Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
DC015D 4 HW689
Benjamin Aoki 850-245-7527 Contractor APTIM Environmental & Infrastructure, LLC Contractor
Contractor Eric Kramer Contractor 813-205-4703
ERIC_4885
Oasis Cleaners
✔ $ 53,258.86 $ 55,769.25 ✔ $ 6,600.00 $ 6,600.00
$ 59,858.86 $ 62,369.25 Completion
✔ Completion 09/11/2026 09/11/2026 0
✔ 1 1 4
APTIM Environmental & Infrastructure, LLC Contractor
Aptim Contract Manager
Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2026.04.29 16:34:07 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2026.04.29 11:26:20 -04'00'
This Task Assignment Change Order reduces labor and subcontractor costs for ST3.
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number: HW689 Task Assignment #: DC015D
Change Order #: 4
Deliverables:
Deliverable Deliverable Due Date
Subtask 2: O&M (Quarter 1) 9/26/2025
Subtask 3: O&M (Quarter 2) 12/19/2025
Subtask 4: Utilities (First 6 Months) 12/19/2025
Subtask 5: Semi-Annual O&M Report 1/23/2026
Subtask 6: O&M (Quarter 3) 3/20/2026
Subtask 7: O&M (Quarter 4) 6/26/2026
Subtask 8: Utilities (Entire year) 6/26/2026
Subtask 1 & 9: Annual O&M Report; Project Management 7/17/2026
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
Subtask 2: FDEP receipt of Q1 O&M Report $7,444.55
Subtask 3: FDEP receipt of Q2 O&M Report $10,206.56
Subtask 4: FDEP receipt of paid utilities receipts: cost reimbursement = not to exceed $2,250.00 Handling Fee = $120 $0.00
Subtask 5: FDEP receipt of Semi-Annual O&M Report $4,037.61
Subtask 6: FDEP receipt of Q3 O&M Report $10,681.85
Subtask 7: FDEP receipt of Q4 O&M Report $10,681.85
Subtask 8: FDEP receipt of paid utilities receipts: cost reimbursement = not to exceed $6,600.00 Handling Fee = $240 $6,840.00
Subtask 1 & 9: FDEP receipt of Annual O&M Report $9,966.44
TOTAL COST $59,858.86
BWC TAFORM 01_18
FFLORIDAA DEPARTMENTT OF
EEnvironmentall Protection
Ronn DeSantis
Alexiss A.. Lambert
Memorandum
TO:
FROM:
SUBJECT:
DATE:
FDEP COST ESTIMATE
Contractor: Aptim Environmental & Infrastructure, LLC
Date: 4/2/2026
Task #: HW689 - DC008C TACO #4 SubTask 1 Project Management SubTask 6 6-Qtr 3 O&M Dec-Feb
Site: Oasis Cleaners ERIC_4885 SubTask 2 2-Qtr 1 O&M Jun-Aug 2025 SubTask 7 7-Qtr 4 O&M Mar-May
Activity/Phase: Annual O&M Services SubTask 3 3- Qtr 2 O&M Sept-Nov SubTask 8 8-Utilities Qtr 3&4 (Dec-May)
Project Manager: Safa Shariat FDEP/Eric Kramer APTIM SubTask 4 4-Utilities Qtr 1&2 (Jun-Nov) SubTask 9 9-Annual O&M Report
SubTask 5 5-Semi-Annual Report SubTask 10
TTotals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$71.05 Project Manager E. Kramer 27 27.0 $71.05 Engineer/Scientist 5 E. Kramer 28 5 5 0 4 5 5 0 4 0 $66.63 Engineer/Scientist 5 G. Roberts 4 0 0 0 2 0 0 0 2 0 $36.08 Engineer/Scientist 3 K. Howard 0 0 0 0 0 0 0 0 0 0 $28.45 Engineer/Scientist 1 R. Lindsay 158 43 37 0 0 39 39 0 0 0 $24.50 Engineer/Scientist 1 B. Blount 0 0 0 0 0 0 0 0 0 0 $36.15 Engineer/Scientist 2 K. McDonald 108 12 12 0 25 12 12 0 35 0 $32.50 Engineering Technician 3 B. Skipper 111 0 37 0 0 37 37 0 0 0 $34.84 Designer 2 S. Ferianc 8 0 0 0 4 0 0 0 4 0 $29.57 Technical Publications Specialist 3 H. Vining 6 0 0 0 3 0 0 0 3 0
$0.00 0 0 0 0 0 0 0 0 0 0 TTotal Hours 450 27 60 91 0 38 93 93 0 48 0
Direct Labor $16,632.32 $1,913.46 $2,012.40 $3,044.20 $0.00 $1,549.28 $3,101.10 $3,101.10 $0.00 $1,910.78 $0.00
Overhead 85.58% $14,233.96 $1,637.54 $1,722.21 $2,605.23 $0.00 $1,325.87 $2,653.93 $2,653.93 $0.00 $1,635.25 $0.00 Gen & Admin 19.38% $3,223.36 $370.83 $390.00 $589.97 $0.00 $300.25 $601.00 $601.00 $0.00 $370.31 $0.00 Fringe 31.96% $5,315.69 $611.54 $643.16 $972.93 $0.00 $495.15 $991.11 $991.11 $0.00 $610.69 $0.00 Total Labor $39,405.33 $4,533.37 $4,767.77 $7,212.33 $0.00 $3,670.55 $7,347.14 $7,347.14 $0.00 $4,527.03 $0.00
Travel Vehicle Rental $1,440.00 $360.00 $360.00 $0.00 $0.00 $360.00 $360.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,440.00 $360.00 $360.00 $0.00 $0.00 $360.00 $360.00 $0.00 $0.00 $0.00
REV: 02/03 CEF SHAW Page 1
FDEP COST ESTIMATE
Date: 4/2/2026
Task #: HW689 - DC008C TACO #4 SubTask 1 Project Management SubTask 6 6-Qtr 3 O&M Dec-Feb
Site: Oasis Cleaners ERIC_4885 SubTask 2 2-Qtr 1 O&M Jun-Aug 2025 SubTask 7 7-Qtr 4 O&M Mar-May
Activity/Phase: Annual O&M Services SubTask 3 3- Qtr 2 O&M Sept-Nov SubTask 8 8-Utilities Qtr 3&4 (Dec-May)
Project Manager: Safa Shariat FDEP/Eric Kramer APTIM SubTask 4 4-Utilities Qtr 1&2 (Jun-Nov) SubTask 9 9-Annual O&M Report
SubTask 5 5-Semi-Annual Report SubTask 10
TTotals 1 2 3 4 5 6 7 8 9 10 SSubcontractor (Equipment Procurement)
UltraSonic Water Level $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $6,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $6,600.00 $0.00 $0.00 Pump Alarm Telementry $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 PRM Filteration $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $6,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $6,600.00 $0.00 $0.00 Handling Fee $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $240.00 $0.00 $0.00 Total Subcontractor Cost $6,840.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $6,840.00 $0.00 $0.00
Laboratory Analytical Costs $1,673.00 $200.00 $273.00 $0.00 $0.00 $600.00 $600.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $440.00 $110.00 $110.00 $0.00 $0.00 $110.00 $110.00 $0.00 $0.00 $0.00 Total Laboratory $2,113.00 $310.00 $383.00 $0.00 $0.00 $710.00 $710.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $420.00 $105.00 $105.00 $0.00 $0.00 $105.00 $105.00 $0.00 $0.00 $0.00 Expendables $480.00 $120.00 $120.00 $0.00 $0.00 $120.00 $120.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $5,220.00 $1,305.00 $1,305.00 $0.00 $0.00 $1,305.00 $1,305.00 $0.00 $0.00 $0.00 Total Field Expenses $6,120.00 $1,530.00 $1,530.00 $0.00 $0.00 $1,530.00 $1,530.00 $0.00 $0.00 $0.00
Subtotal $55,918.33 $4,533.37 $6,967.77 $9,485.33 $0.00 $3,670.55 $9,947.14 $9,947.14 $6,840.00 $4,527.03 $0.00 Completion Fee $3,940.53 $453.34 $476.78 $721.23 $0.00 $367.06 $734.71 $734.71 $0.00 $452.70 $0.00
Total Estimated Cost $59,858.86 $4,986.71 $7,444.55 $10,206.56 $0.00 $4,037.61 $10,681.85 $10,681.85 $6,840.00 $4,979.73 $0.00
Cost from Prior CEF: $62,369.25 Manual Entry Cost from Delta CEF; ($2,510.41) Manual Entry
Cost (Prior + Delta): $59,858.84 Auto-Calculated Rounding Error: $0.02 Auto-Calculated
Final Total Cost: $59,858.86 Auto-Calculated
REV: 02/03 CEF SHAW Page 2
SITE :
SUBTASK:
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer 5
Engineer/Scientist 5 G. Roberts Engineer/Scientist 2 K. Howard
Engineer/Scientist 1 R. Lindsay 43
Engineer/Scientist 1 B. Blount
Engineer/Scientist 1 K. McDonald 12
Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining
TOTAL LABOR 60
VEHICLE TYPE RATE UNIT USEAGE TOTALS
Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 3 $360.00
TOTAL VEHICLE $360.00
PER DIEM STAFF RATE UNIT USEAGE TOTALS
Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE TOTALS
$0.00
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC TOTALS
EPA Method TO-15 (VOC Soil Vapor) $200.00 1 0 $200.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 1 $110.00 Sample Shipping (large cooler) $150.00 0 $0.00
TOTAL LAB $310.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Day 3 $120.00 PPE Level D $35.00 Day 3 $105.00 Construction/O&M Kit $360.00 Day 3 $1,080.00 Construction O&M Supplies $75.00 Day 3 $225.00
TOTAL EQUIPMENT $1,530.00
Oasis Cleaners
11/5/2024
Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.). Submital of the Quarterly monthly reports O&M data collection sheets. (2 hrs.)
2-Qtr 1 O&M Jan-Mar 2025
Monthly Base Work - Loadout prep. (1 hr), Travel Round Trip (6 hrs), SVE O&M (6 hrs) {total = 13 hrs x 3 mo = 39 hrs. Additional work (each quarter) includes SVE Vacuum Readings and collection of VOC Vapor Sample (total 4 hrs).
Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x 3 months = 9 hrs). SVE performance evaluation and system optimization (3 hrs).
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer 5
Engineer/Scientist 5 G. Roberts Engineer/Scientist 2 K. Howard
Engineer/Scientist 1 R. Lindsay 37
Engineer/Scientist 1 B. Blount
Engineer/Scientist 1 K. McDonald 12
Engineering Technician 3 B. Skipper 37
Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining
TOTAL LABOR 91
VEHICLE TYPE RATE UNIT USEAGE TOTALS
Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 3 $360.00
TOTAL VEHICLE $360.00
PER DIEM STAFF RATE UNIT USEAGE TOTALS
Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE TOTALS
PRM Filtration panel modification $966.00 each 0 $0.00
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC TOTALS
EPA Method TO-15 (VOC Soil Vapor) $200.00 1 0 $200.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 1 $73.00 Sample Shipping (Small cooler) $110.00 1 $110.00 Sample Shipping (large cooler) $150.00 0 $0.00
TOTAL LAB $383.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Day 3 $120.00 PPE Level D $35.00 Day 3 $105.00 Construction/O&M Kit $360.00 Day 3 $1,080.00 Construction O&M Supplies $75.00 Day 3 $225.00 Ultrasonic Water Level $663.50 each 0 $0.00
TOTAL EQUIPMENT $1,530.00
Oasis Cleaners
3- Qtr 2 O&M Sept-Nov 4/2/2026
Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.). Submital of the Quarterly monthly reports O&M data collection sheets. (2 hrs.)
Monthly Base Work - Loadout prep. (1 hr), Travel Round Trip (6 hrs), SVE O&M (6 hrs) {total = 11 hrs x 3 mo = 33 hrs. Additional work (each quarter) includes SVE Vacuum Readings and collection of VOC Vapor Sample (total 4 hrs).
Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x 3 months = 9 hrs). SVE performance evaluation and system optimization (3 hrs).
Monthly Base Work - Loadout prep. (1 hr), Travel Round Trip (6 hrs), SVE O&M (4 hrs) {total = 11 hrs x 3 mo = 33 hrs. Additional work once per quarter includes SVE Vacuum Readings and collection of VOC Vapor Sample (total 4 hrs).
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer Engineer/Scientist 5 G. Roberts Engineer/Scientist 2 K. Howard Engineer/Scientist 1 R. Lindsay Engineer/Scientist 1 B. Blount Engineer/Scientist 1 K. McDonald Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE TOTALS
Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE TOTALS
Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE TOTALS
Electrical Service Sept-Oct $0.00 Month 0 0 $0.00 Handling fee Electrical $0.00 Month 0 0 $0.00
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC TOTALS
EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 0 $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Day 0 $0.00 Construction/O&M Kit $360.00 Day 0 $0.00 Construction O&M Supplies $75.00 Day 0 $0.00
TOTAL EQUIPMENT $0.00
Oasis Cleaners
4-Utilities Qtr 1&2 (Jun-Nov) 1/30/2026
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer 4
Engineer/Scientist 5 G. Roberts 2 Engineer/Scientist 2 K. Howard Engineer/Scientist 1 R. Lindsay Engineer/Scientist 1 B. Blount
Engineer/Scientist 1 K. McDonald 25
Designer 2 S. Ferianc 4 Technical Pub Specialist 3 H. Vining 3
TOTAL LABOR 38
VEHICLE TYPE RATE UNIT USEAGE TOTALS
Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE TOTALS
Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE TOTALS
$0.00
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC TOTALS
EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 0 $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Day 0 $0.00 Construction/O&M Kit $360.00 Day 0 $0.00 Construction O&M Supplies $75.00 Day 0 $0.00
TOTAL EQUIPMENT $0.00
Oasis Cleaners
5-Semi-Annual Report 11/5/2024
Engineering evaluation of monthly data for first six months system operation, PE seal of Semi-Annual O&M report, evaluate data, develop recommendations and conclusions (4 hrs.)
Data quality evaluation and report documentation
Semi-Annual O&M Report (Document Production)
Preparation of Semi-Annual O&M Report includes preparation of SVE operational tables, calculations, figures, O&M site visit summary, SVE system operation & performance.
Semi-Annual O&M Report (Drafting)
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer 5
Engineer/Scientist 5 G. Roberts Engineer/Scientist 2 K. Howard
Engineer/Scientist 1 R. Lindsay 39
Engineer/Scientist 1 B. Blount
Engineer/Scientist 1 K. McDonald 12
Engineering Technician 3 B. Skipper 37
Designer 2 S. Ferianc Designer 1 Technical Pub Specialist 3 H. Vining
TOTAL LABOR 93
VEHICLE TYPE RATE UNIT USEAGE TOTALS
Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 3 $360.00
TOTAL VEHICLE $360.00
PER DIEM STAFF RATE UNIT USEAGE TOTALS
Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE TOTALS
$0.00
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC TOTALS
EPA Method TO-15 (VOC Soil Vapor) $200.00 3 0 $600.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 1 $110.00 Sample Shipping (large cooler) $150.00 0 $0.00
TOTAL LAB $710.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Day 3 $120.00 PPE Level D $35.00 Day 3 $105.00 Construction/O&M Kit $360.00 Day 3 $1,080.00 Construction O&M Supplies $75.00 Day 3 $225.00
TOTAL EQUIPMENT $1,530.00
Monthly Base Work - Loadout prep. (1 hr), Travel Round Trip (6 hrs), SVE O&M (4 hrs) {total = 11 hrs x 3 mo = 33 hrs. Additional work once per quarter includes SVE Vacuum Readings and collection of VOC Vapor Sample (total 4 hrs).
Monthly Base Work - Loadout prep. (1 hr), Travel Round Trip (6 hrs), SVE O&M (4 hrs) {total = 11 hrs x 3 mo = 33 hrs. Additional work once per quarter includes SVE Vacuum Readings and collection of VOC Vapor Sample (total 4 hrs). Add -cycle zones to collect vapor samples form two zones
Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x 3 months = 9 hrs). SVE performance evaluation and system optimization (3 hrs).
Oasis Cleaners
6-Qtr 3 O&M Dec-Feb 1/30/2026
Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.). Submital of the Quarterly monthly reports O&M data collection sheets. (2 hrs.)
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer 5
Engineer/Scientist 5 G. Roberts Engineer/Scientist 2 K. Howard
Engineer/Scientist 1 R. Lindsay 37
Engineer/Scientist 1 B. Blount
Engineer/Scientist 1 K. McDonald 12
Engineering Technician 3 B. Skipper 37
Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining
TOTAL LABOR 91
VEHICLE TYPE RATE UNIT USEAGE TOTALS
Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 3 $360.00
TOTAL VEHICLE $360.00
PER DIEM STAFF RATE UNIT USEAGE TOTALS
Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE TOTALS
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC TOTALS
EPA Method TO-15 (VOC Soil Vapor) $200.00 3 0 $600.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 1 $110.00 Sample Shipping (large cooler) $150.00 0 $0.00
TOTAL LAB $710.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Day 3 $120.00 PPE Level D $35.00 Day 3 $105.00 Construction/O&M Kit $360.00 Day 3 $1,080.00 Construction O&M Supplies $75.00 Day 3 $225.00
TOTAL EQUIPMENT $1,530.00
Oasis Cleaners
7-Qtr 4 O&M Mar-May 1/30/2026
Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.). Submital of the Quarterly monthly reports O&M data collection sheets. (2 hrs.)
Monthly Base Work - Loadout prep. (1 hr), Travel Round Trip (6 hrs), SVE O&M (4 hrs) {total = 11 hrs x 3 mo = 33 hrs. Additional work once per quarter includes SVE Vacuum Readings and collection of VOC Vapor Sample (total 4 hrs). Add -cycle zones to collect vapor samples form two zones
Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x 3 months = 9 hrs). SVE performance evaluation and system optimization (3 hrs).
Monthly Base Work - Loadout prep. (1 hr), Travel Round Trip (6 hrs), SVE O&M (4 hrs) {total = 11 hrs x 3 mo = 33 hrs. Additional work once per quarter includes SVE Vacuum Readings and collection of VOC Vapor Sample (total 4 hrs).
SUBTASK: 8-Utilities
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer Engineer/Scientist 5 G. Roberts Engineer/Scientist 2 K. Howard Engineer/Scientist 1 R. Lindsay Engineer/Scientist 1 B. Blount Engineer/Scientist 1 K. McDonald Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE TOTALS
Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE TOTALS
Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE TOTALS
FPL-Electrical Service $550.00 Month 12 $6,600.00 Handling fee Electrical $20.00 Month 12 $240.00
TOTAL $6,840.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC TOTALS
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Day 0 $0.00 Construction/O&M Kit $360.00 Day 0 $0.00 Construction O&M Supplies $75.00 Day 0 $0.00
TOTAL EQUIPMENT $0.00
Oasis Cleaners
1/30/2026
LEVEL OF EFFORT / EXPENSE WORKSHEET
SUBTASK:
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer 4
Engineer/Scientist 5 G. Roberts 2
Engineer/Scientist 2 K. Howard Engineer/Scientist 1 R. Lindsay Engineer/Scientist 1 B. Blount
Engineer/Scientist 1 K. McDonald 35
Designer 2 S. Ferianc 4 Technical Pub Specialist 3 H. Vining 3
TOTAL LABOR 48
VEHICLE TYPE RATE UNIT USEAGE TOTALS
Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE TOTALS
Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noon 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE TOTALS
$0.00
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC TOTALS
EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 0 $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Day $0.00 Shallow GW Sampling Kit $290.00 Day $0.00 Deep Groundwater Sampling Kit $415.00 Day $0.00 Diffusion Sampler (2" well) $36.00 Day $0.00 55-gallon Drum $100.00 each $0.00
TOTAL EQUIPMENT $0.00
Oasis Cleaners
Preparation of Annual O&M Report that includes SVE operational tables, calculations, figures, O&M site visit summary, SVE system operation & performance (35 hrs.)
Annual Groundwater and O&M Reporting (Drafting) Annual Groundwater and O&M Report (Document Production)
9-Annual O&M Report 11/5/2024
Engineering evaluation of monthly data, PE seal of Annual O&M report, evaluate data, develop recommendations and conclusions (4 hrs.)
Technical evaluation of air analytical data (2 hr)
9-Annual O&M Reporting Page 10 of 10 Oasis Cleaners DC015D est
FDEP COST ESTI MATE
Date: 4/2/2026
Task #: HW689 - DC008C TACO #4 SubTask 1 Project Management SubTask 6 6-Qtr 3 O&M Dec-Feb
Site: Oasis Cleaners ERIC_4885 SubTask 2 2-Qtr 1 O&M Jun-Aug 2025 SubTask 7 7-Qtr 4 O&M Mar-May
Activity/Phase: Annual O&M Services SubTask 3 3- Qtr 2 O&M Sept-Nov SubTask 8 8-Utilities Qtr 3&4 (Dec-May)
Project Manager: Safa Shariat FDEP/Eric Kramer APTIM SubTask 4 4-Utilities Qtr 1&2 (Jun-Nov) SubTask 9 9-Annual O&M Report
SubTask 5 5-Semi-Annual Report SubTask 10
TTotals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$71.05 Project Manager E. Kramer 0 -0.4 $71.05 Engineer/Scientist 5 E. Kramer 0 0 0 0 0 0 0 0 0 0 $66.63 Engineer/Scientist 5 G. Roberts 0 0 0 0 0 0 0 0 0 0 $36.08 Engineer/Scientist 3 K. Howard 0 0 0 0 0 0 0 0 0 0 $28.45 Engineer/Scientist 1 R. Lindsay -4 0 -4 0 0 0 0 0 0 0 $24.50 Engineer/Scientist 1 B. Blount 0 0 0 0 0 0 0 0 0 0 $36.15 Engineer/Scientist 2 K. McDonald 0 0 0 0 0 0 0 0 0 0 $32.50 Engineering Technician 3 B. Skipper -4 0 -4 0 0 0 0 0 0 0 $34.84 Designer 2 S. Ferianc 0 0 0 0 0 0 0 0 0 0 $29.57 Technical Publications Specialist 3 H. Vining 0 0 0 0 0 0 0 0 0 0
$0.00 0 0 0 0 0 0 0 0 0 0 TTotal Hours -8 0 0 -8 0 0 0 0 0 0 0
Direct Labor ($275.49) ($31.69) $0.00 ($243.80) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 85.58% ($235.76) ($27.12) $0.00 ($208.64) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 19.38% ($53.39) ($6.14) $0.00 ($47.25) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 31.96% ($88.05) ($10.13) $0.00 ($77.92) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor ($652.69) ($75.08) $0.00 ($577.61) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF SHAW Page 4
Date: 4/2/2026
Task #: HW689 - DC008C TACO #4 SubTask 1 Project Management SubTask 6 6-Qtr 3 O&M Dec-Feb
Site: Oasis Cleaners ERIC_4885 SubTask 2 2-Qtr 1 O&M Jun-Aug 2025 SubTask 7 7-Qtr 4 O&M Mar-May
Activity/Phase: Annual O&M Services SubTask 3 3- Qtr 2 O&M Sept-Nov SubTask 8 8-Utilities Qtr 3&4 (Dec-May)
Project Manager: Safa Shariat FDEP/Eric Kramer APTIM SubTask 4 4-Utilities Qtr 1&2 (Jun-Nov) SubTask 9 9-Annual O&M Report
SubTask 5 5-Semi-Annual Report SubTask 10
TTotals 1 2 3 4 5 6 7 8 9 10 SSubcontractor (Equipment Procurement)
UltraSonic Water Level ($663.50) $0.00 ($663.50) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal ($663.50) $0.00 ($663.50) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee ($66.35) $0.00 ($66.35) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost (($729.85) $0.00 ($729.85) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Pump Alarm Telementry $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 PRM Filteration ($966.00) $0.00 ($966.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal ($966.00) $0.00 ($966.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee ($96.60) $0.00 ($96.60) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost ($1,062.60) $0.00 ($1,062.60) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal ($2,445.14) ($75.08) $0.00 ($2,370.06) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee ($65.27) ($7.51) $0.00 ($57.76) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost ($2,510.41) ($82.59) $0.00 ($2,427.82) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF SHAW Page 5
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer Engineer/Scientist 5 G. Roberts Engineer/Scientist 2 K. Howard
Engineer/Scientist 1 R. Lindsay -4
Engineer/Scientist 1 B. Blount Engineer/Scientist 1 K. McDonald
Engineering Technician 3 B. Skipper -4
Geospatial Analyst 3 H. Vollmer Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining
TOTAL LABOR -8
VEHICLE TYPE RATE UNIT USEAGE TOTALS
Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE TOTALS
Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE TOTALS
PRM Filtration panel modification $966.00 each -1 ($966.00)
TOTAL ($966.00)
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC TOTALS
EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 0 $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Day 0 $0.00 PPE Level D $35.00 Day 0 $0.00 Construction/O&M Kit $360.00 Day 0 $0.00 Construction O&M Supplies $75.00 Day 0 $0.00 Ultrasonic Water Level $663.50 each -1 ($663.50)
TOTAL EQUIPMENT ($663.50)
Oasis Cleaners
3- Qtr 2 O&M Sept-Nov 4/2/2026
Remove: Installation of ultrasonic levl meter and pull control wire 4 hrs. (Ultasonic meter not installed due to difficulty coordinating with contractor and below grade fit issues)
Remove: Installation of ultrasonic levl meter and pull control wire 4 hrs. (Ultasonic meter not installed due to difficulty coordinating with contractor and below grade fit issues)
Date: 1/30/2026 Task #: HW689 - DC015D TACO #3 SubTask 1 Project Management SubTask 6 6-Qtr 3 O&M Dec-Feb
Site: Oasis Cleaners ERIC_4885 SubTask 2 2-Qtr 1 O&M Jun-Aug 2025 SubTask 7 7-Qtr 4 O&M Mar-May Activity/Phase: Annual O&M Services SubTask 3 3- Qtr 2 O&M Sept-Nov SubTask 8 8-Utilities Qtr 3&4 (Dec-May)
Project Manager: Safa Shariat FDEP/Eric Kramer APTIM SubTask 4 4-Utilities Qtr 1&2 (Jun-Nov) SubTask 9 9-Annual O&M Report SubTask 5 5-Semi-Annual Report SubTask 10
TTotals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$71.05 Project Manager E. Kramer 27 27.4 $71.05 Engineer/Scientist 5 E. Kramer 28 5 5 0 4 5 5 0 4 0 $66.63 Engineer/Scientist 5 G. Roberts 4 0 0 0 2 0 0 0 2 0 $36.08 Engineer/Scientist 3 K. Howard 0 0 0 0 0 0 0 0 0 0 $28.45 Engineer/Scientist 1 R. Lindsay 162 43 41 0 0 39 39 0 0 0 $24.50 Engineer/Scientist 1 B. Blount 0 0 0 0 0 0 0 0 0 0 $36.15 Engineer/Scientist 2 K. McDonald 108 12 12 0 25 12 12 0 35 0 $32.50 Engineering Technician 3 B. Skipper 115 0 41 0 0 37 37 0 0 0 $34.84 Designer 2 S. Ferianc 8 0 0 0 4 0 0 0 4 0 $29.57 Technical Publications Specialist 3 H. Vining 6 0 0 0 3 0 0 0 3 0
$0.00 0 0 0 0 0 0 0 0 0 0 TTotal Hours 458 27 60 99 0 38 93 93 0 48 0
Direct Labor $16,907.81 $1,945.15 $2,012.40 $3,288.00 $0.00 $1,549.28 $3,101.10 $3,101.10 $0.00 $1,910.78 $0.00
Overhead 85.58% $14,469.72 $1,664.66 $1,722.21 $2,813.87 $0.00 $1,325.87 $2,653.93 $2,653.93 $0.00 $1,635.25 $0.00 Gen & Admin 19.38% $3,276.74 $376.97 $390.00 $637.21 $0.00 $300.25 $601.00 $601.00 $0.00 $370.31 $0.00 Fringe 31.96% $5,403.73 $621.67 $643.16 $1,050.84 $0.00 $495.15 $991.11 $991.11 $0.00 $610.69 $0.00 Total Labor $40,058.00 $4,608.45 $4,767.77 $7,789.92 $0.00 $3,670.55 $7,347.14 $7,347.14 $0.00 $4,527.03 $0.00
Travel Vehicle Rental $1,440.00 $360.00 $360.00 $0.00 $0.00 $360.00 $360.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,440.00 $360.00 $360.00 $0.00 $0.00 $360.00 $360.00 $0.00 $0.00 $0.00
REV: 02/03 CEF SHAW Page 7
Date: 1/30/2026 Task #: HW689 - DC015D TACO #3 SubTask 1 Project Management SubTask 6 6-Qtr 3 O&M Dec-Feb
Site: Oasis Cleaners ERIC_4885 SubTask 2 2-Qtr 1 O&M Jun-Aug 2025 SubTask 7 7-Qtr 4 O&M Mar-May Activity/Phase: Annual O&M Services SubTask 3 3- Qtr 2 O&M Sept-Nov SubTask 8 8-Utilities Qtr 3&4 (Dec-May)
Project Manager: Safa Shariat FDEP/Eric Kramer APTIM SubTask 4 4-Utilities Qtr 1&2 (Jun-Nov) SubTask 9 9-Annual O&M Report SubTask 5 5-Semi-Annual Report SubTask 10
TTotals 1 2 3 4 5 6 7 8 9 10 SSubcontractor (Equipment Procurement)
UltraSonic Water Level $663.50 $0.00 $663.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $663.50 $0.00 $663.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $66.35 $0.00 $66.35 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $$729.85 $0.00 $729.85 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $6,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $6,600.00 $0.00 $0.00 Pump Alarm Telementry $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 PRM Filteration $966.00 $0.00 $966.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $7,566.00 $0.00 $966.00 $0.00 $0.00 $0.00 $0.00 $6,600.00 $0.00 $0.00 Handling Fee $336.60 $0.00 $96.60 $0.00 $0.00 $0.00 $0.00 $240.00 $0.00 $0.00 Total Subcontractor Cost $7,902.60 $0.00 $1,062.60 $0.00 $0.00 $0.00 $0.00 $6,840.00 $0.00 $0.00
Laboratory Analytical Costs $1,673.00 $200.00 $273.00 $0.00 $0.00 $600.00 $600.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $440.00 $110.00 $110.00 $0.00 $0.00 $110.00 $110.00 $0.00 $0.00 $0.00 Total Laboratory $2,113.00 $310.00 $383.00 $0.00 $0.00 $710.00 $710.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $420.00 $105.00 $105.00 $0.00 $0.00 $105.00 $105.00 $0.00 $0.00 $0.00 Expendables $480.00 $120.00 $120.00 $0.00 $0.00 $120.00 $120.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $5,220.00 $1,305.00 $1,305.00 $0.00 $0.00 $1,305.00 $1,305.00 $0.00 $0.00 $0.00 Total Field Expenses $6,120.00 $1,530.00 $1,530.00 $0.00 $0.00 $1,530.00 $1,530.00 $0.00 $0.00 $0.00
Subtotal $58,363.45 $4,608.45 $6,967.77 $11,855.37 $0.00 $3,670.55 $9,947.14 $9,947.14 $6,840.00 $4,527.03 $0.00 Completion Fee $4,005.80 $460.85 $476.78 $778.99 $0.00 $367.06 $734.71 $734.71 $0.00 $452.70 $0.00
Total Estimated Cost $62,369.25 $5,069.30 $7,444.55 $12,634.36 $0.00 $4,037.61 $10,681.85 $10,681.85 $6,840.00 $4,979.73 $0.00
REV: 02/03 CEF SHAW Page 8
Proposed Scope of Work Oasis Cleaners (former) DC015D 3210 1st Street West, Bradenton, FL Task Assignment DC015C TACO #4 ERIC_4885 (Former FAC ID No. 419500357) Aptim Environmental & Infrastructure, LLC (APTIM) April 1, 2026
The following proposed Task Assignment Change Order (TACO) #4 for the former Oasis Cleaners facility reconciles the costs associated with the authorized scope of work.
Subtask - 1: Project Management This task includes project management activities associated with the completion of Subtasks 2 through 9, as calculated in accordance with Contract HW689.
Subtask 2: Qtr. 1 O&M Reporting: No Changes
Subtask 3: Qtr. 2 O&M Reporting
TACO #2 which is in Subtask 3, authorized the purchase and installation of an optical water level detector that would be placed at the top of the well casing. Operation of this device required modifications to the control panel to receive a 4-20 milliamp analog signal or other digital response to changing groundwater elevation changes. Unfortunately, a cost-effective unit that could fit within the well casing and manhole could not readily be found so the modification was not performed. The high groundwater elevation condition that would allow water entrainment into the remedial system is now managed by adjusting the vacuum extraction pressure, isolating specific vertical SVE wells and adjusting zone operation. The cost reconciliation for this system modification removes 8 personnel hours from ST 3, removal of $966 fee from subcontractor PRM and removal of the optical sensor for $663.50. Total cost reduction for Subtask 3 is $2,510.41.
Subtask 4: Utilities One Month: No Changes
Subtask 5: Semi-Annual Reporting: No Changes
Subtask 6: Qtr. 3 O&M Reporting: No Changes
Subtask 7: Qtr. 4 O&M Reporting: No Changes
Subtask 8: Utilities One Month: No Changes
Subtask 9: Annual O&M Reporting: No Changes
APTIM proposes to perform this scope of work in accordance with the terms and conditions of the DEP Contract No. HW689, dated December 21, 2021, that was executed between the Florida Department of Environmental Protection and APTIM. APTIM will begin the proposed scope of work upon issuance of the Task Assignment Notification.
If you have any questions, please contact us for clarification.
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
DC015D 3 HW689
Alyssa Lamb 850-245-8791 Contractor APTIM Environmental & Infrastructure, LLC Contractor
Contractor Eric Kramer Contractor 813-205-4703
ERIC_4885
Oasis Cleaners
✔ $ 55,769.25 $ 54,643.11 ✔ $ 6,600.00 $ 4,500.00
$ 62,369.25 $ 59,143.11 ✔ Completion
Completion 09/11/2026 09/11/2026 0
1 1
Contractor
Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2026.02.09 08:14:18 -05'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2026.02.06 12:59:00 -05'00'
This Change Order adjusts the utility subtasks for invoicing purposes as well as the addition of vapor sample analysis.
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number: HW689 Task Assignment #: DC015D
Deliverables:
Deliverable Deliverable Due Date Subtask 2- O&M (Quarter 1) 9/26/2025
Subtask 3- O&M (Quarter 2) 12/19/2025 Subtask 4- Utilities (First 6 Months) 12/19/2025 Subtak 5- Semi-Annual O&M Report 1/23/2026 Subtask 6- O&M (Quarter 3) 3/20/2026 Subtask 7- O&M (Quarter 4) 6/26/2026 Subtask 8- Utilities (Entire Year) 6/26/2026 Subtask 1 & 9- Project Management; Annual O&M Report 7/17/2026
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced Subtask 2- Submittal and FDEP approval of the first quarter O&M Report 7,444.55
Subtask 3- Submittal and FDEP approval of the second quarter O&M Report 12,634.36
Subtask 4- Submittal and FDEP approval of paid utility receipts:
Cost Reimbursement = not to exceed $2,250.00 Handling Fee= $120
0.00
Subtask 5- Submittal and FDEP approval of Semi- Annual O&M Report 4,037.61
Subtask 6- Submittal and FDEP approval of the third quarter O&M Report 10,681.85
Subtask 7- Submittal and FDEP approval of the fourth quarter O&M Report 10,681.85
Subtask 8- Submittal and FDEP approval of paid utility receipts:
Cost Reimbursement = not to exceed $6,600.00 Handling Fee= $240
6,840.00
Subtasks 1 & 9- Submittal and FDEP approval of Annual O&M Report 10,049.03
TOTAL COST $62,369.25
BWC TAFORM 01/18