About this file

This document is a Task Assignment Change Order (TACO #1) issued by the State of Florida Department of Environmental Protection (DEP) to APTIM Environmental & Infrastructure, LLC for remedial system operations and maintenance at Oasis Cleaners, a contaminated site located at 3210 1st Street West, Bradenton, Manatee County, Florida. The change order amends the original Task Assignment DC015D under Contract HW689, with project management oversight provided by DEP Project Manager Nicole Knutson and contractor project manager Eric Kramer.

The change order extends the task completion date from March 20, 2026, to August 28, 2026, accounting for delays in Soil Vapor Extraction (SVE) startup due to electrical connection issues. The total task value remains unchanged at $47,434.97, comprised of a fixed unit rate of $42,934.97 for 12 months of operations and maintenance services plus $4,500.00 in cost reimbursement for utilities ($375 per month plus a $20 monthly handling fee). The deliverables include quarterly and semi-annual operations and maintenance reporting, utilities billing, and annual reporting with project management, with specific milestone due dates extending through June 26, 2026. The invoice schedule is tied to DEP approval of completed deliverables, with individual invoice amounts ranging from $2,370.00 to $8,879.16 based on approved subtasks.

View the file

Other files

File Type Posted
CN-370000-HW689-BF01A.pdf.crdownload CRDOWNLOAD file
CN-370000-HW689-BF01D.pdf PDF
CN-370000-HW689-BIL01G.pdf PDF
CN-370000-HW689-BIL1BCO1.pdf PDF
CN-370000-HW689-BIL1BCO3.pdf PDF
CN-370000-HW689-DC001A.pdf PDF
CN-370000-HW689-DC001B.pdf PDF
CN-370000-HW689-DC001C.pdf PDF
CN-370000-HW689-DC001D.pdf PDF
CN-370000-HW689-DC002A.pdf PDF
CN-370000-HW689-DC003B.pdf PDF
CN-370000-HW689-DC004A.pdf PDF
CN-370000-HW689-DC004B.pdf PDF
CN-370000-HW689-DC005C.pdf PDF
CN-370000-HW689-DC006A.pdf PDF
CN-370000-HW689-DC008B.pdf PDF
CN-370000-HW689-DC010B.pdf PDF
CN-370000-HW689-DC011B.pdf PDF
CN-370000-HW689-DC011D.pdf PDF
CN-370000-HW689-DC012A.pdf PDF
CN-370000-HW689-DC013B.pdf PDF
CN-370000-HW689-DC014B.pdf PDF
CN-370000-HW689-DC015E.pdf PDF
CN-370000-HW689-DC019A.pdf PDF
CN-370000-HW689-DC019B.pdf PDF
CN-370000-HW689-DC024A.pdf PDF
CN-370000-HW689-DC025A.pdf PDF
CN-370000-HW689-DC028A.pdf PDF
CN-370000-HW689-DC029A.pdf PDF
CN-370000-HW689-DC02ACO1.pdf PDF
CN-370000-HW689-DC031A.pdf PDF
CN-370000-HW689-DC034A.pdf PDF
CN-370000-HW689-DC035A.pdf PDF
CN-370000-HW689-DC037A.pdf PDF
CN-370000-HW689-DC03ACO1.pdf PDF
CN-370000-HW689-DC03ACO2.pdf PDF
CN-370000-HW689-DC03CC01.pdf PDF
CN-370000-HW689-DC03DCO1.pdf PDF
CN-370000-HW689-DC05CCO1.pdf PDF
CN-370000-HW689-DC05DCO1.pdf PDF
CN-370000-HW689-DC08CCO1.pdf PDF
CN-370000-HW689-DC08CCO2.pdf PDF
CN-370000-HW689-DC08CCO3.pdf PDF
CN-370000-HW689-DC11CCO5.pdf PDF
CN-370000-HW689-DC11CCO6.pdf PDF
CN-370000-HW689-DC12BCO4.pdf PDF
CN-370000-HW689-DC13BCO2.pdf PDF
CN-370000-HW689-DC13BCO4.pdf PDF
CN-370000-HW689-DC13BCO7.pdf PDF
CN-370000-HW689-DC16CCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

DC015D 1 HW689

Nicole Knutson 850-245-8763 Contractor APTIM Environmental & Infrastructure, LLC Contractor

Contractor Eric Kramer Contractor 407-287-3216

ERIC_4885

Oasis Cleaners

✔ $ 42,934.97 $ 42,934.97 ✔ $ 4,500.00 $ 4,500.00

$ 47,434.97 $ 47,434.97 Completion

✔ Completion 03/20/2026 08/28/2026 161

✔ 1 1 1

Contractor

Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2025.09.19 11:22:29 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2025.09.18 10:58:49 -04'00'

This time extension accounts for delays in SVE startup due to electrical connection delays.

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number: HW689 Task Assignment #: DC015D

Change Order #: 1

Deliverables:

Deliverable Deliverable Due Date Subtask 2: Qtr. 1 O&M Reporting 9/12/2025

Subtask 3: Qtr. 2 O&M Reporting 12/12/2025

Subtask 4: Utilities for first 6 months 12/12/2025

Subtask 5: Semi-Annual O&M Reporting 1/16/2026

Subtask 6: Qtr. 3 O&M Reporting 3/13/2026

Subtask 7: Qtr. 4 O&M Reporting 6/19/2026

Subtask 8: Utilities for last 6 months 6/19/2026

Subtasks 9 & 1: Annual O&M Reporting & PM 6/26/2026

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

DEP Approval of Subtask 2: Qtr. 1 O&M Reporting $7,444.55

DEP Approval of Subtask 3: Qtr. 2 O&M Reporting $7,444.55

Upon receipt of Subtask 4: Utilities for first 6 months Cost Reimbursement = $375/mo plus Handling Fee = $20/mo $2,370.00

DEP Approval of Subtask 5: Semi-Annual O&M Reporting $4,037.61

DEP Approval of Subtask 6: Qtr. 3 O&M Reporting $7,444.55

DEP Approval of Subtask 7: Qtr. 4 O&M Reporting $7,444.55

Upon receipt of Subtask 8: Utilities for last 6 months Cost Reimbursement = $375/mo plus Handling Fee = $20/mo $2,370.00

DEP Approval of Subtasks 9 & 1: Annual O&M Reporting & PM $8,879.16

TOTAL COST $47,434.97

BWC TAFORM 01_18

Memorandum

TO: ERIC_4885

Oasis Cleaners

FROM: Nicole Knutson, Project Manager

SUBJECT: Negotiation Summary

HW689 DC015D-1

DATE: September 17, 2025

This time extension accounts for delays in SVE startup due to electrical connection delays. Total task amount remains $47,434.97. APTIM’s time, labor, and subcontractor costs for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable due date has been extended from January 30, 2026 to June 26, 2026. Task completion date has been extended from March 20, 2026 to August 28, 2026.

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW689

DC015D Completion March 20, 2026

APTIM will perform 12 months of O&M of the remedial system at Oasis Cleaners in Bradenton, Manatee County.

Nicole Knutson 850-245-8763 Contractor APTIM Environmental & Infrastructure, LLC Contractor

Contractor Eric Kramer Contractor 407 287 3216

ERIC_4885

3210 1st Street West, Bradenton, Manatee County

Oasis Cleaners

Contractor Contractor

✔ $ 42,934.97 ✔ $ 4,500.00

$ 47,434.97

Scope of Work

APTIM Environmental & Infrastructure, LLC Contractor

Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2024.11.21 16:28:32 -05'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2024.11.21 14:53:41 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number: HW689 Task Assignment #: DC015D

Deliverables:

Deliverable Deliverable Due Date Subtask 2: Qtr. 1 O&M Reporting

25-Apr-25

Subtask 3: Qtr. 2 O&M Reporting 25-Jul-25

Subtask 4: Utilities for first 6 months 25-Sep-25

Subtask 5: Semi-Annual O&M Reporting 8-Aug-25

Subtask 6: Qtr. 3 O&M Reporting 24-Oct-25

Subtask 7: Qtr. 4 O&M Reporting 23-Jan-26

Subtask 8: Utilities for last 6 months 23-Feb-26

Subtasks 9 & 1: Annual O&M Reporting & PM 30-Jan-26

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced DEP Approval of Subtask 2: Qtr. 1 O&M Reporting

$7,444.55

DEP Approval of Subtask 3: Qtr. 2 O&M Reporting $7,444.55

Upon receipt of Subtask 4: Utilities for first 6 months Cost Reimbursement = $375/mo plus Handling Fee = $20/mo $2,370.00

DEP Approval of Subtask 5: Semi-Annual O&M Reporting $4,037.61

DEP Approval of Subtask 6: Qtr. 3 O&M Reporting $7,444.55

DEP Approval of Subtask 7: Qtr. 4 O&M Reporting $7,444.55

Upon receipt of Subtask 8: Utilities for last 6 months Cost Reimbursement = $375/mo plus Handling Fee = $20/mo $2,370.00

DEP Approval of Subtasks 9 & 1: Annual O&M Reporting & PM $8,879.16