This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to APTIM Environmental & Infrastructure, LLC for environmental remediation services at the One Stop Cleaners site in Coral Springs, Broward County, Florida. The TA is entered pursuant to Contract Number HW689 and is designated as TA Number DC003B, with an effective completion date of July 26, 2024. The primary parties include the FDEP (represented by Department Project Manager Kelly Crain) and APTIM (represented by Project Manager Eric Kramer).

The scope of work encompasses 12 months of operation and maintenance (O&M) services and groundwater monitoring for a soil vapor extraction (SVE) remedial system, including quarterly O&M reports, semi-annual and annual reporting, utilities, and groundwater sampling activities. The total contract value is $48,466.12, comprised of a fixed unit rate of $44,557.12 and cost reimbursement of $3,909.00 for utilities and associated fees. Payment is contingent upon FDEP approval of deliverables including quarterly monitoring reports, a semi-annual O&M report, an annual O&M report, and utilities invoices. The work is structured across nine subtasks covering project management, four quarters of O&M activities (April 2023 through March 2024), utilities costs, reports, and groundwater sampling. Labor is estimated at 320 hours, with additional expenses for laboratory analysis, equipment, travel, and third-party services including electrical utilities and waste disposal. An existing Access Agreement with the property owner dated July 2, 1999 is in place.

View the file

Other files

File Type Posted
CN-370000-HW689-BF01A.pdf PDF
CN-370000-HW689-BF01C.pdf PDF
CN-370000-HW689-BF1ACO1.pdf PDF
CN-370000-HW689-BIL01CC1.pdf PDF
CN-370000-HW689-BIL01D.pdf PDF
CN-370000-HW689-BIL01E.pdf PDF
CN-370000-HW689-CSS2AC02.pdf PDF
CN-370000-HW689-DC005A.pdf PDF
CN-370000-HW689-DC007A.pdf PDF
CN-370000-HW689-DC008A.pdf PDF
CN-370000-HW689-DC012B.pdf PDF
CN-370000-HW689-DC013A.pdf PDF
CN-370000-HW689-DC015D.pdf PDF
CN-370000-HW689-DC016A.pdf PDF
CN-370000-HW689-DC016B.pdf PDF
CN-370000-HW689-DC020B.pdf PDF
CN-370000-HW689-DC020C.pdf PDF
CN-370000-HW689-DC021B.pdf PDF
CN-370000-HW689-DC022B.pdf PDF
CN-370000-HW689-DC023A.pdf PDF
CN-370000-HW689-DC024C.pdf PDF
CN-370000-HW689-DC024D.pdf PDF
CN-370000-HW689-DC030A.pdf PDF
CN-370000-HW689-DC033A.pdf PDF
CN-370000-HW689-DC03BCO2.pdf PDF
CN-370000-HW689-DC04CCO1.pdf PDF
CN-370000-HW689-DC05CCO3.pdf PDF
CN-370000-HW689-DC06BCO1.pdf PDF
CN-370000-HW689-DC10ACO1.pdf PDF
CN-370000-HW689-DC11CCO2.pdf PDF
CN-370000-HW689-DC11CCO3.pdf PDF
CN-370000-HW689-DC11CCO4.pdf PDF
CN-370000-HW689-DC11DCO1.pdf PDF
CN-370000-HW689-DC13BCO1.pdf PDF
CN-370000-HW689-DC13BCO3.pdf PDF
CN-370000-HW689-DC14BCO2.pdf PDF
CN-370000-HW689-DC15CCO1.pdf PDF
CN-370000-HW689-DC15CCO2.pdf PDF
CN-370000-HW689-DC15DCO1.pdf PDF
CN-370000-HW689-DC15DCO2.pdf PDF
CN-370000-HW689-DC17BCO4.pdf PDF
CN-370000-HW689-DC18BCO2.pdf PDF
CN-370000-HW689-DC20CCO1.pdf PDF
CN-370000-HW689-DC30ACO2.pdf PDF
CN-370000-HW689-DC32ACO1.pdf PDF
CN-370000-HW689-DC35ACO1.pdf PDF
CN-370000-HW689-FIL 3.pdf PDF
CN-370000-HW689-FIL12.pdf PDF
CN-370000-HW689-FIL19.pdf PDF
CN-370000-HW689-FIL20.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW689

DC003B Completion July 26, 2024

This Task Assignment authorizes APTIM to conduct 12 months O&M of the soil vapor extraction system in accordance with the attached Cost Estimate and Scope of Work dated May 26, 2023.

Kelly Crain 850-245-8953 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

APTIM

APTIM

Eric Kramer 407-287-3216

ERIC_4123

3303 University Dr E, Coral Springs, Broward County

One Stop Cleaners

✔ $ 44,557.12 ✔ $ 3,909.00

$ 48,466.12

Scope of Work

Eric Kramer Digitally signed by Eric Kramer Date: 2023.06.13 17:04:52 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2023.06.13 16:42:01 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Quarter 1 O&M Monitoring Report - Subtask 2 07/14/2023

Quarter 2 O&M Monitoring Report; Semi-Annual O&M Report - Subtasks 3 & 4 11/13/2023

Quarter 3 O&M Monitoring Report - Subtask 6 01/12/2024

Quarter 4 O&M Monitoring Report - Subtask 7 04/12/2024

Utilities for Quarters 1-4 - Subtasks 5 & 8 06/24/2024

Annual O&M Report; Project Management - Subtasks 9 & 1 05/24/2024

Upon submittal and FDEP approval of Quarter 1 O&M Monitoring Report - Subtask 2 $ 6,260.37

Upon submittal and FDEP approval of Quarter 2 O&M Monitoring Report;

Semi-Annual O&M Report - Subtasks 3 & 4 $ 10,101.92

Upon submittal and FDEP approval of Quarter 3 O&M Monitoring Report - Subtask 6 $ 6,260.37

Upon submittal and FDEP approval of Quarter 4 O&M Monitoring Report - Subtask 7 $ 10,945.66

Upon submittal and FDEP approval of Air Permit; Paid Utility Invoices Subtasks 5 & 8: Utilities (Cost Plus Fixed Fee) not to exceed $3,909.00 Permit + Utilities Handling Fees: $440.00

$ 4,349.00

Upon submittal and FDEP approval of Annual O&M Report; Project Management - Subtasks 9 & 1 $ 10,548.80

$ 48,466.12

HW689

DC003B

Printed on recycled paper.

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

To:

From:

Date:

HW689 Contract Negotiation File One Stop Cleaners Coral Springs, Broward County

ERIC_4123

Kelly Crain, Project Manager June 7, 2023

Subject: Negotiation Summary

HW689 DC003B

This Task Assignment authorizes APTIM to conduct 12 months of O&M activities in accordance with the May 26, 2023, Scope of Work, and Cost Estimate.

Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.

Subtask 2: Quarter 1 O&M This task includes quarterly O&M services for the remedial system operation including system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample from the remediation system for field screening with a PID and fixed base laboratory analysis.

Subtask 3: Quarter 2 O&M This task includes quarterly O&M services for the remedial system operation including system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample from the remediation system for field screening with a PID and fixed base laboratory analysis.

Subtask 4: Semi-Annual O&M Report This task includes labor hours for the preparation of a semi-annual remedial system O&M report for two quarters of remedial system operation.

Subtask 5: Quarter 1 & 2 Utilities This task includes the estimated cost associated with providing electrical power to the remedial system for the first 6 month period of operation in this Task Assignment. Costs for renewing the air permit with Broward County for operation of the system are also included in this subtask.

Subtask 6: Quarter 3 O&M This task includes quarterly O&M services for the remedial system operation including system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample from the remediation system for field screening with a PID and fixed base laboratory analysis.

Subtask 7: Quarter 4 O&M This task includes quarterly O&M services for the remedial system operation including system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample from the remediation system for field screening with a PID and fixed base laboratory analysis.

Subtask 8: Quarter 3 & 4 Utilities This task includes the estimated cost associated with providing electrical power to the remedial system for the second 6 month period of operation in this Task Assignment.

The annual fee for cellular communications service is $309 will be paid in the last quarter of this semi-annual period of the task assignment.

Subtask 9: Annual O&M Report This task includes labor hours for the preparation of a semi-annual remedial system O&M report for two quarters of remedial system operation.

APTIM confirmed on May 26, 2023, that an Access Agreement with the current real property owner of the One Stop Cleaners (ERIC_4123) site has been executed.

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $48,466.12 with 320 labor hours.

HW689 DC003B

Negotiation Summary

FDEP COST ESTIMATE

Contractor: Aptim Environmental & Infrastructure, LLC Date: 5/26/2023

Task #: HW689 - DC003B ERIC_4123 SubTask 1 Project Management SubTask 6 Qtr 3 Oct-Dec 2023 Site: One Stop Cleaners SubTask 2 Qtr 1 O&M Apr-June 2023 SubTask 7 Qtr 4 Jan-Mar 2024

Activity/Phase: O&M and Annual GW Sampling SubTask 3 Qtr 2 Jul-Sept 2023 SubTask 8 Utilities Qtr 3 & 4 Project Manager: Skylar Schwed/Eric Kramer SubTask 4 Semi-Annual Report SubTask 9 Annual Report

SubTask 5 Utilites Quarters 1 & 2 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$68.41 Project Manager E. Kramer 21 21.2 $68.41 Engineer/Scientist 5 E. Kramer 32 6 6 4 0 6 6 0 4 0 $64.45 Engineer/Scientist 5 G. Roberts 22 0 0 2 0 0 0 0 20 0 $35.31 Engineer/Scientist 2 K. McDonald 100 12 12 25 0 12 15 0 24 0 $27.29 Engineering Technician 2 J. Bell 133 28 28 0 0 28 49 0 0 0 $34.03 Designer 2 S. Ferianc 6 0 0 3 0 0 0 0 3 0 $28.89 Technical Publications Spec H. Vining 6 0 0 3 0 0 0 0 3 0

$0.00 0 0 0 0 0 0 0 0 0 0 Total Hours 320 21 46 46 37 0 46 70 0 54 0

Direct Labor $12,593.97 $1,448.86 $1,598.30 $1,598.30 $1,474.05 $0.00 $1,598.30 $2,277.32 $0.00 $2,598.84 $0.00

Overhead 85.58% $10,777.93 $1,239.93 $1,367.83 $1,367.83 $1,261.49 $0.00 $1,367.83 $1,948.93 $0.00 $2,224.09 $0.00 Gen & Admin 19.38% $2,440.71 $280.79 $309.75 $309.75 $285.67 $0.00 $309.75 $441.34 $0.00 $503.66 $0.00 Fringe 31.96% $4,025.05 $463.06 $510.82 $510.82 $471.11 $0.00 $510.82 $727.83 $0.00 $830.59 $0.00 Total Labor $29,837.66 $3,432.64 $3,786.70 $3,786.70 $3,492.32 $0.00 $3,786.70 $5,395.42 $0.00 $6,157.18 $0.00

Travel Vehicle Rental $1,680.00 $360.00 $360.00 $0.00 $0.00 $360.00 $600.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,680.00 $360.00 $360.00 $0.00 $0.00 $360.00 $600.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $187.00 $0.00 $0.00 $0.00 $0.00 $0.00 $187.00 $0.00 $0.00 $0.00

Utilities $3,909.00 $0.00 $0.00 $0.00 $1,800.00 $0.00 $0.00 $2,109.00 $0.00 $0.00 Broward Co Air Permit $180.00 $0.00 $0.00 $0.00 $180.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $4,276.00 $0.00 $0.00 $0.00 $1,980.00 $0.00 $187.00 $2,109.00 $0.00 $0.00 Handling Fee $278.70 $0.00 $0.00 $0.00 $120.00 $0.00 $18.70 $140.00 $0.00 $0.00 Total Subcontractor Cost $4,554.70 $0.00 $0.00 $0.00 $2,100.00 $0.00 $205.70 $2,249.00 $0.00 $0.00

Laboratory Analytical Costs $1,530.00 $200.00 $200.00 $0.00 $0.00 $200.00 $930.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $550.00 $110.00 $110.00 $0.00 $0.00 $110.00 $220.00 $0.00 $0.00 $0.00 Total Laboratory $2,080.00 $310.00 $310.00 $0.00 $0.00 $310.00 $1,150.00 $0.00 $0.00 $0.00

Field Expenses

FDEP COST ESTIMATE

Contractor: Aptim Environmental & Infrastructure, LLC

Date: 5/26/2023 Task #: HW689 - DC003B ERIC_4123 SubTask 1 Project Management SubTask 6 Qtr 3 Oct-Dec 2023

Site: One Stop Cleaners SubTask 2 Qtr 1 O&M Apr-June 2023 SubTask 7 Qtr 4 Jan-Mar 2024 Activity/Phase: O&M and Annual GW Sampling SubTask 3 Qtr 2 Jul-Sept 2023 SubTask 8 Utilities Qtr 3 & 4

Project Manager: Skylar Schwed/Eric Kramer SubTask 4 Semi-Annual Report SubTask 9 Annual Report SubTask 5 Utilites Quarters 1 & 2 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $560.00 $120.00 $120.00 $0.00 $0.00 $120.00 $200.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $6,670.00 $1,305.00 $1,305.00 $0.00 $0.00 $1,305.00 $2,755.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $100.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $7,330.00 $1,425.00 $1,425.00 $0.00 $0.00 $1,425.00 $3,055.00 $0.00 $0.00 $0.00

Subtotal $45,482.36 $3,432.64 $5,881.70 $5,881.70 $3,492.32 $2,100.00 $5,881.70 $10,406.12 $2,249.00 $6,157.18 $0.00 Completion Fee $2,983.76 $343.26 $378.67 $378.67 $349.23 $0.00 $378.67 $539.54 $0.00 $615.72 $0.00

Total Estimated Cost $48,466.12 $3,775.90 $6,260.37 $6,260.37 $3,841.55 $2,100.00 $6,260.37 $10,945.66 $2,249.00 $6,772.90 $0.00

SITE :

SUBTASK:

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 6

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 1 K. McDonald 12

Engineering Technician 2 J. Bell 28

Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining

TOTAL LABOR 46

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

$0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOC Soil Vapor) $200.00 1 0 $200.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 1 $110.00 Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $310.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 3 $120.00 Construction/O&M Kit $360.00 Day 3 $1,080.00 Construction O&M Supplies $75.00 Day 3 $225.00

TOTAL EQUIPMENT $1,425.00

One Stop Cleaners

Qtr 1 O&M Apr-June 2023 5/26/2023

Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.). Submital of Quarterly reports of monthly O&M data collection sheets. (3 hrs.)

Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x 3 months = 9 hrs). SVE performance evaluation and system optimization (3 hrs).

Monthly Base Work - {Mob (1 hr), Travel Round Trip (2 hrs), SVE O&M (5 hrs) {total = 8 hrs x 3 mo = 24 hrs}. Additional work (each quarter) includes SVE Vacuum Readings and collection of VOC Vapor Sample (total 4 hrs).

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 6

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 1 K. McDonald 12

Engineering Technician 2 J. Bell 28

Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining

TOTAL LABOR 46

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

$0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOC Soil Vapor) $200.00 1 0 $200.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 1 $110.00 Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $310.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 3 $120.00 Construction/O&M Kit $360.00 Day 3 $1,080.00 Construction O&M Supplies $75.00 Day 3 $225.00

TOTAL EQUIPMENT $1,425.00

One Stop Cleaners

Qtr 2 Jul-Sept 2023 5/26/2023

Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.). Submital of Quarterly reports of monthly O&M data collection sheets. (3 hrs.)

Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x 3 months = 9 hrs). SVE performance evaluation and system optimization (3 hrs).

Monthly Base Work - {Mob (1 hr), Travel Round Trip (2 hrs), SVE O&M (5 hrs) {total = 8 hrs x 3 mo = 24 hrs}. Additional work (each quarter) includes SVE Vacuum Readings and collection of VOC Vapor Sample (total 4 hrs).

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 4

Engineer/Scientist 5 G. Roberts 2

Engineer/Scientist 1 K. McDonald 25

Engineering Technician 2 J. Bell Designer 2 S. Ferianc 3 Technical Pub Specialist 3 H. Vining 3

TOTAL LABOR 37

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

$0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00 Construction/O&M Kit $360.00 Day 0 $0.00 Construction O&M Supplies $75.00 Day 0 $0.00

TOTAL EQUIPMENT $0.00

One Stop Cleaners

Semi-Annual Report 5/26/2023

Engineering evaluation of monthly data for first six months system operation, PE seal of Semi-Annual O&M report, evaluate data, develop recommendations and conclusions (4 hrs.)

Data quality evaluation and report documentation

Semi-Annual O&M Report (Document Production)

Preparation of Semi-Annual O&M Report includes preparation of SVE operational tables, calculations, figures, O&M site visit summary, SVE system operation & performance.

Semi-Annual O&M Report (Drafting)

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer Engineer/Scientist 5 G. Roberts Engineer/Scientist 1 K. McDonald Engineering Technician 2 J. Bell Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

FPL-Electrical Service April to September $300.00 Month 6 $1,800.00 Handling fee Electrical $20.00 Month 6 $120.00 Broward County Board of Commissioners (Air Permit Fee) $180.00 each 1 $180.00

TOTAL $2,100.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOC Soil Vapor) $200.00 0 0 $0.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 0 $0.00 Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00 Construction/O&M Kit $360.00 Day 0 $0.00 Construction O&M Supplies $75.00 Day 0 $0.00

TOTAL EQUIPMENT $0.00

Utilites Quarters 1 & 2

One Stop Cleaners

5/26/2023

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 6

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 2 K. McDonald 12

Engineering Technician 2 J. Bell 28

Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining

TOTAL LABOR 46

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOC Soil Vapor) $200.00 1 0 $200.00 EPA Method 8260 (Halos Only) $73.00 0 0 $0.00 EPA Method 8260 (Halos Only/IDW) $73.00 0 $0.00 Sample Shipping (Small cooler) $110.00 1 $110.00 Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $310.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 3 $120.00 Construction/O&M Kit $360.00 Day 3 $1,080.00 Construction O&M Supplies $75.00 Day 3 $225.00

TOTAL EQUIPMENT $1,425.00

One Stop Cleaners

Qtr 3 Oct-Dec 2023 5/26/2023

Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.).

Submittal of quarterly O&M data collections sheets (3 hrs.).

Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x 3 months = 9 hrs). SVE performance evaluation and system optimization (3 hrs).

Monthly Base Work - {Mob (1 hr), Travel Round Trip (2 hrs), SVE O&M (5 hrs) {total = 8 hrs x 3 mo = 24 hrs}. Additional work (each quarter) includes SVE Vacuum Readings and collection of VOC Vapor Sample (Total 4 hrs).

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 6

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 2 K. McDonald 15

Engineering Technician 2 J. Bell 49

Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining

TOTAL LABOR 70

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 5 $600.00

TOTAL VEHICLE $600.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

EnviroServe Non-Haz Soil/Water T&D $187.00 Drum 1 $187.00

TOTAL $187.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOC Soil Vapor) $200.00 1 0 $200.00 EPA Method 8260 (Halos Only) $73.00 9 0 $657.00 EPA Method 8260 (Halos Only/IDW) $73.00 1 $73.00 Sample Shipping (Small cooler) $110.00 2 $220.00 Sample Shipping (large cooler) $150.00 0 $0.00

TOTAL LAB $1,150.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 5 $200.00 Construction/O&M Kit $360.00 Day 5 $1,800.00 Construction O&M Supplies $75.00 Day 5 $375.00 Shallow GW Sampling Kit $290.00 Day 2 $580.00 Drum $100.00 Each 1 $100.00

TOTAL EQUIPMENT $3,055.00

One Stop Cleaners

Qtr 4 Jan-Mar 2024 5/26/2023

Engineering evaluation of monthly data, direct staff engineer for system adjustments (3 hrs.).

Submittal of quarterly O&M data collections sheets (3 hrs.).

Proposed groundwater samples: multi-sampling well MS003 (from 11’, 23’, 38’, 50’ bls); from monitoring wells MW007, MW012, MW016, MW028, MW030. Water level gauging in 29 monitor wells. Quarterly VOC Vapor Samples by TO-15 Modified.

Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x3 months = 9 hrs). SVE performance evaluation and system optimization (6 hrs).

Monthly Base Work - {Mob (1 hr), Travel Round Trip (2 hrs), SVE O&M (5 hrs) {total = 8 hrs x 3 mo = 24 hrs}. Additional work (each quarter) includes SVE Vacuum Readings and collection of VOC Vapor Sample (Total 4 hrs). Groundwater Sampling: Travel Preparation and Mobilization (1 hr), Round trip Travel (2 hrs). Locate and collect water levels and total depth measurements from 29 monitor wells (4 hrs). Preparation and Testing/Calibration of GW Sampling Field Equipment (1 hr/day). Annual groundwater sampling from MS003 (from 11’, 23’, 38’, 50’ bls) and MW007, MW012, MW016, MW028, MW030 at 1 hr per sample (9 hrs), Purge Water Handling (1 hr), Sample Preparation, Chain of custody preparation, Sample Packaging, Delivery to Laboratory (1 hr). Site Restoration and Cleanup (1 hr).

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer Engineer/Scientist 5 G. Roberts Engineer/Scientist 1 K. McDonald Engineering Technician 2 J. Bell Designer 2 S. Ferianc Technical Pub Specialist 3 H. Vining

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

FPL-Electrical Service March to August $300.00 Month 6 $1,800.00 Handling fee Electrical $20.00 Month 6 $120.00 EOS Annual Telemetry fee Telemetry $309.00 annual 1 $309.00 Handling fee Electrical $20.00 Month 1 $20.00

TOTAL $2,249.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00 Construction/O&M Kit $360.00 Day 0 $0.00 Construction O&M Supplies $75.00 Day 0 $0.00

TOTAL EQUIPMENT $0.00

One Stop Cleaners

Utilities Qtr 3 & 4 5/26/2023

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 4

Engineer/Scientist 5 G. Roberts

Engineer/Scientist 2 K. McDonald 24

Designer 2 S. Ferianc 3 Technical Pub Specialist 3 H. Vining 3

TOTAL LABOR 54

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $110.00 Day 0 $0.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 0 $0.00 Day 0 $36.00 Day 0 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

One Stop Cleaners

Annual Report 5/26/2023

Engineering evaluation of monthly data, PE seal of Annual O&M report, evaluate data, develop recommendations and conclusions (4 hrs.)

Assimilate field notes and laboratory report. Prepare GW Elevation and GW Analytical Data figures (4 hrs), Prepare Groundwater Related Data Summary Text (16 hrs).

Annual Groundwater and O&M Report (Document Production)

Preparation of Annual O&M Report (24 hrs which includes preparation of SVE operational tables, calculations, figures, O&M site visit summary, SVE system operation & performance)

Annual Groundwater and O&M Reporting (Drafting)

Proposed Scope of Work O&M Services & Groundwater Monitoring (12 months) Former One Stop Cleaners 3303 University Drive, Coral Springs, Broward County, FL 33065 FAC ID No. 069501160 (ERIC_4123) Aptim Environmental & Infrastructure, Inc. (APTIM) 5/26/22

The following proposed scope of work has been developed for the former One Stop Cleaners site located in Coral Springs, Florida, and was prepared to provide remedial system operation and maintenance (O&M) services and groundwater monitoring activities for a period of 12 months. Attached are the CEF and LOE proposed for the One Stop Cleaners as Task Assignment (TA) request DC003B. The proposed level of effort includes four quarters of O&M activities in support of SVE operation through March 2024.

Subtask 2: This task includes quarterly O&M services (April through June 2023) for the remedial system operation. The services include system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample (June 2023) from the remediation system for field screening with a PID and fixed base laboratory analysis. One quarterly monitoring report will be submitted as a deliverable that will present monthly O&M data for each of the three months per quarter.

Subtask 3: This task includes quarterly O&M services (July through September 2023) for the remedial system operation. The services include system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample (September 2023) from the remediation system for field screening with a PID and fixed base laboratory analysis. One quarterly monitoring report will be submitted as a deliverable that will present monthly O&M data for each of the three months per quarter.

Subtask 4: This task includes preparation of a semi-annual remedial system O&M report (April through September 2023) for two quarters of remedial system operation.

The O&M Report will include quarterly influent vapor analytical results, associated forms summarizing field activities performed in support of the remedial system operation, and conclusions and recommendations for continued system operation.

Subtask 5: This task includes the estimated cost associated with providing electrical power to the remedial system for the first six (6) month period of operation in this Task Assignment. Service cost for the cellular communications is paid annually, and the last invoice was previously paid up to January 2023 in the previous TA. An air license with a two year duration is issued by Broward County for operation of the system. It was renewed in January 2022 and will be renewed again in January 2024, therefore the costs for renewal are included in the task assignment.

Subtask 6: This task includes quarterly O&M services (October through December 2023) for the remedial system operation. The services include system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample (December 2023) from the remediation system for field screening with a PID and fixed base laboratory analysis. One quarterly monitoring report will be submitted as a deliverable that will present monthly O&M data for each of the three months per quarter.

Subtask 7: This task includes quarterly O&M services (January through March 2024) for the remedial system operation. The services include system maintenance, field and system data collection, verification of efficient system operation and collection of one quarterly vapor influent sample (March 2024) from the remediation system for field screening with a PID and fixed base laboratory analysis. One quarterly monitoring report will be submitted as a deliverable that will present monthly O&M data for each of the three months per quarter.

In addition, this task includes annual groundwater sampling. The designated monitoring well set will remain the same as in previous years, originally based on the FDEP October 24, 2011 Deliverable Review Letter, and includes samples from multi-chambered well MS003 (from 11’, 23’, 38’, 50’ bls) and from monitoring wells MW007, MW012, MW016, MW028, and MW030. If additional wells are requested, prior to that time, based on data presented in the currently tasked annual report, the additional sampling will be incorporated into the sampling effort under a change order. Please note that to better accommodate the schedule of the school, all internal sampling activities should be completed during the spring break for students which may shift sampling depending on the school’s 2023-2024 schedule.

Subtask 8: This task includes the estimated cost associated with providing electrical power to the remedial system for the second six (6) month period of operation in this Task Assignment. The annual fee for cellular communications service is $309 will be paid in the last quarter of this semi-annual period of the task assignment.

Subtask 9: Included in this subtask is preparation of an annual report that includes the second six months of SVE operation and maintenance, and annual groundwater sampling. The Annual Groundwater and O&M Report will be prepared summarizing the O&M data and groundwater monitoring data throughout the year of remedial system operation. The O&M Report will include quarterly influent vapor analytical results, associated forms summarizing field activities performed in support of the remedial system operation, and conclusions and recommendations for continued system operation.

A schedule of the proposed O&M, groundwater sampling, and reporting activities follows:

Qtr. 1 O&M Reporting Due Date 7/14/23

Qtr. 2 O&M Reporting Due date 11/13/23

Semi-Annual O&M Report Due Date 11/3/23

Qtr. 3 O&M Reporting Due date 1/12/24

Qtr. 4 O&M Reporting Due date 4/12/24

Annual O&M Report Due date 5/24/24

TA completion Due Date 7/26/24

This LOE and proposed scope of work does not include extensive system diagnostics and repairs. Required diagnostic and repair services will be estimated, approved and funded individually, as required and based on O&M findings.

APTIM proposes to perform this scope of work in accordance with the terms and conditions of the contract executed December 21, 2021 between APTIM Environmental & Infrastructure, LLC and Florida Department of Environmental Protection No. HW689.

APTIM will begin the proposed scope of work upon written authorization. APTIM has an existing Access Agreement in place from the current site owner dated 7/2/99.

If you have any questions, please contact us for clarification.

Item Description Units Unit Price Total

Amount Units Unit Price Total

Amount Units Unit Price Total

Amount

Pickup/Transporation 1 $50.00 $50.00 Included in Drum Disposal Cost 1 $350.00 $350.00 Disposal (soil) NA NA NA Disposal (liquid) 1 $120.00 $120.00 1 $195.00 $195.00 1 $385.00 $385.00 Additional Costs 1 $17.00 $17.00 None 1 $122.00 $122.00 Paperwork Fee None $350.00 1 $150.00 $150.00

Total $187.00 $545.00 $1,007.00

US EcologyEnviroServe Erwin Remediation

IDW Pickup and Disposal Bid Summary One Stop Cleaners and Shoe Repair

3303 University Drive

Coral Springs, Broward County, Florida 33065

FDEP Site ERIC_4123

June 8, 2023

Roberts, Gregg

From: Craig Burns <craigburns@enviroserve.com> Sent: Wednesday, June 7, 2023 4:41 PM To: Roberts, Gregg Cc: Kramer, Eric Subject: APTIM_Request for Quotation for Non-Hazardous IDW T&D (w/PFAS)-One Stop, Coral Springs, FL

EXTERNAL SENDER

Thanks for the email Gregg. See rates in red font below.

Craig Burns www.enviroserve.com

24/7 Emergency Response

(800) 488‐0910

Craig Burns

Account Manager

755 Prairie Industrial Pkwy Mulberry, FL 33860

M 863 327 6289 craigburns@enviroserve.com

From: Roberts, Gregg <Gregg.Roberts@aptim.com> Sent: Wednesday, June 7, 2023 1:49 PM To: Craig Burns <craigburns@enviroserve.com> Cc: Kramer, Eric <Eric.Kramer@aptim.com> Subject: Request for Quotation for Non‐Hazardous IDW T&D (w/PFAS)‐One Stop, Coral Springs, FL

Hello Craig, APTIM is requesting disposal estimates for an FDEP environmental assessment proposal. The scope includes the pick‐up and disposal of one 55‐gal drum of non‐hazardous decontamination fluids and well purge water (liquids) which will Hello Craig, APTIM is requesting disposal estimates for an FDEP environmental assessment proposal. The scope includes the pick-up and disposal of one 55-gal drum of non-hazardous decontamination fluids and well purge water (liquids) which will be generated during upcoming groundwater sampling event. $120/per drum T&D liquids or solids, $50/stop fee for less than 6 drums, 10% FSC to total cost.

Site Info:

One Stop Cleaners and Shoe Repair 3303 North University Drive Coral Springs, Florida 33065 ERIC_4123 (Former FAC ID No. 069501160) DEP/EPA Generator ID Number FLR000031583 APTIM Project Number TBD

Currently – Coral Springs Charter School (3205 North University Drive)

The IDW transportation and disposal estimate is for non-hazardous waste. The One Stop Cleaners site is a former drycleaning facility, which is being monitored for drycleaning contaminants in groundwater (VOHs). The liquid IDW will be sampled for volatile organic halogens (VOHs) by EPA Method 8260.

It should be noted that the site groundwater was recently tested for the presence of PFAS constituents and results for PFOA and PFAS ranged from 16 to 94 ng/L and 120 to 210 ng/L, respectively. These results (samples collected 4/17/23) will be submitted for characterization of the waste, , if necessary. If an actual IDW PFAS sample would be required, or if you would require any additional analysis for the waste characterization, please indicate so in your response.

I don’t need a formal proposal for the disposal of the drums, an email response would be acceptable. Please include all other fees and costs associated with the drum disposal (transportation fees, drum quantity fees, etc.). If you could, please provide a quote by close of business Friday June 9th, I would greatly appreciate it.

Please let me know if you have any questions.

Gregg

GREGG ROBERTS, PG

Project Manager

APTIM | ENVIRONMENT & SUSTAINABILITY

O 813 612 3687 M 863 670 0215

E gregg.roberts@aptim.com

725 US Highway 301 South Tampa, FL 33619

APTIM.com

Roberts, Gregg

From: Robert Donado <robert@erwinremediation.com> Sent: Wednesday, June 7, 2023 1:57 PM To: Roberts, Gregg Cc: Kramer, Eric Subject: Re: Request for Quotation for Non-Hazardous IDW T&D (w/PFAS)-One Stop, Coral Springs, FL

EXTERNAL SENDER

Gregg, The cost for transport and disposal of one 55‐gallon drum of PFAS/PFOS contaminated water is $195.00 drum along with a profiling fee of $350.00. Total will be $545.00.

The PFAS laboratory results from 4/17/2023 can be used for the profiling. VOHs will be all we will need.

Thanks, Robert Donado robert@erwinremediation.com Erwin Remediation, Inc.

PO Box 884

(850) 466-2358 Gulf Breeze, FL 32562

On Wed, Jun 7, 2023 at 12:48 PM Roberts, Gregg <Gregg.Roberts@aptim.com> wrote:

Hello Robert, APTIM is requesting disposal estimates for an FDEP environmental assessment proposal. The scope includes the pick-up and disposal of one 55-gal drum of non-hazardous decontamination fluids and well purge water (liquids) which will be generated during upcoming groundwater sampling event.

Site Info:

One Stop Cleaners and Shoe Repair

3303 North University Drive

Coral Springs, Florida 33065

ERIC_4123 (Former FAC ID No. 069501160)

DEP/EPA Generator ID Number FLR000031583

APTIM Project Number TBD

Currently – Coral Springs Charter School (3205 North University Drive)

The IDW transportation and disposal estimate is for non-hazardous waste. The One Stop Cleaners site is a former drycleaning facility, which is being monitored for drycleaning contaminants in groundwater (VOHs). The liquid IDW will be sampled for volatile organic halogens (VOHs) by EPA Method 8260.

It should be noted that the site groundwater was recently tested for the presence of PFAS constituents and results for PFOA and PFAS ranged from 16 to 94 ng/L and 120 to 210 ng/L, respectively. These results (samples collected 4/17/23) will be submitted for characterization of the waste, if necessary. If an actual IDW PFAS sample would be required, or if you would require any additional analysis for the waste characterization, please indicate so in your response.

I don’t need a formal proposal for the disposal of the drums, an email response would be acceptable. Please include all other fees and costs associated with the drum disposal (transportation fees, drum quantity fees, etc.). If you could, please provide a quote by close of business Friday June 9th, I would greatly appreciate it.

Please let me know if you have any questions.

Gregg

GREGG ROBERTS, PG

Project Manager

APTIM | ENVIRONMENT & SUSTAINABILITY

O 813 612 3687

M 863 670 0215

E gregg.roberts@aptim.com

725 US Highway 301 South

Tampa, FL 33619

APTIM.com

PROPOSAL#: MS-060723-TAM

CUSTOMER: Aptim

ADDRESS: 725 US Highway 301 South

Tampa, FL 33619

PHONE: (813) 612-3687

EMAIL: gregg.roberts@aptim.com

June 7th, 2023

Dear Gregg Roberts:

I appreciate this opportunity to provide environmental management solutions on behalf of US Ecology Tampa, Inc.

(“Contractor”). To follow up on our discussion, I am pleased to present this proposal.

Contractor’s parent US Ecology, Inc., together with its subsidiaries, is a leading North American provider of environmental services to commercial and government entities. We address the complex waste management needs of our customers by offering treatment, disposal, and recycling of hazardous and radioactive waste, as well as a wide range of complementary field and industrial services. US Ecology’s 60 years of experience and focus on safety, environmental compliance, and customer service, enable us to reliably and cost effectively meet the needs of our customers.

We understand you need a professional, integrated transportation, treatment, and disposal solution, and we have designed this project to meet your needs. Our best-in-class customer service leverages our industry leading capabilities and will allow us to deliver the strongest solution available in the market today. We look forward to supporting you on this project!

This proposal is valid for 90 days, and is subject to Contractor’s terms and conditions included herein, which you agree will apply to all services. Upon the expiration of this proposal, this offer to perform services, and the specified prices, are subject to change or withdrawal. When a waste approval is granted, you will receive a price confirmation document further specifying the applicable pricing and billing unit. Please indicate your acceptance of this proposal by signing below.

SCOPE OF WORK:

US Ecology’s Tampa Field Services group is pleased to submit this proposal to provide the labor, materials and equipment necessary to properly package, transport and dispose of designated waste materials in Coral Springs, FL .

USE proposes to perform the following work:

• Properly segregate and label all designated waste materials in accordance with all applicable regulations (as necessary).

• Provide all necessary shipping documents and transport the material in licensed vehicles

• Customer/Generator prepared materials must be in DOT-shippable containers.

• Pricing applicable on all containers (percentage of 55-gallon drum price): 5 – 15 gallons 35%; 16 – 30 gallons

75%; 31 – 55 gallons 100%; 56 – 85 gallons %150; CYB 300%

US Ecology Tampa, Inc.

Aptim

Signature

Signature

Print Name

Print Name

Title

Title

Date

Date

PROPOSAL

TREATMENT TYPE:

Waste Services – Disposal of IDW PFAS Drums from Coral Springs, FL

Pricing is pending an approved profile and acceptance for waste verification.

RATES:

Description Treat Group Size Unit Rate Quantity Minimums Ext Cost

PFAS Liquids / Solids 1281 55 Gal $321.00 1 $385.20

Paperwork Fee – Per Project, Not Drum Project $150.00 1 $150.00

Environmental Insurance Recovery Fee* 20%

*Included in disposal cost above

Estimated Disposal Subtotal $535.20

Transportation - Coral Springs, FL to Tampa, FL

Size Unit Rate Quantity Ext Cost

Transportation Minimum $350.00 $350.00

Container Rate 55 Gal $53.00 1

Fuel Surcharge - Varies Weekly 35% $122.50

Demurrage - After 1 Hour Free Hour $125.00

Estimated Transportation Total $472.50

Estimated Project Total $1,007.70

Thank you, Marco Sapone Account Executive – Florida US ecology marco.sapone@usecology.com c: (386) 530-9891 mailto:marco.sapone@usecology.com

File details come from the government source that posted it. Updated .