statement_of_Work.pdf | ||
| JA-6_Site_Map_ _As_Built_Drawings.pdf | ||
| JA-4_Wage_Determination.pdf | ||
| FA5004-16-B-C004.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION/CONTRACT NO.
SCHEDULE OF MATERIAL SUBMITTALS
KEY: 1 SC -1 WEEK PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 2 CM -2 WEEKS PRIOR TO COMMISSIONING 4 15 -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR DIVISION 15
4 SC -4 WEEKS PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 4 CM -4 WEEKS PRIOR TO COMMISSIONING 4 M -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR SPEC SECTION
PR -4 WEEKS PRIOR TO CONSTRUCTION ACTIVITY
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L
I
N
E
U
M
B
E
R
ITEM OR DESCRIPTION
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL
C
E R
T
IF
IC
A
T
IO
N O
F C
O M
P L
IA
N
C E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
R 'S
R E
C O
M M
E N
D A
T
IO
N S
M A
N U
F A
C T
U R
E R
'S W
A R
R A
N T
Y
C A
T A
L O
G
D
A T
A
O P
E R
A T
IN
G
I N
S T
R U
C T
IO
N
S
S E
R V
IC
E
S
IZ
E
U
S E
S C
H E
D U
L E
O T
H E
R
REQUIRED
SUB-
MISSION
DATE
DATE
RECEIVED
IN CON-
TRACTING
DATE TO
CIVIL
ENGINEER-
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP
DATE
CONTRACTOR
NOTIFIED
CONTRAC-
TOR RE-
SUBMIT-
TAL
FINAL APPROVAL REMARKS
APPROV
ED
DIS-
APPROV
ED
STATEMENT OF WORK
(SOW)
1 Work Plan, SOW 3.1 5 4 wks prior to work
01010 DESCRIPTION OF
WORK AND COORDINATION
AF Form 103
01010 1.11 A
2 wks prior to work start
01000 SUMMARY OF WORK
Welding Permits 01000 - 9.1 (If applicable)
2 wks prior to work
01030 SAFETY,
ENVIRONMENTAL
PROTECTION,
REGULATIONS, AND CODES
4 Construction Operations and
Safety Plan - 1.4
4 wks prior to work
5 Safety and Health Plan - 1.8
4 wks prior to work
6 Environmental Protection Plan
(EPP) - 1.20
6 wks prior to work
7 Hazardous Materials Inventory -
1.21
2 wks prior to work
8 Hazardous Waste
Accumulation Log - 1.22 2 As Applicable
NOI and asbestos abatement plan (if required) 1.26B 4
10 working days prior to work start
Submit only if applicable
Waste disposal/Borrow pit worksheet, 1.26C (if required) 2 w/in 3 days of material transfer Submit only if applicable
Asbestos waste manifests, 1.26D (if required) 2 w/in 3 days of material transfer Submit only if applicable
Abatement Drawings, 1.26F (if required) 2 with Closeout submittals Submit only if applicable
Final Asbestos report, 1.26G (if required) 3 with Closeout submittals Submit only if applicable
14 Schedule- 4.2 2 4 wks prior to work
FTQW 16-1023 Repair Roof At Arctic Survival
(B3347)
SOLICITATION/CONTRACT NO.
SCHEDULE OF MATERIAL SUBMITTALS
KEY: 1 SC -1 WEEK PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 2 CM -2 WEEKS PRIOR TO COMMISSIONING 4 15 -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR DIVISION 15
4 SC -4 WEEKS PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 4 CM -4 WEEKS PRIOR TO COMMISSIONING 4 M -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR SPEC SECTION
PR -4 WEEKS PRIOR TO CONSTRUCTION ACTIVITY
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L
I
E
U
M
B
E
R
ITEM OR DESCRIPTION
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL
C
E R
T
IF
IC
A
T
IO
N O
F C
O M
P L
IA
N
C E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
R 'S
R E
C O
M M
E N
D A
T
IO
N S
M A
N U
F A
C T
U R
E R
'S W
A R
R A
N T
Y
C A
T A
L O
G
D
A T
A
O P
E R
A T
IN
G
I N
S T
R U
C T
IO
N
S
S E
R V
IC
E
S
IZ
E
U
S E
S C
H E
D U
L E
O T
H E
R
REQUIRED
SUB-
MISSION
DATE
DATE
RECEIVED
IN CON-
TRACTING
DATE TO
CIVIL
ENGINEER-
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP
DATE
CONTRACTOR
NOTIFIED
CONTRAC-
TOR RE-
SUBMIT-
TAL
FINAL APPROVAL REMARKS
APPROV
ED
DIS-
APPROV
ED
FTQW 16-1023 Repair Roof At Arctic Survival
(B3347)
06100 ROUGH CARPENTRY
15 Product Data - 3.1 2
2 wks prior to ordering materials
07530 SINGLE-PLY
MEMBRANE ROOFING
16 Product Data - 2.1 2
2 wks prior to ordering materials
17 Manufacturer's Warranty - 2.2 2 1 wk after complete
07650 - FLEXIBLE FLASHING
18 Product Data - 3.1 2
2 wks prior to ordering materials
19 Shop Drawings - 3.2 3 4 wks prior to work
075323 - ETHYLENE
PROPYLENE DIENE
MONOMER ROOFING
20 Shop Drawings - SD-02 3 4 wks prior to work
21 Product Data - SD-03 2 4 wks prior to work
22 Design Data - SD-05 2 4 wks prior to work
23 Certificates - SD-07 2 4 wks prior to work
Manufacturer's Instructions -
SD-08
4 wks prior to work
25 Closeout Submittals - SD-11 2 1 wk after complete